TIDMEDL
RNS Number : 8607N
Edenville Energy PLC
27 September 2019
27 September 2019
EDENVILLE ENERGY PLC
("Edenville" or the "Company")
Interim Results for the six months to 30 June 2019
Edenville Energy plc (AIM: EDL), the company developing a coal
project in southwest Tanzania, announces the Company's unaudited
interim results for the six months ended 30 June 2019.
Key Period Highlights
-- Executed equity placing to raise GBP510,000 (gross) in April
2019 to advance coal production
-- Coal wash plant upgraded and now fully operational; including
a Lamella water treatment plant, the introduction of a coal
sizer and installation of a pre-screening plant, thereby
enabling greater efficiency and productivity
-- Started to re-treat fine coal, recovering approximately 40%
of coal material above 8mm for either direct sale or subsequent
blending with existing coal stocks to increase saleable product
-- Completed the land compensation for the New Northern Mining
Area (the "Northern Area")
-- In June 2019 the Company established the new road to the
Northern Area and commenced stripping and exposing of coal
Post Period Highlights
-- Coal mining commenced in the Northern Area
-- Encouraging coal sampling results. Analysis of unwashed Northern
Area coal returned energy values averaging 6,200kcal/kg,
with the highest being over 6,800kcal/kg. These energy values
are significantly higher than those seen in previously mined
areas, which averaged approximately 5,000kcal/kg; the yielding
of +6,000 kcal/kg GCV from unwashed coal provides the opportunity
to sell coal without the requirement to put it through the
wash plant
-- Large coal measures of approximately 20m (and up to 40m)
in thickness, 4 metres from surface, have been exposed in
the Northern Area, compared to measures of approximately
3.5m in thickness in previously mined areas
-- Mining now focused in the Northern Area given lower strip
ratio, improved economics and better quality of coal
-- Purchased two 30 tonne trucks from TATA, to be used in mining
load and haul, moving away from contractor haulage to owner
operated haulage
-- In September 2019 the Company raised an additional GBP300,000
by way of a placing of 600,000,000 new ordinary shares, envisaged
to provide sufficient capital until the Company turns cash
flow positive from operations
-- Appointment of mining industry expert Alistair Muir as a
Non-Executive Director replacing Arun Srivastava
Jeff Malaihollo, Chairman of Edenville, commented: "During 2019
the Company has achieved encouraging operational progress at the
Rukwa coal project. The completion of the various upgrades to the
wash plant are already providing greater recoveries, a reduction in
consumables and should also enable greater throughput as mining
operations continue to expand. The opening up of the Northern
Mining Area has yielded materially positive results, with thicker
seams and higher quality coal than previously experienced at Rukwa.
As a consequence the Board believes both the economics and the
profitability of operations should improve further as we continue
to increase coal sales to new and historic customers.
"From a corporate perspective, the Company has recapitalised
itself and formed a solid foundation from which to further build
and achieve our primary short term objective, to become cash flow
positive from operations during H1 2020.
"Whilst additional work naturally remains to be done, we are
confident of reaching those value-enhancing milestones for
shareholders in the timeframes previously outlined. We would like
to thank all of our shareholders for their continuing support and
we look forward to the remainder of 2019 with confidence."
For further information please contact:
+44 (0) 20 3934
Edenville Energy Plc 6630
Jeff Malaihollo - Chairman
Rufus Short - CEO
SP Angel Corporate Finance +44 (0) 20 3470
LLP 0470
(Nominated Adviser and Joint
Broker)
David Hignell
Jamie Spotswood
Abigail Wayne
+44 (0) 20 7936
Brandon Hill Capital Limited 5200
(Joint Broker)
Oliver Stansfield
Jonathan Evans
+44 (0) 20 3934
IFC Advisory Limited 6630
(Financial PR and IR)
Tim Metcalfe
Graham Herring
Florence Chandler
CEO's report
Operational Report
Production of Coal
During the period the Company's primary focus was on the coal
mining operations at the Company's Rukwa Coal Project (the
"Project") in southwest Tanzania.
January 2019 got off to a good start with the addition of a
second excavator to open up the mine along with the existing
machine. The Lamella Plant was operational and the newly
constructed pre-screen plant started processing test material in
January 2019 and became fully operational in February.
In January 2019 the Company decided to carry out an Open Offer
to existing shareholders in order to raise the remaining capital
needed to open up the Northern Mining Area and subsequently
increase production. However, the Open Offer, at 0.12p per share,
was poorly received and only approximately 10% of the planned
GBP619,099 was eventually raised. This left the Company in a
challenging situation on how best to meet customers' orders and
expand the operation.
From February 2019 the Company took measures to conserve capital
and continue supply to key customers whilst seeking alternative
funding arrangements. As announced on 1 April 2019, production was
adversely impacted in H1 2019 with approximately 18,772 tonnes of
Run of Mine ("ROM") coal processed to produce 4,411 tonnes of
washed coal and 11,134 tonnes of fine coal between 1 January 2019
and 30 June 2019.
On 29 April 2019 the Company announced a conditional fundraising
of GBP510,000 along with certain cost saving measures and started
to make preparations to apply some of this funding to the Project
development. The main areas targeted were the opening up of the pit
in the Northern Area, which has higher quality coal and thicker and
easier to access coal seams. At the same time we made small
upgrades to the plant and infrastructure, such as an improved water
pumping system and installation of a coal sizer prior to the plant.
At the end of the period land compensation work and the building of
the road to the Northern Area were completed. In addition,
overburden stripping, which exposed coal, was undertaken in the
Northern Area and mining subsequently commencing in July 2019.
The Company's target is to firstly reach a steady state
production rate of 6,000 tonnes per month of washed coal product,
which we believe will enable the Tanzania operations to break even.
Following this the second target is to reach 10,000 tonnes of
washed coal produced per month which will provide positive cash
flow for the Company. The Directors believe the Company remains on
track to become cash flow positive from existing operations during
H1 2020.
The fine coal is effectively produced as a by-product and, to
that end, we are continuing discussions with the previously
outlined buyers of fine coal. The introduction of the pre-screen
means that some of the stockpiled fine coal can now be reprocessed.
During the period we targeted areas of stockpiled fine coal that
contained economically recoverable coal to feed through the
pre-screen. Approximately 4,500 tonnes of the fine stockpile have
been treated yielding 1,800 tonnes of sized coal.
Until recently, the Company had been relying on trucks supplied
by contractors, which had sometimes proved to be an expensive and
inefficient option. To this end, as announced on 21 August 2019,
Edenville took the decision to purchase two 30 tonnes trucks which
are now used to provide the backbone of load and haul operations at
the Project. The wash plant is currently operating on a two shift
basis, with the new trucks currently supplying the plant on one
shift with the other shift being used to process coal from
stockpiles. As the Northern Area continues to develop the focus of
mining is moving to this area and a double shift operation of
extracting coal from the Northern Area will start once training of
operators is completed by mid-October 2019.
Production in H2 2019 started well with the plant producing
1,134 tonnes of washed product, principally in the first half of
July 2019, as the effects of the upgrades began to show. The wash
plant was reaching production rates of over 100 tonnes per day from
a single shift during this period. However, during the second half
of July and the majority of August 2019, mining was adversely
affected by the lack of available contractor trucks and a delay on
the delivery of our own trucks, which in turn compromised the
plant's production ability. With the arrival of our own trucks in
late August 2019 this issue has now been resolved and the available
coal supply is steadily increasing, with further increases in
production rates anticipated in the short term. This will
subsequently enable increased sales to identified customers, many
of whom require a surety of supply, which the Company should now be
able to offer. As production of washed coal increases the Directors
expect unit sales costs to progressively fall. Post period end
approximately 1,510 tonnes of washed coal has been shipped between
1 July 2019 and 20 September 2019.
Coal to Power Project
In October 2018 the Company submitted a Request for
Qualification ("RFQ") for coal fired generation projects in
Tanzania to Tanzania Electric Supply Company ("Tanesco"), which
Tanesco officially accepted as being complete and complying with
their requirements. However, two weeks later, for reasons not given
by Tanesco, the RFQ was cancelled and subsequently reinstated for a
resubmission date in December 2018. Edenville resubmitted their RFQ
documents in line with the criteria set forward by Tanesco, which
appeared identical to the previous criteria. On 14 February 2019
Tanesco informed the Company that it had been unsuccessful in
moving through the RFQ process to supply power to Tanesco. No clear
explanation has been given for this decision to date. As far as the
Company is aware no other privately held coal projects in Tanzania
progressed successfully through the process.
The AFR RI-3A Tanzania - Zambia Transmission Interconnector
project, which is being part financed by the World Bank, is
continuing to move forward which we believe will have positive
implications for our proposed coal to power project. The financing
agreement for credit is now in place and the procurement plan is
continuing to progress. As previously stated the Company's long
term plan is to provide electricity to this transmission grid once
it is completed and we are continuing to work towards this goal.
Currently completion is stated as being in 2024.
However, in the short to medium term the focus of the Company is
on it coal mining operations and the sale of coal to Tanzanian and
other customers in East Africa.
Financial Results
For the six month period ended 30 June 2019 the Company had
revenue of GBP151,140 (H1 2018: GBP59,310).
The Group made a loss after taxation of GBP888,045 (H1 2018 loss
of GBP544,959). The net assets at 30 June 2019 amounted to
GBP6,367,559 (30 June 2018 GBP7,568,436).
The total comprehensive loss for the period was GBP887,339 (H1
2018 loss of GBP387,412), which included a gain of GBP706 (H1 2017
gain of GBP157,457) arising from the translation of the Tanzanian
subsidiary accounts from US Dollars to Sterling.
Rufus Short
Chief Executive Officer
CONSOLIDATED STATEMENT OF COMPREHENSIVE INCOME
Six months Six months Year
ended ended ended
30 June 30 June 31 Dec
19 18 18
Unaudited Unaudited Audited
Note GBP GBP GBP
Revenue 151,140 59,310 337,125
Cost of sales (476,352) (54,663) (1,191,312)
Gross profit (325,212) 4,647 (854,187)
Administrative expenses (483,112) (526,648) (839,515)
Share based payments (16,077) (23,235) (76,319)
Written off intangible asset - - -
Group operating loss (824,401) (545,236) (1,770,021)
Finance income 56 277 529
Finance costs (63,700) (16,212)
Loss on operations before taxation (888,045) (544,959) (1,785,704)
Taxation - - -
Loss for the period after taxation (888,045) (544,959) (1,785,704)
Other comprehensive income/(loss):
Gain/(loss) on translation of
overseas subsidiary 706 157,547 (378,531)
Total comprehensive (loss)/income
for the period (887,339) (387,412) (1,407,173)
Attributable to:
Equity holders of the Company (886,401) (386,955) (1,404,725)
Non-controlling interest (938) (457) (2,448)
(887,339) (387,412) (1,407,173)
Loss per share
- basic and diluted (pence) 2 (0.04) (0.04) (0.12)
The income for the period arises from the Group's continuing
operations.
CONSOLIDATED statement of financial position
as at 30 june 2019
As at As at As at
30 June 30 June 31 Dec
19 18 18
Unaudited Unaudited Audited
Note GBP GBP GBP
Non-current assets
Property, plant and equipment 4 1,027,062 975,267 1,139,031
Intangible assets 5 5,779,973 5,664,122 5,775,829
6,807,035 6,639,389 6,914,860
Current assets
Inventories 329,559 163,184 256,082
Trade and other receivables 506,042 390,755 396,671
Cash and cash equivalents 75,843 537,478 160,042
911,444 1,091,417 812,795
Current liabilities
Trade and other payables (749,860) (162,370) (556,063)
Convertible loan notes (252,428) (288,118)
(1,002,280) (162,370) (844,181)
Current assets less current
liabilities (90,844) 929,047 (31,386)
Total assets less current liabilities 6,716,191 7,568,438 6,883,474
Non - current liabilities
Convertible loan notes (348,632) - (282,076)
6,367,559 7,568,436 6,601,398
Capital and reserves
Called-up share capital 6 3,294,935 2,722,036 2,722,036
Share premium account 18,631,157 18,566,642 18,566,642
Share based payment reserve 291,540 224,376 275,463
Foreign currency translation
reserve 934,202 712,512 933,496
Retained earnings (16,771,838) (14,647,974) (15,884,731)
Issued capital and reserves
attributable to owners of the
parent company 6,379,996 7,577,592 6,612,906
Non-controlling interest (12,437) (9,156) (11,508)
Total equity 6,367,559 7,568,436 6,601,398
CONSOLIDATED statement of changes in equity
----------------------------------Equity
Interests--------------------------------
Foreign
Share currency Non-
Share Share Retained option translation Controlling
capital premium Earnings reserve reserve Total interest Total
GBP GBP GBP GBP GBP GBP GBP GBP
Balance at 1
January
2019 2,722,036 18,566,642 (15,884,731) 275,463 933,496 6,612,906 (11,508) 6,601,398
Issue of share
capital 572,899 64,515 - - - 637,414 - 637,414
Share based
payment
charge - - - 16,077 - 16,077 - 16,077
Foreign currency
translation - - - - 706 706 9 715
Loss for the
period - - (887,107) - - (887,107) (938) (888,045)
Balance at 30
June
2019 3,294,935 18,631,157 (16,771,838) 291,540 934,202 6,379,996 (12,437) 6,367,559
Balance at 1
January
2018 2,679,750 17,910,928 (14,212,274) 309,943 554,965 7,243,312 (8,464) 7,234,848
Issue of share
capital 42,286 697,714 - - - 740,000 - 740,000
Share issue costs - (42,000) - - - (42,000) - (42,000)
Share based
payment
charge - - - 23,235 - 23,235 - 23,235
Lapse of share
options - - 108,802 (108,802) - - - -
Foreign currency
translation - - - - 157,547 157,547 (235) 157,312
Loss for the
period - - (544,502) - - (544,502) (457) (544,959)
Balance at 30
June
2018 2,722,036 18,566,642 (14,647,974) 224,376 712,512 7,577,592 (9,156) 7,568,436
Foreign
Share currency Non-
Share Share Retained option translation Controlling
capital premium Earnings reserve reserve Total interest Total
GBP GBP GBP GBP GBP GBP GBP GBP
Balance at 1
January
2018 2,679,750 17,910,928 (14,212,274) 309,943 554,965 7,243,312 (8,464) 7,234,848
Issue of share
capital 42,286 697,714 - - - 740,000 - 740,000
Cost of issue - (42,000) - - - (42,000) - (42,000)
Share
options/warrants
charge - - - 76,319 - 76,319 - 76,319
Cancellation of
share
options - - 110,799 (110,799) - - - -
Foreign currency
translation - - - - 378,531 378,531 (746) 377,785
Loss for the year - - (1,783,256) - - (1,783,256) (2,448) (1,785,704)
Non-controlling
interest
share of
goodwill - - - - - - 150 150
Balance at 31
December
2018 2,722,036 18,566,642 (15,884,731) 275,463 933,496 6,612,906 (11,508) 6,601,398
consolidated CASH FLOW STATEMENT
Six months Six months Year
ended ended ended
30 June 30 June 31 Dec
19 18 18
Unaudited Unaudited Audited
GBP GBP GBP
Cash flows from operating activities
Operating loss (824,401) (545,263) (1,770,021)
Depreciation 110,929 104,493 229,732
Amortisation 14,461 - 57,928
Share based payments 16,077 23,235 76,319
(Increase) in inventories (73,477) (163,184) (256,082)
(Decrease) in trade and other
receivables (108,496) (81,565) (77,196)
Increase in trade and other payables 191,590 13,527 390,069
Foreign exchange gain/(loss) (11,006) 4,323 37,584
Net cash used in operating activities (684,323) (644,434) (1,311,667)
Cash flows from investing activities
Purchase of exploration and evaluation
assets - (467,553) (468,145)
Purchase of property, plant and
equipment (706) - (259,601)
Finance income 56 277 529
Finance cost (16,884) - -
Net cash used in investing activities (17,494) (467,276) (727,217)
Cash flows from financing activities
Proceeds from issue of convertible
loan notes - - 548,853
Repayment of convertible loan (11,787) -
notes
Proceeds on issue of shares 630,214 740,000 740,000
Share issue costs - (42,000) (42,000)
Net cash generated from financing
activities 618,427 698,000 1,246,853
Net decrease in cash and cash
equivalents (83,430) (413,710) (792,031)
Cash and cash equivalents at beginning
of year 160,042 951,078 951,078
Exchange losses on cash and cash
equivalents (769) 110 995
Cash and cash equivalents at end
of year 75,843 537,478 160,042
NOTES TO THE INTERIM REPORT
1. Financial information and basis of preparation
The interim financial statements of Edenville Energy Plc are
unaudited consolidated financial statements for the six months
ended 30 June 2019 which have been prepared in accordance with
IFRSs as adopted by the European Union. They include unaudited
comparatives for the six months ended 30 June 2018 together with
audited comparatives for the year ended 31 December 2018.
The interim financial statements do not constitute statutory
accounts within the meaning of section 434 of the Companies Act
2006. The statutory accounts for the year ended 31 December 2018
have been reported on by the company's auditors and have been filed
with the Registrar of Companies. The report of the auditors was (i)
unqualified, (ii) contained a "Material uncertainty relating to
going concern paragraph and (iii) did not contain any statement
under section 498 of the Companies Act 2006.
The interim consolidated financial statements for the six months
ended 30 June 2019 have been prepared on the basis of accounting
policies expected to be adopted for the year ended 31 December
2019. These are anticipated to be consistent with those set out in
the Group's latest financial statements for the year ended 31
December 2018. These accounting policies are drawn up in accordance
with adopted International Accounting Standards ("IAS") and
International Financial Reporting Standards ("IFRS") as issued by
the International Accounting Standards Board and adopted by the
EU.
2. Loss per share
The calculation of the basic and diluted loss per share is based
on the following data:
30 June 19 30 June 18 31 December
18
GBP GBP GBP
Loss after taxation (888,045) (544,959) (1,785,704)
Weighted average number
of shares in the period 2,311,584,263 1,412,667,005 1,476,497,888
Basic and diluted loss
per share (pence) (0.04) (0.04) (0.12)
The loss attributable to equity shareholders and weighted
average number of ordinary shares for the purposes of calculating
diluted earnings per ordinary share are identical to those used for
basic earnings per ordinary share. This is because the exercise of
share options and warrants would have the effect of reducing the
loss per ordinary share and is therefore anti-dilutive.
3. Dividends
No dividends are proposed for the six months ended 30 June 2019
(six months ended 30 June 2018: GBPnil, year ended 31 December
2018: GBPnil).
4. Tangible assets
Plant & Fixtures Motor vehicles
machinery & fittings Total
GBP GBP GBP GBP
Cost or valuation
As at 1 January
2019 1,435,541 7,360 93,946 1,536,847
Additions 706 - - 706
Foreign exchange
adjustment 4,600 10 249 4,859
At 30 June 2019 1,440,847 7,370 94,195 1,542,412
Accumulated depreciation
As at 1 January
2019 306,410 7,010 84,396 397,816
Charge for period 109,736 43 1,150 110,929
Foreign exchange
adjustment 6,325 10 270 6,605
As at 30 June 2019 422,471 7,063 85,816 515,350
Net book value
As at 30 June 2019 1,018,376 307 8,379 1,027,062
Plant & Fixtures Motor vehicles
machinery & fittings Total
GBP GBP GBP GBP
Cost or valuation
As at 1 January
2018 1,111,852 7,184 89,709 1,208,745
Additions - - - -
Foreign exchange
adjustment 25,679 70 1,697 27,446
At 30 June 2018 1,137,531 7,254 91,406 1,236,191
Accumulated depreciation
As at 1 January
2018 64,873 6,719 77,570 149,162
Charge for period 102,941 58 1,494 104,493
Foreign exchange
adjustment 5,687 70 1,512 7,269
As at 30 June 2018 173,501 6,847 80,576 260,924
Net book value
As at 30 June 2018 964,030 407 10,830 975,267
4. Tangible assets (continued)
Plant & Fixtures Motor vehicles
machinery & fittings Total
GBP GBP GBP GBP
Cost or valuation
As at 1 January
2018 1,111,852 7,184 89,709 1,208,745
Additions 259,601 - - 259,601
Foreign exchange
adjustment 64,088 176 4,237 68,501
At 31 December 2018 1,435,541 7,360 93,946 1,536,847
Accumulated depreciation
As at 1 January
2018 64,873 6,719 77,570 149,162
Charge for the year 226,551 115 3,066 229,732
Foreign exchange
adjustment 14,986 176 3,760 18,922
At 31 December 2018 306,410 7,010 84,396 397,816
Net book value
As at 31 December
2018 1,129,131 350 9,550 1,139,031
5. Intangible assets
Development Goodwill Total
and production
expenditure
GBP GBP GBP
Cost or valuation
As at 1 January
2019 5,501,291 1,572,197 7,073,488
Foreign exchange
adjustment 17,721 5,064 22,785
At 30 June 2019 5,519,012 1,577,261 7,096,273
Accumulated amortisation
and impairment
As at 1 January
2019 57,928 1,239,731 1,297,659
Charge for the
period 14,461 - 14,461
Foreign exchange
adjustment 187 3,993 4,180
As at 30 June
2019 72,576 1,243,724 1,316,300
Net book value
As at 30 June
2019 5,446,436 333,537 5,779,973
5. Intangible assets (continued)
Exploration
and evaluation
assets
Tanzanian Development
Licences and production Goodwill Total
expenditure
GBP GBP GBP
As at 1 January 2018 4,757,087 - 1,485,965 6,243,052
Additions 452,758 14,795 - 467,553
Foreign exchange
adjustment 117,944 - 34,552 152,496
Transfer (5,327,789) 5,327,789
At 30 June 2018 - 5,342,584 1,520,517 6,863,101
Accumulated amortisation
and impairment
As at 1 January 2018 - - 1,171,734 1,171,734
Foreign exchange
adjustment - - 27,245 27,245
As at 30 June 2018 - - 1,198,979 1,198,979
Net book value
As at 30 June 2018 - 5,342,584 321,538 5,664,122
Cost or valuation
As at 1 January 2018 4,757,087 1,485,965 6,243,052
Additions 468,145 - 468,145
Foreign exchange
adjustment 276,059 86,232 362,291
At 31 December 2018 5,501,291 1,572,197 7,073,488
Accumulated amortisation
and impairment
As at 1 January 2018 - 1,171,734 1,171,734
Depletion of development
and production assets 57,928 - 57,928
Foreign exchange
adjustment - 67,997 67,997
At 31 December 2018 57,928 1,239,731 1,297,659
Net book value
As at 31 December
2018 5,443,363 332,466 5,775,829
6. Share capital
No GBP No GBP GBP
Ordinary Ordinary Deferred Deferred Total
shares of shares shares of shares share
0.02p each of 0.02p 0.001p each of 0.001p capital
each each
Issued and fully paid
At 1 January 2019 1,547,746,369 309,551 241,248,512,346 2,412,485 2,722,036
On 20 February 2019
the company issued 36,000,000
shares at 0.02p 36,000,000 7,200 - - 7,200
On 20 February 2019
the Company issued 64,515,192
shares at 0.12p each 64,515,192 12,904 - - 12,904
On 2 May 2019 the Company
issued 500,000,000 shares
at 0.02p each 500,000,000 100,000 - - 100,000
On 20 May 2019 the Company
issued 2,263,980,200
shares at 0.02p each 2,263,980,200 452,795 - - 452,795
As at 30 June 2019 4,412,241,761 882,450 241,248,512,346 2,412,485 3,294,935
================ ========== ================ =========== ==========
No GBP No GBP GBP
Ordinary Ordinary Deferred Deferred Total
shares of shares shares of shares share
0.02p each of 0.02p 0.001p each of 0.001p capital
each each
Issued and fully paid
At 1 January 2018 1,336,317,797 267,265 241,248,512,346 2,412,485 2,679,750
On 3 May 2018 the Company
issued 211,428,572 shares
at 0.35p each 211,428,572 42,286 - - 42,286
As at 30 June 2018 1,547,746,369 309,551 241,248,512,346 2,412,485 2,722,036
============== ========== ================ =========== ==========
No GBP No GBP GBP
Ordinary Ordinary Deferred Deferred Total
shares of shares shares of shares share
0.02p each of 0.02p 0.001p each of 0.001p capital
each each
Issued and fully paid
At 1 January 2018 1,336,317,797 267,265 241,248,512,346 2,412,485 2,679,750
On 3 May 2018 the Company
issued 211,428,572 shares
at 0.35p each 211,428,572 42,286 - - 42,286
As at 31 December 2018 1,547,746,369 309,551 241,248,512,346 2,412,485 2,722,036
============== ========== ================ =========== ==========
7. Distribution on interim report to shareholders
The interim report will be available for inspection by the
public at the registered office of the company during normal
business hours on any weekday and from the Company's website
http://www.edenville-energy.com/. Further copies are available on
request.
This information is provided by RNS, the news service of the
London Stock Exchange. RNS is approved by the Financial Conduct
Authority to act as a Primary Information Provider in the United
Kingdom. Terms and conditions relating to the use and distribution
of this information may apply. For further information, please
contact rns@lseg.com or visit www.rns.com.
END
IR BUGDCCSDBGCL
(END) Dow Jones Newswires
September 27, 2019 02:00 ET (06:00 GMT)
Edenville Energy (LSE:EDL)
Historical Stock Chart
From Mar 2024 to Apr 2024
Edenville Energy (LSE:EDL)
Historical Stock Chart
From Apr 2023 to Apr 2024