Progress on the Freda Rebecca expansion project has been slower than expected
mainly due to the bureaucracy of the Zimbabwe investment approval system,
sourcing materials and spares, and construction skills availability.
Commissioning of the new and refurbished tankage should start in second quarter
of 2007 with ramp up to 60,000 tons of ore and 4,000 ozs of gold per month.