Ascent Resources PLC Operational Update-commencement of test production (0748N)
August 04 2017 - 2:00AM
UK Regulatory
TIDMAST
RNS Number : 0748N
Ascent Resources PLC
04 August 2017
4 August 2017
Ascent Resources plc
("Ascent" or the "Company")
Operational Update - commencement of test production
The Board of Ascent Resources plc (AIM: AST), the European
focused oil & gas exploration and production company, is
pleased to provide an update on progress with its Petišovci project
in Slovenia.
Infrastructure to produce to INA
The installation of the necessary infrastructure to accommodate
export production has now been completed.
The operational certificate has been received for the pipeline
from the CPP to the export line.
Refurbishment of the separation equipment at the CPP has
completed. The refurbished separator has been installed and
connected to the existing plant. To complete testing, we will
switch the current flow of gas from Pg-10 through the refurbished
infrastructure this morning (Friday 4(th) August). This gas will
continue to be sold locally during testing.
Our customer, INA, has received initial positive feedback from
the authorities in relation to the re-certification of its pipeline
on the Croatian side of the border. The authority has asked for
clarification on a number of points which we have been advised
should be completed shortly. Once the recertification has been
finalised production of gas to INA will commence.
Well Pg-11A
The service company which has been contracted to complete the
operations at well Pg-11A arrived on-site on 1 August after
procuring the required tooling, we have made good progress over the
past few days and will provide a further update in due course. Once
this final operation has been completed the well will be connected
through to the CPP via the flowline which has already been
constructed.
Colin Hutchinson, CEO, commented:
"We are pleased that the infrastructure to produce is now ready
and that the recertification on the Croatian side of the border is
moving towards a positive conclusion."
Enquiries:
Ascent Resources plc
Clive Carver, Chairman 0207 251
Colin Hutchinson, CEO 4905
Stockdale Securities Limited, Nominated
Adviser and Joint Broker
Richard Johnson 0207 601
Edward Thomas 6100
Northland Capital Partners Limited,
Joint Broker 0203 861
Tom Price 6625
Abchurch, Financial PR and IR 0207 398
Tim Thompson 7700
This information is provided by RNS
The company news service from the London Stock Exchange
END
MSCPJMATMBBMBTR
(END) Dow Jones Newswires
August 04, 2017 02:00 ET (06:00 GMT)
Ascent Resources (LSE:AST)
Historical Stock Chart
From Mar 2024 to Apr 2024
Ascent Resources (LSE:AST)
Historical Stock Chart
From Apr 2023 to Apr 2024