Q3 2021 Production Report

W Resources Plc (AIM:WRES), the tungsten, tin and gold mining company with assets in Spain and Portugal, announces its Q3 2021 quarterly production report for the La Parrilla mine in Spain, a period in which the Company achieved record tungsten recovery rates, grades and production.

Q3 Highlights

-- Tungsten recovery rate of 58% up from 47% in Q2 2021 and tungsten concentrate recovery grades of 66.7% up 3% on Q2 2021

   --        Tungsten production of 168.3 tonnes ("t") up 58% on Q2 2021 

-- 11 shipments made - nine tungsten concentrate shipments (180t) and two tin concentrate shipments (40.8t)

   --        Construction of the second water dam underway with target completion in November 2021 
   --        Robust commodity pricing with tungsten and tin increasing in the period 
   --        Plant utilisation remains high at 87.1% compared to 88.2% in Q2 2021 
   --        Moved to a 24 / 7 operation on 7 September 2021 

Key Metrics

   --        A total of 279,196t of Run of Mine ("ROM") ore fed to the La Parrilla plant in Q3 2021 
   --        Total tungsten and tin concentrate production of 192.4t 
   --        Tungsten ("WO(3) ") concentrate production of 168.3t 
   --        Tin ("Sn") concentrate production of 24.1 dry metric tonnes ("dmt") 

La Parrilla Production Summary

Whilst Q3 2021 recorded a number of record performance milestones, production was impacted by a number of challenges which resulted in an estimated production loss of circa 40t of tungsten concentrate, including:

-- A number of power outages were caused by technical problems with the LNG generators. This has been resolved by the supplier after isolating the cause of the stoppages. To mitigate against future power outages the Company is installing an additional connection to the grid power supply. This is expected to be finalised in 2022 and will supply sufficient electricity to power the entire plant.

The pro-rata below adjusts for the variance in production days.

 
                               Q3 2021   Q2 2021     Variance   Variance 
 La Parrilla Production         Actual    Actual   Comparison   Pro rata 
  Summary 
---------------------------  ---------  --------  -----------  --------- 
 WO(3) contained metal 
  (mtu)                         11,229     6,919        62.3%      18.4% 
 Sn contained metal (dmt)         12.5      12.4         0.8%     -26.4% 
 Total contained metal 
  (dmt)                          124.8      81.6        53.0%      11.6% 
---------------------------  ---------  --------  -----------  --------- 
 ('dmt' - dry metric tonnes, 'mtu' - metric tonne unit (1 mtu = 
  10kg of contained metal)) 
 

Michael Masterman, Chairman of W Resources , commented: "Q3 2021 was our best performing quarter to date and we expect to see this growth continue as we head towards the end of the year. Notwithstanding a number of challenges towards the end of the quarter, the result is testament to the management team at the La Parrilla mine which reacted quickly to minimise any disruption.

"In September, the Extremadura region of Spain, where the La Parrilla mine is located, experienced torrential rain fall for a period of time. Although the mine continued to work, production did slow due to the wet feed being fed into the plant. The team at La Parrilla is looking to introduce a silo to hold a minimum of one weeks' supply of dry stock which should negate the problems caused by similar flash flooding.

"Work at the mine has continued with new staff recruited and the introduction of a 24 / 7 operation seeing activities increase throughout the mine. In Q3 2021, work commenced on the second water dam which we expect will be completed in November 2021 and will serve to protect the mine from further water issues.

"Work continues apace and the La Parrilla team has a clear focus on increasing production and efficiencies as the reality of continuous production becomes the norm. "

Q3 2021 Overview

The final phase of the project to provide a permanent solution to the water issues at La Parrilla, comprising of a second dam, is currently underway and is expected to be completed in November.

The recovery rate for tungsten during Q3 2021 was 58%, the highest to date for any quarter notwithstanding further work is needed to improve tin recoveries.

ROM feed increased to 279,196t for the quarter, another record and up 21% on Q2 2021.

11 shipments of concentrate were made during Q3 2021, almost doubling the number of shipments made in Q2 2021.

 
                                 Q3 2021   Q2 2021     Variance   Variance 
 La Parrilla Production           Actual    Actual   Comparison   Pro rata 
  Summary 
-----------------------------   --------  --------  -----------  --------- 
 
 ROM feed: tonnes mined 
  (wmt)                          279,196   231,613          21%       -12% 
 Strip ratio                        3.53      2.89          22% 
 Jig plant: tonnes processed 
  (dmt)                          207,327   173,901          19%       -13% 
 
 WO(3) feed grade (ppm)              934       855           9% 
 WO(3) recovery (%)                  58%       47%          23% 
 WO(3) concentrate (dmt)           168.3     106.4          58%        15% 
 WO(3) concentrate grade 
  (%)                               66.7      65.0           3% 
 WO(3) contained metal 
  (mtu)                           11,229     6,919          62%        18% 
 
 Sn feed grade (ppm)                 263       259           2% 
 Sn recovery (%)                     23%       27%         -15% 
 Sn concentrate (dmt)               24.1      23.8           1%       -26% 
 Sn concentrate grade 
  (%)                               51.9      51.9           0%       -27% 
 Sn contained metal (dmt)           12.5      12.4           1%       -26% 
 
 Total concentrate (dmt)           192.4     130.2          48%         8% 
 Total contained metal 
  (dmt)                            124.8      81.6          53%        12% 
------------------------------  --------  --------  -----------  --------- 
 

Recovery

Tungsten recovery increased by 23% during Q3 2021, rising from 47% to 58%, although tin recovery fell by 15% from 27% to 23%.

Health and Safety

During the period there were three serious and one minor accident and three reported Covid-19 incidences. The Company believes its robust measures for controlling entry to and from the mine help in reducing Covid-19 events. Additional training is always provided to employees following serious accidents at the mine.

Plant Utilisation

Plant utilisation decreased to 87% slightly down from 88% in Q2 2021 - adversely impacted by the number of power outages experienced during the quarter.

Shipments

Nine shipments of tungsten concentrate totalling 180t and two shipments of tin concentrate totalling 40.8t were completed in Q3 2021.

 
                         Q3 2021   Q2 2021     Variance   Variance 
 La Parrilla Shipment     Actual    Actual   Comparison   Pro rata 
  Summary 
----------------------  --------  --------  -----------  --------- 
 Tungsten concentrate 
  (t)                      180.0     100.0          80%        31% 
 Tin concentrate (t)        40.8      19.3         111%        54% 
----------------------  --------  --------  -----------  --------- 
 

Commodity Pricing

European ammonium paratungstate ("APT") pricing remains strong and has further increased to US$315-320 as at 15 October 2021 - Fastmarkets MB.

The LME Tin price continues to strengthen reaching a three-month forward price of US$37,875 per tonne as per Fastmarkets MB, 14 October 2021.

Production Guidance

The Company is leasing a water treatment plant to improve water quality in the feed to the process plant and expects this measure to reduce maintenance issues and improve productivity.

Associated maintenance issues and supply chain bottlenecks for replacement parts have led to lower plant availability and as a result W Resources has adjusted its full year production guidance to between 650t and 750t of concentrate.

The Company expects Q4 2021 production to be greater than Q3 2021 production. However, production volumes will not reach the T2 run rate until Q1 2022.

The months of August and September were both EBITDA positive for W's operating subsidiary Iberian Resources Spain ("IRS") and the Company firmly expects Q4 2021 to be EBITDA positive as well for IRS with the mine at La Parrilla increasing production as the quarter progresses.

Employees

The number of staff employed at La Parrilla mine as at 30 September 2021 was 124 compared to 90 as at 30 June.

The historic La Parrilla mine production summary is as follows:

 
 La Parrilla Historic     Q1 2020   Q2 2020   Q3 2020   Q4 2020   Q1 2021   Q2 2021   Q3 2021 
  Production 
 Summary                   Actual    Actual    Actual    Actual    Actual    Actual    Actual 
-----------------------  --------  --------  --------  --------  --------  --------  -------- 
 No. of working days                               39        52        45        54        74 
 
 ROM feed: tonnes 
  mined (wmt)             273,656   253,256   171,454   261,841   196,094   231,613   279,196 
 Strip ratio                 1.07      0.58      1.38      1.19      5.13      2.89      3.53 
 Jig plant: tonnes 
  processed (dmt)         240,926   228,060   148,417   236,677   163,866   173,901   207,327 
 
 WO(3) feed grade 
  (ppm)                       800       845       857       943       744       855       934 
 WO(3) recovery (%)           17%       16%       30%       31%       32%       47%       58% 
 WO(3) concentrate 
  (dmt)                      58.9      47.6      54.7       100      63.5     106.4     168.3 
 WO(3) concentrate 
  grade (%)                  56.1      57.4      69.8      67.0      61.6      65.0      66.7 
 WO(3) contained metal 
  (mtu)                     3,306     2,756     3,820     6,698     3,916     6,919    11,229 
 
 Sn feed grade (ppm)          282       307       181       321       228       259       263 
 Sn recovery (%)              22%       25%       37%       26%       44%       27%       23% 
 Sn concentrate (dmt)        23.3      41.2      22.9      33.4      28.9      23.8      24.1 
 Sn concentrate grade 
  (%)                        51.9      48.5      42.7      56.3      56.6      51.9      51.9 
 Sn contained metal 
  (dmt)                      12.1      20.0       9.8      18.8      16.3      12.4      12.5 
 
 Total concentrate 
  (dmt)                      82.2      88.8      77.6     133.4      92.4     130.2     192.4 
 Total contained metal 
  (dmt)                      45.2      47.6        48      85.8      55.5      81.6     124.8 
-----------------------  --------  --------  --------  --------  --------  --------  -------- 
 

Shipments

The historic tungsten and tin concentrate shipments from the La Parrilla mine are as follows:

 
                         Q1 2020   Q2 2020   Q3 2020   Q4 2020   Q1 2021   Q2 2021   Q3 2021 
                          Actual    Actual    Actual    Actual    Actual    Actual    Actual 
----------------------  --------  --------  --------  --------  --------  --------  -------- 
 Tungsten concentrate 
  (t)                       30.1      58.9      62.1     100.2      59.2     100.0     180.0 
 Tin concentrate 
  (t)                       20.2      20.6      38.1      26.1      20.0      19.3      40.8 
----------------------  --------  --------  --------  --------  --------  --------  -------- 
 

The information contained within this announcement is deemed to constitute inside information as stipulated under the retained EU law version of the Market Abuse Regulation (EU) No. 596/2014 (the "UK MAR") which is part of UK law by virtue of the European Union (Withdrawal) Act 2018. The information is disclosed in accordance with the Company's obligations under Article 17 of the UK MAR. Upon the publication of this announcement, this inside information is now considered to be in the public domain.

Enquiries:

 
 W Resources Plc                        Grant Thornton UK LLP 
  Paul Hailes                            Colin Aaronson / Harrison Clarke 
  investor@wresources.com                / Lukas Girzadas 
  www.wresources.com                     T: +44 (0) 20 7383 5100 
 Alternative Resource Capital / Shard   Alma PR 
  Capital                                Justine James 
  Alex Wood                              M: +44 (0) 7525 324431 
  T:+44 (0) 207 186 9004                 wres@almapr.co.uk 
  www.altrescap.com 
  Damon Heath 
  T:+44 (0) 207 186 9952 
  www.shardcapital.com 
 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.

END

DRLMBBATMTJTMMB

(END) Dow Jones Newswires

October 21, 2021 02:00 ET (06:00 GMT)

W Resources (LSE:WRES)
Historical Stock Chart
From Feb 2024 to Mar 2024 Click Here for more W Resources Charts.
W Resources (LSE:WRES)
Historical Stock Chart
From Mar 2023 to Mar 2024 Click Here for more W Resources Charts.