Kouroussa Guinea Update

Civil Works Begin & Material High-Grade Drilling Assays Received

Hummingbird Resources plc (AIM: HUM) provides an update on t he Company's mine development progress and results from further assays of the 2021 Resources and Reserves infill drilling programme at the Kouroussa Gold Mine ("Kouroussa" or "the Project") in Guinea .

For the full release, including photos and drilling graphics, please follow the link

http://www.rns-pdf.londonstockexchange.com/rns/3929H_1-2022-4-5.pdf

Further, updated video footage of the Kouroussa development is available here , and an updated interview with COO, Anthony Köcken on the overall progress at Kouroussa, can be viewed here .

Kouroussa Update:

The development and construction of Kouroussa continues to advance rapidly and remains on track to achieve the scheduled first gold pour by the end of Q2 2023. The construction update is as follows:

   --      Civil and construction works: 

o Civil works have begun, and earthworks are nearing completion at the processing plant with mine camp site areas to then allow for cement foundation works to begin

o Foundation concrete and steel reinforcement work is taking place for the CIL tanks installation

o Mine camp for construction personnel is now operational, allowing the Company to have more construction personnel on site versus housed in the local areas, with over 350 construction, administrative and security personnel in place for the overall construction process

   --      Processing plant: 

o Fabrication of the CIL tanks have commenced on-site and are rapidly advancing towards completion

o Structural, mechanical, and piping works will begin following the completion of foundation works at the process plant area

   --      Long lead items, contracts, and community engagement: 

o Further long lead items have been purchased, including apron feeders, jaw crusher, SAG mill, cyclone cluster and agitators

o Construction equipment, tooling, machinery, personnel, and consumables continue to arrive on-site and are in position for the next phase of the overall build process

o Power plant and mining contractor contracts are in the final stages of negotiation and are expected to be awarded soon

o Detailed community engagement is taking place with our on-site health, safety, environmental and community ("HSEC") teams

Kouroussa Drilling Highlights :

Hummingbird has received assay results on a further 86 Reverse Circulation ("RC") and 12 diamond holes on the high-grade Koekoe ("KK") deposit, delivering approximately 9,900 meters ("m") of the Company's c.24,000m infill 2021 drilling programme. The focus of this infill drilling programme has been to convert current in-pit Inferred material to Indicated and build upon the already extensive historical drilling to expand Kouroussa's life of mine and overall Reserves base.

The Company is awaiting the final c.3,600m of assays, which are expected to be received soon and will conclude the 2021 Kouroussa drilling results to be received.

   --      Notable drill results from the KK deposit include: 

o 3m @ 18.63 g/t from 27m (KRC1953)

o 7m @ 2.98 g/t from 36m (KRC2003)

o 11m @ 5.62 g/t from 64m (KRC2036)

o 3m @ 34.84 g/t from 51m (KRC2041)

o 1m @ 47.60 g/t from 152m (KRC2042) *

o 9m @ 4.55 g/t from 34m (KRC2044)

o 2m @ 9.65 g/t from 120m (KRCD1886)

o 8.6m @ 6.31 g/t from 107.6m (KRCD1891)

o 7m @ 9.83 g/t from 101m (KRCD1896)

o 12.6m @ 5.11 g/t from 66.45m (KRCD1898)

*Note that Hole KRC2042 ended with mineralisation ongoing

These and previous results continue to show the significant gold endowment at Kouroussa, with multiple high-grade zones that remain open.

These assays, alongside additional results from the Kouroussa and Yanfolila drilling programmes will feed into the updated Company 2022 Resources and Reserves statement that is expected to be released in Q2 2022.

Dan Betts, CEO of Hummingbird Resources, commented:

"We are rapidly advancing into the next phase of the Kouroussa build process with civil works now underway. We remain focused on delivering Kouroussa on schedule and on budget for a first gold pour by the end of Q2 2023, which will then more than double our current production profile.

Our 2021 Kouroussa drilling programme continues to deliver results that highlight the significant gold endowment we have at Kouroussa. Our geology team has also identified thicker mineralisation zones and shallower dipping westerly zones than originally believed, which is a positive for future mining at Kouroussa. These results continue to be analysed and incorporated into our updated Company Resources and Reserves statement, which is expected to be released at the end of Q2."

Anthony Köcken, COO of Hummingbird Resources, commented:

"Our Kouroussa construction team is working well in advancing the Project towards the first gold pour. We are now in the civil work construction phase, which involves a new level of technical expertise that our teams are now bringing into the overall process. The awarding of power and mining contractor contracts is nearing finalisation, which will also be a key milestone for Kouroussa, allowing key infrastructure and mining processes to begin."

Kouroussa Drilling Results Summary

The 2021 Kouroussa infill drilling campaign was completed in December, and all RC assay results have now been delivered, as we await the final diamond drill hole assays of c.3,600m to be received and analysed.

The objectives of this infill drilling campaign have been to convert current Inferred Mineral Resources within the KK open pits to Indicated Mineral Resources and to include the multiple mineralisation zones not contained within the current grade domains. Drilling was targeted at the deeper inferred material within the main KK pit, extensions of the current Mineral Reserve Estimate, shallow mineralised zones and initial testing of underground Mineral Resource potential.

Given the results as seen from today's release, and those of the other four Kouroussa drilling results we have released, as well as the historical drilling results of over 300,000m, the Company believes that these objectives have been achieved. Our geology team and external consultants are busy collating the 2021 drilling data to be included in our upcoming Company Resources and Reserves statement, scheduled for release in late Q2 2022.

Initial observations from this infill drilling programme indicate that there are two predominant orientations of mineralisation, namely the subvertical domains around the main shear zones and flatter lying domains to the west of the main shear zone. The main shear zone domain in Sanu Filanan appears to be wider, and the westerly zones shallower dipping than modelled in the original interpretation. Much of the mineralisation appears to be open at depth. The deepest drill holes were c.200m in length and several drill holes ended in further mineralisation, which is encouraging.

Furthermore, the results show there is significant exploration potential along strike and down plunge with several targets generated for future exploration to expand the current Mineral Resource. There are also Inferred Mineral Resources at deposits X Vein and Bag Farm Junction, which have historical drilling completed, but no drilling has been completed by Hummingbird to date.

Koekoe selected drill results

 
 Hole ID     Depth From (m)   Depth To (m)   Intercept Description 
 KRC1953     27               30             3m @ 18.63 g/t 
            ---------------  -------------  ---------------------- 
 KRC1955     17               22             5m @ 2.99 g/t 
            ---------------  -------------  ---------------------- 
 KRC1969     26               32             6m @ 1.94 g/t 
            ---------------  -------------  ---------------------- 
 KRC1971     18               23             5m @ 2.16 g/t 
            ---------------  -------------  ---------------------- 
 KRC1976     3                4              1m @ 19.13 g/t 
            ---------------  -------------  ---------------------- 
 KRC1989     12               23             11m @ 1.36 g/t 
            ---------------  -------------  ---------------------- 
 KRC2002     58               59             1m @ 11.10 g/t 
            ---------------  -------------  ---------------------- 
 KRC2003     36               43             7m @ 2.98 g/t 
            ---------------  -------------  ---------------------- 
 KRC2005     30               34             4m @ 2.71 g/t 
            ---------------  -------------  ---------------------- 
 KRC2005     82               83             1m @ 12.10 g/t 
            ---------------  -------------  ---------------------- 
 KRC2008     51               54             3m @ 4.03 g/t 
            ---------------  -------------  ---------------------- 
 KRC2010     41               45             4m @ 3.11 g/t 
            ---------------  -------------  ---------------------- 
 KRC2017     19               25             6m @ 3.01 g/t 
            ---------------  -------------  ---------------------- 
 KRC2017     28               32             4m @ 3.46 g/t 
            ---------------  -------------  ---------------------- 
 KRC2027     28               29             1m @ 11.30 g/t 
            ---------------  -------------  ---------------------- 
 KRC2028     69               74             5m @ 2.42 g/t 
            ---------------  -------------  ---------------------- 
 KRC2034     28               37             9m @ 1.86 g/t 
            ---------------  -------------  ---------------------- 
 KRC2036     34               40             6m @ 3.13 g/t 
            ---------------  -------------  ---------------------- 
 KRC2036     64               75             11m @ 5.62 g/t 
            ---------------  -------------  ---------------------- 
 KRC2037     87               88             1m @ 18.50 g/t 
            ---------------  -------------  ---------------------- 
 KRC2041     51               54             3m @ 34.84 g/t 
            ---------------  -------------  ---------------------- 
 KRC2042     152              153            1m @ 47.60 g/t 
            ---------------  -------------  ---------------------- 
 KRC2044     34               43             9m @ 4.55 g/t 
            ---------------  -------------  ---------------------- 
 KRCD1886    120              122            2m @ 9.65 g/t 
            ---------------  -------------  ---------------------- 
 KRCD1887    26.38            31             4.6m @ 2.29 g/t 
            ---------------  -------------  ---------------------- 
 KRCD1888    134              140            6m @ 2.99 g/t 
            ---------------  -------------  ---------------------- 
 KRCD1888    143              147.3          4.3m @ 3.67 g/t 
            ---------------  -------------  ---------------------- 
 KRCD1891    107.6            116.2          8.6m @ 6.31 g/t 
            ---------------  -------------  ---------------------- 
 KRCD1895    66.5             68             1.5m @ 7.07 g/t 
            ---------------  -------------  ---------------------- 
 KRCD1896    101              108.03         7m @ 9.83 g/t 
            ---------------  -------------  ---------------------- 
 KRCD1898    66.45            79             12.6m @ 5.11 g/t 
            ---------------  -------------  ---------------------- 
 

Trigger 1 g/t, 1m minimum interval, 2m maximum internal waste

Koekoe summary of previously released Hummingbird selected drill results

 
 Hole ID       Depth From (m)   Depth To (m)   Intercept Description 
 KRC1754       27               47             20m @ 7.96 g/t 
              ---------------  -------------  ---------------------- 
 KRC1776       82               87             5m @ 37.11 g/t 
              ---------------  -------------  ---------------------- 
 KRC1778       96               101            5m @ 19.02 g/t 
              ---------------  -------------  ---------------------- 
 KRC1780       56               63             7m @ 8.71 g/t 
              ---------------  -------------  ---------------------- 
 KRC1831       57               63             6m @ 18.80 g/t 
              ---------------  -------------  ---------------------- 
 KRC1839       74               92             18m @ 7.37 g/t 
              ---------------  -------------  ---------------------- 
 KRC1840       46               64             18m @ 4.12 g/t 
              ---------------  -------------  ---------------------- 
 KRC1844       65               69             4m @ 53.84 g/t 
              ---------------  -------------  ---------------------- 
 KRC1844       133              140            7m @ 9.78 g/t 
              ---------------  -------------  ---------------------- 
 KRC1849       55               69             14m @ 21.85 g/t 
              ---------------  -------------  ---------------------- 
 KRC1853       52               61             9m @ 6.74 g/t 
              ---------------  -------------  ---------------------- 
 KRC1853       93               104            11m @ 5.25 g/t 
              ---------------  -------------  ---------------------- 
 KRC1856       90               99             9m @ 36.35 g/t 
              ---------------  -------------  ---------------------- 
 KRC1857       49               57             8m @ 9.35 g/t 
              ---------------  -------------  ---------------------- 
 KRC1864       95               103            8m @ 7.77 g/t 
              ---------------  -------------  ---------------------- 
 KRC1866       76               104            28m @ 9.35 g/t 
              ---------------  -------------  ---------------------- 
 KRC1903       96               105            9m @ 30.58 g/t 
              ---------------  -------------  ---------------------- 
 KRC1917       92               99             7m @ 10.14 g/t 
              ---------------  -------------  ---------------------- 
 KRC1921       89               99             10m @ 7.34 g/t 
              ---------------  -------------  ---------------------- 
 KRC1924       53               63             10m @ 10.26 g/t 
              ---------------  -------------  ---------------------- 
 KRC1941       11               19             8m @ 7.50 g/t 
              ---------------  -------------  ---------------------- 
 KRC1953       27               30             3m @ 18.63 g/t 
              ---------------  -------------  ---------------------- 
 KRC2041       51               54             3m @ 34.84 g/t 
              ---------------  -------------  ---------------------- 
 KRCD1729A*    84               114            30m @ 64.31 g/t 
              ---------------  -------------  ---------------------- 
 KRCD1728*     135              147            12m @ 5.39 g/t 
              ---------------  -------------  ---------------------- 
 KRCD1869      123.6            126            2.4m @ 22.58 g/t 
              ---------------  -------------  ---------------------- 
 KRCD1873      28               52             24m @ 5.33 g/t 
              ---------------  -------------  ---------------------- 
 KRCD1880      94.1             98.8           4.7m @ 15.82 g/t 
              ---------------  -------------  ---------------------- 
 KRCD1883      147              152.6          5.6m @ 9.31 g/t 
              ---------------  -------------  ---------------------- 
 KRCD1884      12.9             23.9           11m @ 5.35 g/t 
              ---------------  -------------  ---------------------- 
 KRCD1884      36               41             5m @ 11.11 g/t 
              ---------------  -------------  ---------------------- 
 KRCD1891      107.6            116.2          8.6m @ 6.31 g/t 
              ---------------  -------------  ---------------------- 
 KRCD1896      101              108            7m @ 9.83 g/t 
              ---------------  -------------  ---------------------- 
 KRCD1898      66.5             79             12.6m @ 5.11 g/t 
              ---------------  -------------  ---------------------- 
 

* Downhole length of metallurgical hole intercept (not true width)

Trigger 1 g/t, 1m minimum interval, 2m maximum internal waste

Qualified Person Review:

David Muir has reviewed and approved the technical information contained within this announcement in his capacity as a Qualified Person, as required under the AIM Rules for Companies. David is the Group Database Manager for Hummingbird, and is a "Competent Person", according to the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves ("JORC Code, 2012 Edition") and is a member of good standing with the Australian Institute of Geoscientists (AIG).

Notes to Editors:

Hummingbird Resources (AIM: HUM) is a multi-asset, multi-jurisdiction gold production, development and exploration Company, a member of the World Gold Council and a founding member of Single Mine Origin ( singlemineorigin.com ). The Company currently has two core gold projects, the operational Yanfolila Gold Mine in Mali, and the Kouroussa Gold Mine in Guinea, which will more than double current gold production when in production, scheduled for first gold pour end of Q2 2023. Further, the Company has a controlling interest in the Dugbe Gold Project in Liberia that is being developed by Pasofino Gold Limited through an earn-in agreement. Our vision is to continue to grow our asset base, producing profitable ounces while placing our Environmental, Social & Governance ('ESG') policies and practices at the heart of all we do.

For further information, please visit hummingbirdresources.co.uk or subscribe to our investor releases via investor email alerts

 
 Daniel Betts, CEO               Hummingbird Resources plc   Tel: +44 (0) 20 7409 6660 
  Thomas Hill, FD 
  Anthony Köcken, COO 
  Edward Montgomery, CSO & ESG 
 James Spinney                   Strand Hanson Limited       Tel: +44 (0) 20 7409 3494 
  Ritchie Balmer                  Nominated Adviser 
                                --------------------------  ---------------------------- 
 James Asensio                   Canaccord Genuity Limited   Tel: +44 (0) 20 7523 8000 
  Thomas Diehl                    Broker 
                                --------------------------  ---------------------------- 
 Bobby Morse                     Buchanan                    Tel: +44 (0) 20 7466 5000 
  Ariadna Peretz                  Financial PR/IR             Email: HUM@buchanan.uk.com 
  James Husband 
                                --------------------------  ---------------------------- 
 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.

END

UPDEAPLSEEEAEFA

(END) Dow Jones Newswires

April 06, 2022 02:01 ET (06:01 GMT)

Hummingbird Resources (LSE:HUM)
Historical Stock Chart
From Aug 2024 to Sep 2024 Click Here for more Hummingbird Resources Charts.
Hummingbird Resources (LSE:HUM)
Historical Stock Chart
From Sep 2023 to Sep 2024 Click Here for more Hummingbird Resources Charts.