W Resources Plc
("W" or the "Company")
Jig and Mill Contract Including Vendor Finance Awarded to
allmineral
W Resources Plc (AIM:WRES), the tungsten, copper and gold
exploration and development company with assets in Spain and
Portugal, has awarded the Design and Construct Contract for the La
Parrilla Jig and Mill to allmineral Aufbereitungstechnik GmbH &
Co. KG of Germany ("allmineral") at a contract price of EUR4.98m.
allmineral is providing vendor finance for just under 50% of the
contract price on very competitive terms.
The Jig and Mill is a core component of the La Parrilla plant
infrastructure which upgrades the crushed ore by a factor of 1.5 to
achieve an expected 91% metal recovery prior to concentration by
efficiently rejecting 55% of Run of Mine ("ROM") feed at coarse
sizes. It is designed to accept feed at a rate of 350tph and has
been designed to allow rapid expansion of La Parrilla from 1.95mtpa
to 3.5mtpa ROM.
The twin jig and twin mill circuit provides flexibility for
operations going forwards. The design ensures robust metallurgical
efficiency with the ability to scalp out barren ore from the feed
prior to jigging and also to provide finer liberation sizes prior
to final gravity concentration, if required. Unique to the design,
100% of the fines are collected in the jig circuit and pumped to
the gravity circuit for recovery and not discarded to tailings.
Michael Masterman, Chairman of W Resources commented: "The award
of the Jig and Mill contract is a critical component of the
development of the large scale La Parrilla Tungsten and Tin mine.
We are very pleased to award this contract to allmineral under
attractive finance terms. We have built a cooperative relationship
to agree both the technical and commercial terms and we look
forward to completing construction."
As previously announced on 19 January 2017, W has applied for
grants from the Extremadura Regional Government in Spain and this
process is ongoing in line with the application process.
Engineering, procurement and financing of the other La Parrilla
plant components is advancing and we will update the market with
each material development.
Enquiries:
W Resources Plc Grant Thornton UK LLP
Michael Masterman Colin Aaronson / Harrison
T: +44 (0) 20 7193 7463 Clarke
www.wresources.co.uk T: +44 (0) 20 7383 5100
SI Capital Gable Communications
Andy Thacker / Nick Emerson Justine James
T: +44 (0) 1483 413500 T: +44 (0) 20 7193 7463
www.sicapital.co.uk M: +44 (0) 7525 324431
The information contained within this RNS is considered to be
inside information, for the purposes of Article 7 of EU Regulation
596/2014, prior to its release.
This information is provided by RNS
The company news service from the London Stock Exchange
END
CNTUAURRBBASAUR
(END) Dow Jones Newswires
April 12, 2017 02:00 ET (06:00 GMT)
W Resources (LSE:WRES)
Historical Stock Chart
From Mar 2024 to Apr 2024
W Resources (LSE:WRES)
Historical Stock Chart
From Apr 2023 to Apr 2024