Atlantis Resources Limited Completion of MeyGen Horizontal Drilling Programme
July 24 2015 - 7:16AM
RNS Non-Regulatory
TIDMARL
Atlantis Resources Limited
24 July 2015
Atlantis Resources Limited
("Atlantis" or the "Company")
Completion of Horizontal Drilling Programme - MeyGen
Atlantis, a global leader in the tidal power sector, is pleased
to announce that all of the horizontal directional drilling ("HDD")
works for MeyGen Phase 1A have now been completed on time for the
cable installation.
Four bore holes were drilled at a distance of 570 meters
underground to within 2m of their exit target offshore which is a
significant engineering achievement and a milestone for this
flagship project.
The installation of the offshore submarine cable can now
commence during the summer.
The HDD work package has been completed on time and with no
reported incidents or injuries.
Enquiries:
Atlantis Resources +44 (0)20 3727 1000
Tim Cornelius, Chief Executive Officer
Duncan Black, Chief Financial Officer
Peel Hunt LLP (Nominated Adviser and
Broker) +44 (0)20 7418 8900
Daniel Harris
Jock Maxwell Macdonald
Euan Brown
FTI Consulting +44 (0)20 3727 1000
Ben Brewerton
Alex Beagley
Stephanie Blott
James Styles
This information is provided by RNS
The company news service from the London Stock Exchange
END
NRAPGUAGMUPAGGC
Atlantis (LSE:ARL)
Historical Stock Chart
From Mar 2024 to Apr 2024
Atlantis (LSE:ARL)
Historical Stock Chart
From Apr 2023 to Apr 2024