Pan African Resources Plc Operational Update quarter ended 30/09/18
November 06 2018 - 2:00AM
UK Regulatory
TIDMPAF
Pan African Resources PLC
("Pan African" or "the company" or "the group")
(Incorporated and registered in England and Wales under Companies Act 1985 with
registered number 3937466 on 25 February 2000)
Share code on AIM: PAF
Share code on JSE: PAN
ISIN: GB0004300496
OPERATIONAL UPDATE FOR THE QUARTER ENDED 30 SEPTEMBER 2018
Pan African is pleased to provide an operational update for the first quarter
of the 2019 financial year ("this quarter" or "first quarter"), and further
information on the performance of the Elikhulu Tailings Retreatment Plant
("Elikhulu").
Pan African CEO Cobus Loots commented:
"Pan African recorded a commendable safety and production performance for the
first quarter of the 2019 financial year. The group produced 37,729oz of gold
during the quarter, and with Elikhulu now commissioned and running at design
capacity, we are confident of achieving our production guidance of
approximately 170,000oz for the 2019 financial year.
Elikhulu ramped-up to its design capacity of 1-million tonnes per month during
October 2018, ahead of the original schedule and on budget. Average gold
recoveries achieved were consistent with our forecasts, with further
optimisation of recoveries expected in the short term. The incorporation of the
Evander Tailings Retreatment Plant ("ETRP") into Elikhulu, which will increase
Elikhulu's capacity to 1.2-million tonnes per month, is progressing on
schedule, with full commissioning expected to be completed by January 2019.
Barberton Mines is on track to meet its full-year production guidance of
100,000oz, with the underground operations' production benefitting from
Fairview Mine's high-grade 272 and 358 platforms, and the newly installed
regrind mill at the Barberton Tailings Retreatment Plant ("BTRP") performing as
anticipated.
At Evander Mines, we have commenced mining and vamping of the remnant
high-grade stopes as part of the phased closure of the underground mining
operations as an initiative to supplement Evander Mines' production, while
commencing with the equipping and preparatory work to advance the mining of the
8 Shaft pillar and high-grade areas in proximity to the pillar. The first phase
of the equipping and preparatory work is expected to be completed in the third
quarter of the 2019 financial year.
The drilling programme on Barberton Mines' Royal Sheba prospect has been
completed, and we look forward to updating shareholders on the progress of this
exciting growth project in the coming months with an updated resource statement
to be released by the end of November 2018, and the feasibility study still on
schedule for release in February 2019."
Safety
The group has significantly improved its safety performance in the first
quarter, and we remain committed and focussed to ensuring the safety of all our
employees, while we continue to strive towards a zero harm environment.
* Fairview Mine achieved its one-million fatality-free shift milestone during
July 2018;
* The group had no fatalities in this quarter (2018 Q1: no fatalities);
* The group's lost-time injury frequency rate improved significantly to 0.57
(2018 Q1:3.64);
* The reportable injury frequency rate improved significantly in this quarter
to zero (2018 Q1: 0.91); and
* The group is implementing recommendations from independent safety experts,
following reviews of the respective mining operations' safety systems and
controls.
Elikhulu
* As previously communicated, Elikhulu was successfully commissioned during
September 2018, ahead of the original project schedule and on budget;
* During October 2018, the plant attained steady-state production with a
throughput of 1-million tonnes per month. The average gold recoveries
achieved were consistent with our forecasts, with further optimisation of
recoveries expected in the next months; and
* The incorporation of the existing ETRP throughput into Elikhulu's
processing capacity, which will result in an increased processing capacity
of 1.2-million tonnes per month, is on track with full commissioning
expected to be completed by January 2019.
* Barberton Mines Proprietary Limited ("Barberton Mines")
* Barberton Mines produced 27,201oz for this quarter, with underground mining
operations contributing 21,278oz, and the BTRP contributing 5,923oz.
Barberton Mines remains on track to deliver its annual production guidance
of approximately 100,000oz for the 2019 financial year.
* Barberton Mines' underground operations are benefitting from increased
underground mining flexibility due to, inter alia, both the high-grade 272
and 358 platforms being available at the Fairview Mine operation. The BTRP
is also benefiting from the commissioning of the regrind mill during May
2018, which has improved throughput and recoveries.
* Barberton Mines has increased development rates to further improve Fairview
Mine's mining flexibility at the 11-block by developing towards an
additional high-grade platform (256 platform), below the existing 272 and
358 platforms. This platform is expected to be in production by the end of
the 2019 financial year.
Evander Gold Mines Proprietary Limited ("Evander Mines")
* Evander Mines has implemented the following initiatives to maximise Evander
Mines' underground gold production:
1. Mining and vamping of the remnant high-grade stopes as part of the phased
closure of the underground mining operations, which contributed 3,815oz
during this quarter; and
2. While the above operations are ongoing, the mine has commenced equipping
and preparatory work to advance mining of the 8 Shaft pillar and high-grade
areas in proximity to the pillar, following a comprehensive review on the
technical merits thereof. The first phase of the equipping and development
of the 8 Shaft pillar and surrounding areas is estimated to be completed in
the third quarter of the 2019 financial year.
* The ETRP and surface-source operations produced 3,819oz for this quarter,
and the operation is investigating new sources of feed for the Kinross
plant, once the ETRP operation is integrated into Elikhulu.
The financial information contained in this announcement has neither been
reviewed nor audited by the company's auditors and is the responsibility of the
directors of Pan African.
For further information on Pan African, please visit the company's website at
www.panafricanresources.com
6 November 2018
Contact information
Corporate Office Registered Office
The Firs Office Building Suite 31
2nd Floor, Office 201 Second Floor
Cnr. Cradock and Biermann Avenues 107 Cheapside
Rosebank, Johannesburg London
South Africa EC2V 6DN
Office: + 27 (0) 11 243 2900 United Kingdom
Facsimile: + 27 (0) 11 880 1240 Office: + 44 (0) 20 7796 8644
Facsimile: + 44 (0) 20 7796 8645
Cobus Loots Deon Louw
Pan African Resources PLC Pan African Resources PLC
Chief Executive Officer Financial Director
Office: + 27 (0) 11 243 2900 Office: + 27 (0) 11 243 2900
Phil Dexter John Prior / Paul Gillam
St James's Corporate Services Numis Securities Limited
Limited Nominated Adviser and Joint Broker
Company Secretary Office: +44 (0) 20 7260 1000
Office: + 44 (0) 20 7796 8644
Sholto Simpson Ross Allister/James Bavister/David
One Capital McKeown
JSE Sponsor Peel Hunt LLP
Office: + 27 (0) 11 550 5009 Joint Broker
Office: +44 (0) 20 7418 8900
Julian Gwillim Jeffrey Couch/Thomas Rider
Aprio Strategic Communications BMO Capital Markets Limited
Public & Investor Relations SA Joint Broker
Office: +27 (0)11 880 0037 Office: +44 (0) 20 7236 1010
Bobby Morse
Buchanan
Public & Investor Relations UK
Office: +44 (0)20 7466 5000
Email: PAF@buchanan.uk.com
Website: www.panafricanresources.com
END
(END) Dow Jones Newswires
November 06, 2018 02:00 ET (07:00 GMT)
Pan African Resources (LSE:PAF)
Historical Stock Chart
From Apr 2024 to May 2024
Pan African Resources (LSE:PAF)
Historical Stock Chart
From May 2023 to May 2024