Operational Update (7988E)
April 13 2011 - 2:00AM
UK Regulatory
TIDMWTI
RNS Number : 7988E
Weatherly International PLC
13 April 2011
Weatherly International Plc ("Weatherly" or the "Company")
Operational Update
Highlights
-- First 500 tonne consignment of copper concentrate delivered
to Louis Dreyfus
-- Production for remainder of year estimated at 4,500 - 5,000
tonnes
-- Company to issue quarterly production reports commencing July
2011
-- Metallurgical test work on Tschudi ore nearing completion
Central Operations
Weatherly is pleased to announce that its first 500 tonne
consignment of copper concentrate has been delivered to the buyer,
Louis Dreyfus Commodities, at the port of Walvis Bay. As previously
announced mining activities resumed in January, although there have
been some delays with the mobilisation of the haulage contractor
who only finally commenced trucking late in March.
Fortunately, these transport delays and a prolonged rainy season
have had little effect on the overall mine "ramp-up" and there is
no change to the previous production forecast of 4,500 - 5,000
tonnes of copper for the remainder of the year. We expect the mine
to be profitable in the current quarter and this will be reflected
in the Company's annual accounts for the year ending June 30, 2011
to be issued later in the year. We also intend to commence issuing
quarterly production reports and the first of these will be
published in July 2011.
Tschudi and Tsumeb
At Tschudi (43mt at 0.83% Cu& 10g/tAg), preliminary
metallurgical work to determine the optimum process route is
reaching its conclusion. Sedgman Engineering is evaluating three
process routes as part of the feasibility study. The first route is
to heap leach all ore types from the open pit using acid and then
process the ore using the SX-EW process to produce an LME-grade
copper cathode. The second route, which has the advantage of
recovering the silver, would utilise conventional flotation to
produce a copper-silver concentrate which would be sold on to
smelters. A third alternative which incorporates the retreatment of
the old Tsumeb tailings is also being investigated. In this regard,
drilling of the Tsumeb tailings has been completed and assay
results are expected towards the end of May. This will enable
Coffey Mining to complete a fully compliant resource statement.
For further information, please contact:
Rod Webster, Chief Executive Officer, Weatherly International
Plc
+44 (0) 20 7917 2989
Samantha Harrison / Jen Boorer, Ambrian Partners Limited
+44 (0) 20 7634 4700
Carina Corbett, 4C Communications (Investor Relations)
+44 (0) 20 3170 7973
This information is provided by RNS
The company news service from the London Stock Exchange
END