TIDMAAZ
RNS Number : 8800L
Anglo Asian Mining PLC
24 July 2017
Anglo Asian Mining plc / Ticker: AAZ / Index: AIM / Sector:
Mining
24 July 2017
Anglo Asian Mining plc
Ugur Gold Deposit Development and Gedabek Exploration Update
Anglo Asian Mining plc ("Anglo Asian" or the "Company"), the AIM
listed gold, copper and silver producer, is pleased to announce an
exploration and development update for the Ugur gold deposit
("Ugur" or the "Ugur deposit") located at the Company's Gedabek
licence area ("Gedabek Licence") in Western Azerbaijan, together
with an exploration update on the wider Gedabek Licence.
Ugur development highlights
-- Development at Ugur progressing on schedule for first production in Q4 2017
-- Core and reverse circulation ("RC") drilling and assaying
completed to enable an independent JORC classified Resource and
Reserve report expected in Q3 2017
-- A preliminary sectional estimate of Azeri classified reserves
by the Company shows approximately 195,000 ounces of in-situ
gold*
-- Completed drilling expands the total resource at the Gedabek
Licence, providing significant potential upside to the Company's
future gold production
-- Geotechnical studies show no issues with the competency of
the rock and independent environmental impact assessments have been
completed
-- Condemnation drilling prior to final siting of surface
infrastructure expected to be completed by end of July 2017
-- Good progress made with the road between the Ugur deposit and
the Company's processing facilities
-- Top soil pre-strip and storage planned for late Q3 2017
* note this is not a JORC compliant reserve or resource
Other Gedabek exploration highlights
-- Further exploration in the main Gedabek open pit mine
underway with 61 RC and two core drill-holes completed
-- 216 metres of a planned 465 metres tunnel between the Gadir
underground mine and the down dip extension of the main Gedabek
open pit now completed
Anglo Asian CEO, Reza Vaziri, said "Anglo Asian will have
progressed from making our first exploratory drill-hole of the Ugur
deposit to producing ore from an open pit mine in little over one
year. This is a testament to the speed at which the Company can
react when presented with value accretive opportunities.
"Production flexibility, expansion and opportunity are resulting
from the development of the Ugur gold deposit together with the
exploration and optimisation of other deposits in the Gedabek
contract area. The resultant production profile will allow a
timeframe for expanded exploration and evaluation of other
mineralisation indicators for future growth."
Anglo Asian Group Director of Geology & Mining, Stephen
Westhead, said "The Ugur deposit clearly demonstrates Anglo Asian's
ability to rapidly progress projects from exploration to reserves
and, if viable, into production. The first Ugur drill hole was
completed in September 2016 and we are planning to commence mining
in Q4 2017. Our geology and mining team has maximised the
opportunity of very good exploration potential of possible ore
deposits close to the Company's existing extraction and processing
facilities. This provides significant benefit to Anglo Asian by
increasing reserves for future production, as well as for
replacement of gold ounces previously mined.
"Ugur is likely to provide the Company with an easily mineable,
50-metre-deep gold oxide ore body containing an in-house estimate
of approximately 195,000 ounces of in-situ gold, which is highly
amenable to agitation and heap leach processing."
Ugur Gold Deposit Exploration and Development Update
Discovery and development
Anglo Asian's in-house exploration team defined a new mineral
occurrence in 2016 named "Ugur" (meaning "good luck" or "success"
in the Azeri language) from geological mapping. Ugur is located
three kilometres north-west from the Company's processing
facilities at its Gedabek Licence. Since the discovery of Ugur, the
Company has been extensively exploring the deposit to define its
resource and reserves and constructing the required infrastructure,
including road access between the Ugur deposit and the Company's
processing facilities, to enable mining to commence. Pre-stripping
of the top soil is planned to commence in late July 2017 with
mining by conventional shovel and truck haulage commencing in Q4
2017. Metallurgical test-work has confirmed the amenability of the
Ugur gold ore to both heap and agitation leaching.
Drilling and geological evaluation
55 "phase one" RC drill holes totalling 1,842 metres, 50 core
drill holes totalling 6,355 metres, and 33 infill RC drill holes
totalling 2,766 metres have now been drilled at Ugur, which has
resulted in confirmation of an oxide gold-rich zone to a depth
varying between 50 to 60 metres. The area covered by this drilling
and proposed open pit outline is 350 metres (east-north-east) by
250 metres (north-north-west).
A summary of the drilling is as follows:
Name of drill-hole Type Start date Finish Number Length
date of drill (metres)
holes
--------------------- -------------- ------------ ---------- ---------- ----------
Reverse 23 Sept. 14 Nov.
Reverse circulation circulation 2016 2016 56 1,842
--------------------- -------------- ------------ ---------- ---------- ----------
4 October 25 June
Core Diamond 2016 2017 50 6,355
--------------------- -------------- ------------ ---------- ---------- ----------
16 April 27 April
Geotechnical Diamond 2017 2017 2 164
--------------------- -------------- ------------ ---------- ---------- ----------
Reverse circulation
- Reserve Reverse 19 March 9 July
and resource circulation 2017 2017 33 2,766
--------------------- -------------- ------------ ---------- ---------- ----------
Condemnation 25 June 6 July
drilling Diamond 2017 2017 3 373
--------------------- -------------- ------------ ---------- ---------- ----------
TOTAL DRILLING 144 11,500
--------------------------------------------------------------- ---------- ----------
Maps showing the location of the core diamond drill holes and
reverse circulation drill holes are available on the Company's web
site at
http://www.angloasianmining.com/operations/reserves-exploration-and-development/.
Full results from the Ugur drilling programme are set out in
Appendix one below.
External quality assurance and quality control assaying is
nearing completion. Independent check assaying of 760 samples and
full multi-element analysis are being undertaken by western
consultants. These assays will provide a check of the grades of
mineralisation as assayed and analysed by the Company's
laboratories. Extensive in-house quality assurance and control
assaying is also being carried out by Anglo Asian. External quality
assurance and control data is now being received by the Company and
compared to in-house laboratory results. The data will form part of
the JORC resource and reserve report. Extensive specific gravity
tests have also been completed for ore tonnage calculations.
Condemnation drilling to prove the absence of mineralisation
below proposed areas of infrastructure, including the waste dump
areas, soil storage areas and lay down area for office facilities
and mechanical workshops has commenced. Three condemnation drill
holes with a total of 373 metres have been completed and a further
nine drill holes will be undertaken. The work is planned to be
completed by the end of August 2017.
Geotechnical and environmental assessment studies
Independent geotechnical studies have been completed by the
environmental engineering company, CQA International Limited, to
assess rock mass strength and structural geological relationships
for mine design parameters. Two geotechnical drill holes (76 metres
and 164 metres in length) from the position of the "ore" in the
proposed open pit area into the preliminary designed backwall have
been completed and geo-technically assessed. Independent rock
strength tests, which showed good rock competency, are complete and
will be utilised in the open pit wall design.
Independent environmental impact assessments have been completed
and hydrogeological baseline monitoring will be established.
Resources and reserves
The drilling and assaying of drill samples from Ugur for the
purpose of resource estimation is completed. A sectional resource
and reserve estimate made by Anglo Asian to Azeri standards
resulted in an in-situ resource of 195,000 ounces of gold.
Three-dimensional geological modelling of Ugur has been
successfully completed. An independent JORC resource estimation and
reserve calculation report is being prepared and is anticipated to
be published in Q3 2017.
Road construction and other surface infrastructure
development
The construction of a 4.6 kilometre road between the Ugur
deposit and the Company's processing facilities commenced in May
2017. Road access from the processing facilities to the proposed
pit is now complete. Culvert construction is to be completed and an
estimated 25 per cent. of top sheeting remains to be completed to
finish the road. Safety berms and windrows are 80 per cent
constructed along the full length of the road, and road delineators
are being installed every 50 metres. It is estimated that the road
will be fully completed by the end of July 2017.
A schematic plan of the road layout showing the extent of the
completed road and photographs of the road construction are
available on the Company's web site at
http://www.angloasianmining.com/operations/reserves-exploration-and-development/.
Infrastructure sites for soil storage area, waste dump and
equipment laydown and workshop areas have been delineated.
Containers for office, emergency workshop and maintenance
facilities, hygiene and other facilities are being fitted out in
preparation for production.
2017 Exploration and Production Optimisation Update
Strategy
Anglo Asian is undertaking an extensive exploration and
production optimisation programme during 2017 with the aim of
creating future flexibility and growth at its Gedabek Licence. This
programme will be achieved by utilising ore from the Company's
extensive stockpiles for processing to maintain production while
mining in the main open pit is temporarily suspended. The
utilisation of ore stockpiles reduces the ore inventory of the
Company and makes space available, if required, for future
stockpiling of ore. Certain mining operations will be temporarily
ceased to enable development exploration, optimisation and
redeployment of equipment to other tasks. Mining in the Gedabek
open pit was reduced during May 2017 until the end of the year and
some of the Company's heavy earthmoving equipment is being
redeployed for transporting stockpiled ore, construction of the
infrastructure for the new Ugur open pit mine and raising the
tailings dam wall.
The Company's strategy for 2017 is expected to have a positive
impact on production starting from Q4 2017. In this quarter, the
Company will be able to recommence mining in both the Gadir and
Gosha underground mines. In addition, production will commence from
the new Ugur open pit. These various sources of ore will enable the
Company to quickly increase production and give it flexibility to
optimise its processing strategy. The resumption of full production
from the main open pit in Q1 2018 will further enhance the ability
of the Company to increase production and give it additional
flexibility in processing.
Surface and Gedabek Open Pit Exploration
Surface core drilling targeted to intersect the down dip
extension of Gadir mineralisation comprised six drill-holes with a
total of 2,640 metres of drilling. These drill holes intersected
Gadir style mineralisation and confirm the extended resource
potential.
H1 2017 work at the Gedabek open pit relating to production
comprised the drilling of 61 reverse circulation drill-holes with a
total of 2,134 metres. Sampling included 7,624 samples from bench
drill-holes as part of the mining grade control and 1,213 mining
block samples. The exploration and optimisation drilling commenced
in June 2017 with two core drill-holes completed with a total of
357 metres and assay results are awaited. On completion of the
condemnation drilling work at Ugur, an additional two core drill
rigs and one reverse circulation drill rig will be redeployed to
the Gedabek open pit area.
Gedabek Deep Mineralisation Study
Tunnelling from the Gadir underground mine to the down dip
extension of the Gedabek open pit mineralisation has commenced. 215
metres of the planned 465 metres have been completed to date. It is
expected that the tunnel will be completed by the end of
August/early September 2017. This will allow the Company to assess
the extent of the higher-grade gold mineralisation below the
Gedabek open pit as found in exploration drill holes. The future
project plan is to construct a tunnel following the mineralisation
under the Gedabek open pit and to carry out underground fan
drilling to assess the future underground mining potential. This
work will also provide geotechnical data for assessing the rock
characteristics for underground stability that would be used in
mine design work. Data collected will be utilised to evaluate the
future open pit to underground transition. The fan drilling work is
planned for 2018.
Ore production has been reduced from the Gadir underground mine
(from February 2017 until September 2017) to allow for development
and exploration drilling. Any ore mined from Gadir during this
exploration development phase will be mainly stockpiled for Q4 2017
production, however, 24,000 tonnes of ore were sent for processing
during the six months to 30 June 2017.
Competent Person Statement
The information in the announcement that relates to exploration
results is based on information compiled by Dr Stephen Westhead,
Director of Geology & Mining at Anglo Asian Mining, who is a
Fellow of The Geological Society of London, a Chartered Geologist,
Fellow of the Society of Economic Geologists and a Member of The
Institute of Materials, Minerals and Mining.
Stephen Westhead has sufficient experience, relevant to the
style of mineralisation and type of deposit under consideration and
to the activity that he is undertaking, to qualify as a qualified
person as defined by the AIM rules. Stephen Westhead has reviewed
the exploration results included in this announcement.
Market Abuse Regulation (MAR) Disclosure
Certain information contained in this announcement would have
been deemed inside information for the purposes of Article 7 of
Regulation (EU) No 596/2014 until the release of this
announcement.
For further information please visit www.angloasianmining.com or
contact:
Anglo Asian Mining Tel: +994 12 596
Reza Vaziri plc 3350
-------------------- ------------------- ------------------
Anglo Asian Mining Tel: +994 502 910
Bill Morgan plc 400
-------------------- ------------------- ------------------
Anglo Asian Mining Tel: +994 502 916
Stephen Westhead plc 894
-------------------- ------------------- ------------------
Ewan Leggat SP Angel Corporate Tel: +44 (0) 20
Finance LLP 3470 0470
Nominated Adviser
and Broker
-------------------- ------------------- ------------------
Soltan Tagiev SP Angel Corporate Tel + 44 (0) 20
Finance LLP 3470 0470
-------------------- ------------------- ------------------
Lottie Brocklehurst St Brides Partners Tel: +44 (0) 20
Ltd 7236 1177
-------------------- ------------------- ------------------
Susie Geliher St Brides Partners Tel: +44 (0) 20
Ltd 7236 1177
-------------------- ------------------- ------------------
Notes:
Anglo Asian Mining plc (AIM:AAZ) is a gold, copper and silver
producer in Central Asia with a broad portfolio of production and
exploration assets in Azerbaijan. The Company has a 1,962 square
kilometre portfolio, assembled from analysis of historic Soviet
geological data and held under a Production Sharing Agreement
modelled on the Azeri oil industry.
The Company developed Azerbaijan's first operating
gold/copper/silver mine, Gedabek, which commenced gold production
in May 2009. Gedabek is an open cast mine with a series of
interconnected pits. The Company also operates the high grade
Gadir underground mine which is co-located at the Gedabek site.
The Company has a second underground mine, Gosha, which is 50
kilometres from Gedabek. Ore mined at Gosha is processed at Anglo
Asian's Gedabek plant.
Gold production for the year ended 31 December 2016 from Gedabek
totaled 65,394 ounces with 1,941 tonnes of copper also produced.
Gedabek is a polymetallic deposit and its ore has a high copper
content, and as a result the Company produces copper concentrate
from its Sulphidisation, Acidification, Recycling, and Thickening
(SART) plant. Anglo Asian also produces a copper and precious metal
concentrate from its flotation plant, which is processing tailings
from the agitation leach plant.
Anglo Asian is also actively seeking to exploit its first mover
advantage in Azerbaijan to identify additional projects, as well as
looking for other properties in order to fulfil its expansion
ambitions and become a mid-tier gold and copper metal production
company.
APPIX 1
FULL RESULTS OF UGUR DRILLING PROGRAMME
Core drill holes (drill holes 7 to 50)
Depth of drill hole
------------------------------------------------
Drill-hole
number From (metres) To (metres) Interval (metres) Gold (g/t) Silver (g/t)
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD07 0.0 61.0 61.0 1.89 7.36
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD08 0.0 77.0 77.0 2.36 24.19
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD09 10.0 85.5 75.5 0.88 3.60
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD10 0.0 112.5 112.5 1.20 5.71
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD11 124.2 125.3 1.1 0.34 1.82
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD12 0.0 13.0 13.0 0.33 1.06
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD13 88.0 90.0 2.0 0.86 0.40
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD14 0.0 71.5 71.5 0.66 4.25
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD14 71.5 76.5 5.0 1.90 2.25
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD14 76.5 91.7 15.2 0.31 0.70
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD16 0.0 42.0 42.0 1.06 6.74
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD16 42.0 114.0 72.0 0.40 2.50
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD17 0.0 15.0 15.0 2.13 11.60
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD18 0.0 50.0 50.0 0.72 5.06
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD18 61.0 74.3 13.3 1.10 2.37
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD19 0.0 7.0 7.0 1.00 3.47
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD19 12.0 45.0 33.0 1.02 6.46
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD19 45.0 71.4 26.4 0.37 1.38
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD20 5.0 9.0 4.0 1.30 1.42
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD20 9.0 27.0 18.0 0.33 1.48
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD20 27.0 33.0 6.0 1.78 5.33
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD20 71.0 72.0 1.0 1.11 0.40
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD21 0.0 9.1 9.1 0.47 6.26
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD21 9.1 15.0 5.9 1.05 4.51
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD21 15.0 32.0 17.0 0.36 4.70
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD21 32.0 46.5 14.5 1.01 3.70
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD21 46.5 104.5 58.0 0.31 0.86
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD22 0.0 14.0 14.0 0.81 1.34
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD24 0.0 2.9 2.9 0.32 3.04
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD25 14.5 22.0 7.5 1.50 4.87
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD25 25.0 27.0 2.0 0.39 4.06
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD26 0.0 3.0 3.0 4.58 10.43
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD27 13.0 51.5 38.5 1.46 6.49
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD28 0.0 43.5 43.5 1.06 2.25
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD30 5.5 49.8 44.3 1.51 7.87
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD30 82.5 90.0 7.5 2.25 1.74
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD31 0.0 7.0 7.0 0.37 1.49
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD31 52.5 62.5 10.0 0.34 0.86
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD32 0.0 51.9 51.9 0.45 4.81
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD35 66.5 77.5 11.0 0.48 4.10
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD37 84.5 103.5 19.0 1.28 3.03
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD38 33.0 36.0 3.0 0.30 1.20
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD39 50.0 56.0 6.0 0.33 1.20
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD40 148.0 150.0 2.0 0.31 1.10
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD41 56.5 58.5 2.0 0.55 1.19
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD41 108.5 116.0 7.5 0.32 0.94
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD42 0.0 71.0 71.0 0.34 5.03
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD43 0.0 61.8 61.8 0.61 2.65
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD44 0.0 10.0 10.0 1.14 9.20
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD44 38.0 61.8 23.8 0.48 2.40
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD45 0.0 32.0 32.0 0.36 1.38
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD46 0.0 42.0 42.0 0.32 4.90
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD46 42.0 62.0 20.0 0.33 1.95
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD47 0.0 14.0 14.0 0.90 8.20
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD47 14.0 71.5 57.5 0.46 6.00
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD48 0.0 17.0 17.0 1.30 11.20
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD49 0.0 24.0 24.0 1.04 10.60
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD49 24.0 61.0 37.0 0.70 3.70
------------ -------------- ------------ ------------------ ----------------- --------------------
UGDD50 0.0 8.5 8.5 0.35 2.50
------------ -------------- ------------ ------------------ ----------------- --------------------
Reverse Circulation drill holes (RC holes 1 to 32)
Depth of drill hole
-------------------- ------------ ------------------ ----------------- ------------------
Drill-hole From To (metres) Interval (metres)
number (metres) Gold (g/t) Silver (g/t)
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC01 0.0 6.0 6.0 no sample no sample
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC01 6.0 7.0 1.0 0.16 2.12
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC01 7.0 24.0 17.0 2.28 11.79
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC01 24.0 33.0 9.0 0.57 1.18
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC01 33.0 60.0 27.0 1.36 2.71
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC01 60.0 84.0 24.0 0.70 1.03
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC03 1.0 32.0 31.0 0.22 0.61
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC03 32.0 102.0 70.0 1.35 3.18
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC03 102.0 119.0 17.0 0.39 1.94
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC05 0.0 111.0 111.0 0.19 0.56
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC07 9.0 57.0 48.0 2.45 4.42
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC07 57.0 113.0 56.0 0.33 1.49
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC09 0 57 57 1.37 9.96
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC09 57 81 24 0.36 1.70
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC10 0 4 4 0.32 7.33
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC10 4 15 11 10.79 19.10
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC10 15 54 39 1.73 10.30
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC11 0 50 50 1.42 11.20
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC11 50 68 18 0.91 2.50
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC12 5 22 17 1.80 10.10
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC12 22 26 4 6.50 17.80
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC12 26 42 16 2.04 12.00
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC12 42 69 27 0.36 1.90
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC13 0 5 5 0.43 1.70
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC13 5 14 9 1.00 8.60
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC13 14 33 19 0.58 5.60
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC13 33 50 17 0.50 5.20
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC16 0 7 7 0.76 6.20
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC16 7 72 65 1.58 9.70
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC17 0 6 6 0.31 0.90
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC17 6 9 3 3.11 22.80
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC17 9 29 20 0.41 4.70
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC17 29 33 4 1.37 8.70
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC17 33 75 42 1.10 10.80
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC18 0 21 21 0.35 3.70
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC18 21 29 8 1.36 11.00
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC18 29 48 19 0.82 8.60
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC18 48 60 12 0.56 5.40
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC18 60 66 6 1.46 16.00
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC19 0 15 15 1.20 11.00
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC19 15 48 33 0.71 8.50
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC19 48 61 13 0.33 3.10
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC19 61 71 10 0.99 7.50
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC19 71 87 16 0.80 6.80
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC20 0 42 42 1.68 6.08
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC20 42 64 22 0.60 7.50
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC20 64 75 11 1.14 12.70
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC21 0 3 3 0.30 2.90
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC21 3 31 28 2.70 17.20
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC21 31 67 36 1.95 10.80
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC21 67 82 15 0.64 5.80
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC21 82 91 9 0.19 0.80
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC22 0 34 34 2.30 15.20
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC22 34 52 18 8.30 12.20
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC22 52 69 17 0.83 2.50
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC23 0 41 41 0.35 2.15
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC23 41 64 23 0.94 3.10
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC23 64 79 15 0.77 1.94
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC24 0 47 47 1.53 13.40
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC25 0 14 14 0.58 1.60
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC25 14 38 24 1.20 11.70
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC25 38 78 40 0.52 1.20
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC26 0 61 61 2.00 11.50
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC27 0 71 71 1.10 9.50
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC27 71 80 9 0.37 1.20
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC28 34 40 6 0.78 2.60
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC29 11 47 36 1.65 10.70
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC29 59 70 11 0.70 2.80
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC29 70 84 14 0.40 1.20
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC30 0 13 13 0.47 4.30
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC30 13 16 3 1.70 7.80
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC31 7 15 8 1.20 2.70
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC31 26 34 8 0.41 0.90
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC32 0 7 7 0.30 1.10
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC32 17 21 4 0.78 4.70
------------ -------------------- ------------ ------------------ ----------------- ------------------
RGRC32 35 40 5 0.73 0.90
------------ -------------------- ------------ ------------------ ----------------- ------------------
This information is provided by RNS
The company news service from the London Stock Exchange
END
UPDLIFLADVISFID
(END) Dow Jones Newswires
July 24, 2017 05:33 ET (09:33 GMT)