Silver Standard Resources Inc. (TSX:SSO)(NASDAQ:SSRI) ("Silver
Standard" or the "Company") announced today the results of the
Feasibility Study for its 100% owned Pitarrilla Project
("Pitarrilla" or the "Project") located in the State of Durango,
Mexico. The Feasibility Study was completed by M3 Engineering and
Technology Corporation and Silver Standard.
Feasibility Study highlights(1)
-- Silver Mineral Reserves: Probable Mineral Reserves of 479 million ounces
of silver, approximately 5.2x the 91.7 million ounces reported
previously.
-- Long-life and high production: A 32-year project producing an average of
15 million ounces of silver per year during the first 18 years of
production.
-- Robust project economics: An after-tax net present value (NPV) of $737
million at base case metal prices and $1.7 billion at spot prices. An
after-tax internal rate of return (IRR) of 12.8% at base case metal
prices and 21.2% at spot prices.
-- Capital expenditures: Total construction costs of $741 million,
including $157 million of pre-production operating costs and $131
million of pre-production revenue.
-- Low technical risk: Utilizes standard truck-and-shovel open-pit mining
methods and well-established flotation and leach processing methods.
"The completion of the Pitarrilla Feasibility Study represents a
major milestone for the Company," said John Smith, President and
CEO of Silver Standard. "In adopting an open-pit mining concept, we
have defined one of Mexico's largest silver mines and substantially
increased silver reserves. We are now actively engaged in
activities to bring the project into construction. While
recognizing Silver Standard's strong balance sheet, we are also
looking to secure financing for the project. Our aim is to have the
project ready for a construction decision in 2013."
(1) See the Company's September 21, 2009 NI 43-101 Technical
Report filed on SEDAR and the Company's website. NPV calculated
using a 5% discount rate. All financial metrics and estimates are
based on U.S. dollars. Base case metal prices: $27.50 per ounce
silver in the final pre-production year and the first two years of
production, and $25.00 per ounce silver thereafter; $0.90 per pound
of lead and $0.95 per pound of zinc. Spot case metal prices:
November 23, 2012, closing prices of $34.13 per ounce of silver,
$0.99 per pound of lead and $0.87 per pound of zinc.
Economic analysis
The Pitarrilla Feasibility Study indicates strong economic
returns and high leverage to silver prices. The metal price
assumptions and key financial estimates for the project are
presented in Table 1.
----------------------------------------------------------------------------
Table 1: Key financial estimates for the Pitarrilla Project
----------------------------------------------------------------------------
Financial Base Upside Downside Spot Price
metrics Case Case Case Case
----------------------------------------------------------------------------
Silver Price $/oz $25.00 $30.00 $22.50 $34.13
Lead Price $/lb $0.90 $1.10 $0.80 $0.99
Zinc Price $/lb $0.95 $1.10 $0.85 $0.87
Diesel Price $/litre $0.80 $0.95 $0.70 $0.85
$MXN per $USD 12.50 12.50 12.50 12.96
Pre-tax NPV 5% $M $1,176 $1,972 $680 $2,552
After-tax NPV 5% $M $737 $1,316 $368 $1,741
Pre-tax IRR % 15.8% 20.8% 11.5% 25.3%
After-tax IRR % 12.8% 17.2% 9.1% 21.2%
Undiscounted Cash
Flow $M $2,015 $3,187 $1,328 $3,948
Payback After COD Years Year 7.4 Year 4.8 Year 10.4 Year 3.8
----------------------------------------------------------------------------
Notes: (1) Base case silver price is $27.50 per ounce in the final pre-
production year and the first two years of production, and $25 per ounce
thereafter, (2) The MXN:USD exchange rate is assumed to equal $12.86 in the
second half of 2013 and the first half of 2014, $12.58 in the second half of
2014 and the first half of 2015 and $12.50 thereafter, (3) COD means
Commercial Operation Date.
Project overview
The Feasibility Study evaluates the development and construction
of an open-pit mine, processing facilities, a tailings storage
facility and supporting infrastructure. Pitarrilla will be one of
the largest silver mines in Mexico, producing an estimated 333
million ounces of silver, 582 million pounds of lead and 1,669
million pounds of zinc over a 32 year project life. The mine will
produce an average of 15 million ounces of silver per year during
the first 18 years of production.
Pitarrilla will use a standard truck and shovel open-pit mining
method. A fleet of trucks is expected to haul an average of over
175,000 tonnes of material per day over 20 years. The plant will
use standard grind, float and agitated leach circuits to process
16,000 tonnes per day of flotation/leach ore or 12,000 tonnes per
day of direct leach ore. The Project will produce lead and zinc
concentrates and a silver dore.
Pitarrilla is located approximately 160 kilometres
north-northwest of the city of Durango. A paved roadway extends to
within 47 kilometres of the plant site. The Company has been
advised by the Comision Federal De Electricidad, Mexico's national
power utility, that it will provide power for the Project via a new
powerline.
Mineral Resource estimate
This updated Mineral Resource estimate is based on all available
data for the Pitarrilla deposit, including the results from over
15,000 meters of drilling performed at the Project during 2012.
----------------------------------------------------------------------------
Table 2: Pitarrilla Mineral Resource estimate (effective as of December 4,
2012)
----------------------------------------------------------------------------
Cut-off Ag Tonnes Ag Pb Zn Ag Pb Zn
Category (g/t) (Mt) (g/t) (%) (%) (Moz) (Mlbs) (Mlbs)
----------------------------------------------------------------------------
Measured 20.00 23.62 85.56 - - 65 - -
---------------------------------------------------------------
30.00 20.31 95.42 - - 62 - -
---------------------------------------------------------------
40.00 16.90 107.62 - - 58 - -
----------------------------------------------------------------------------
Indicated 30.00 240.00 81.94 - - 632 - -
---------------------------------------------------------------
40.00 199.61 91.41 - - 587 - -
---------------------------------------------------------------
20.00 292.35 - 0.31 0.71 - 2,009 4,581
---------------------------------------------------------------
30.00 260.31 - 0.32 0.72 - 1,815 4,146
---------------------------------------------------------------
40.00 216.51 - 0.33 0.75 - 1,574 3,590
----------------------------------------------------------------------------
Measured +
Indicated 30.00 260.31 82.99 0.32 0.72 695 1,815 4,146
---------------------------------------------------------------
40.00 216.51 92.68 0.33 0.75 645 1,574 3,590
----------------------------------------------------------------------------
Inferred 20.00 26.48 55.98 0.21 0.48 48 123 281
---------------------------------------------------------------
30.00 22.08 62.12 0.21 0.49 44 101 236
---------------------------------------------------------------
40.00 17.09 70.00 0.21 0.49 38 79 186
----------------------------------------------------------------------------
Notes:
1. Jeremy D. Vincent, B.Sc. (Hons), P.Geo., is the Qualified Person for the
reported Mineral Resources estimate.
2. All Mineral Resource estimates have been classified in accordance with
current Canadian Institute of Mining, Metallurgy and Petroleum (CIM)
definition standards.
3. Ag was estimated using Localised Uniform Conditioning (LUC). Pb and Zn
were estimated using Ordinary Kriging (OK).
4. Mineral Resource estimates of Pb and Zn are not classified as Measured
to account for the added uncertainty introduced by the volume-variance
effect when using different estimation techniques (Ag by LUC; Pb and Zn
by OK).
5. A silver cut-off grade of 30 g/t Ag is considered at this time to be the
most likely economic cut-off grade for large-scale open- pit mining of
the Pitarrilla deposit.
6. Silver capping (top cut) grades used in the estimation ranged between
400 g/t Ag and 1,700 g/t Ag for the various oxide domains, and between
960 g/t Ag and 1,150 g/t Ag for the two transitional domains, and
between uncapped and 1,200 g/t Ag for the various sulphide domains. Lead
capping grades used in the estimation ranged between uncapped and 3.6%
Pb for the various oxide domains, between 3.6% Pb and 3.8% Pb for the
transitional domains, and between uncapped and 6.7% Pb in the various
sulphide domains. Zinc capping grades used in the estimation ranged
between 0.56% Zn and 4.8% Zn in the various oxide domains, between 6.4%
Zn and 7.1% Zn in the transitional domains, and between uncapped and
17.7% Zn in the various sulphide domains.
7. Detailed bulk density modeling was conducted taking into account
lithological variability (including an analysis of voids),
mineralization, and degree of oxidation.
8. The drillhole database including collar, survey, assay, lithology,
oxidation, and bulk density, used in the preparation of the Mineral
Resources estimate was verified by Mr. Vincent by conducting detailed
verification checks, including QA/QC of location and assay data.
9. The reported Measured and Indicated Mineral Resources are regarded as
sufficient for medium to long term production open pit planning and mine
scheduling on a quarterly basis. Grade control drilling and a mine
blending strategy to control grade variations are recommended for short-
term mine planning.
10. Mineral Resources situated below the current open-pit shell design are
considered potentially economically viable in an underground mining
scenario, and are therefore included in the total reported Pitarrilla
Mineral Resources. A Preliminary Economic Assessment (PEA) or higher
level study validating the economics of the underground mining scenario
has not been undertaken at this time.
11. Mineral Resources that are not Mineral Reserves do not have demonstrated
economic viability. While the classification categories of Mineral
Resources used in this news release are recognized and required under
Canadian regulations, the U.S. Securities and Exchange Commission (SEC)
does not recognize them and U.S. companies are generally not permitted
to disclose resources in documents they file with the SEC.
12. The reported tonnes, grade, and metal content may not tally precisely
due to rounding.
Mineral Reserve estimate
The Company has prepared an updated Mineral Reserve estimate for
Pitarrilla. Under the estimate, Probable Mineral Reserves of silver
have increased to 479 million ounces of silver at Pitarrilla, 5.2
times the 91.7 million ounces reported in the Company's September
21, 2009 NI 43-101 Technical Report.
Table 3: Pitarrilla Mineral Reserve estimate (effective as of December 4,
2012)
----------------------------------------------------------------------------
Tonnage Mined Grade Contained Metal
----------------------------------------------------------------------------
Ag Pb Zn Ag Pb Zn
Category Process Type (Mt) (g/t) (%) (%) (Mozs) (Mlbs) (Mlbs)
----------------------------------------------------------------------------
Probable Direct Leach 43.4 91.5 0.169 0.422 127.5 161.6 403.9
----------------------------------------------------------------------------
Probable Flotation/Leach 113.2 96.5 0.341 0.929 351.2 851.8 2,317.7
----------------------------------------------------------------------------
Notes:
1. Andrew W. Sharp, B.Eng, FAusIMM, is the Qualified Person for the
reported Mineral Reserve estimate.
2. All Mineral Reserves have been classified in accordance with current CIM
definition standards.
3. Mineral Reserves are contained within Measured and Indicated Resources
with a pit design using metal prices for silver, lead and zinc of
US$25/oz, US$0.90/lb, and US$0.95/lb, respectively.
4. The pit designs are generated from appropriate mining costs, processing
costs, metal recoveries and inter ramp pit slope angles (varying from 36
degrees to 48 degrees).
5. The Mineral Reserves estimate uses a net smelter return (NSR)
calculation to determine the cut-off. The Mineral Reserves estimate
contains two ore types - direct leach ore and flotation/leach ore. There
are two different cut-off values: the constant cut-off value for direct
leach ore is $16.38/tonne, and for flotation/leach ore is $16.40/tonne.
6. The NSR calculation method varies for the two ore types. For the two ore
types combined, the overall average process recovery of silver, lead and
zinc are 69.6%, 57.4% and 61.3% respectively.
a. For flotation/leach ore, the NSR is estimated based on recoveries
that vary by head grade for Ag, Pb and Zn and are also reduced in
performance depending on the amount of oxidation present.
Concentrate grades also vary by oxidation and head grades. NSR
estimates are inclusive of transport costs, penalties and refinery
charges. The NSR of this ore type is augmented by the addition of
cyanide leach of the flotation tail, net of leach process costs and
dore sales and refining costs.
b. For direct leach ore, the NSR is estimated from the silver head
grade, the silver recovered from the cyanide leach process and the
applicable dore sales costs and refining costs. The cyanide leach
silver recovery is directly estimated in the model from assays and
metallurgical testing.
7. No mining dilution is applied to the grade of the resource. Dilution
intrinsic to the resource model is considered sufficient to represent
the mining selectivity considered.
8. The life of mine strip ratio is 5.96.
9. Tonnage and grade measurements are in metric units. Contained silver
ounces are reported as millions of troy ounces (Mozs). Contained lead
and zinc are reported as millions of imperial pounds (Mlbs).
10. The Reserve is 100% in-situ, as no mining of the ore has occurred.
11. Tables may not sum due to rounding.
Mining and processing
Pitarrilla will use standard truck and shovel open-pit mining
methods. The expected mining life is 20 years, including three
pre-production years. The pit will be mined in five phases,
starting with Breccia Ridge and Cordon Colorado. Over the life of
the Project, a fleet of trucks is expected to haul approximately
1.1 billion tonnes of material and 157 million tonnes of ore, at a
strip ratio of 5.96:1.
Pitarrilla's plant is expected to use standard crush, grind,
float and agitated leach equipment to process 16,000 tonnes per day
of float/leach ore or 12,000 tonnes per day of direct leach ore.
The two ore types will utilize a common crushing and grinding
circuit. Initially, highly-oxidized ore will be direct leached in
an agitated leach circuit. Silver will then be extracted from the
pregnant leach solution using the Merrill-Crowe process to produce
silver-rich dore bars. Subsequently, the less oxidized and
un-weathered sulphide ores will be processed in sequential lead and
zinc flotation circuits to produce separate silver-bearing lead and
zinc concentrates. Tailings from the flotation circuits will be
processed in the agitated leach circuit to recover additional
silver.
Over the Project's life, the plant is expected to produce an
estimated 604,000 tonnes of lead concentrate, with grades averaging
43% lead and 9,500 g/t silver, and an estimated 1.5 million tonnes
of zinc concentrate, with grades averaging 46% zinc and 604 g/t
silver. The leach circuit will produce 118.5 million ounces of
silver in silver- rich dore bars. Discussions and analysis to date
indicate that the lead and zinc concentrates may be sold
domestically or internationally to potential customers in Asia,
Europe and North America.
Table 4: Average production schedule for the Pitarrilla Project
----------------------------------------------------------------------------
Annual average Annual average Annual average
Production schedule Units (years 1-9) (years 10-18) (life of project)
----------------------------------------------------------------------------
Total mined Kt 74,631 35,457 33,039
Waste mined Kt 64,206 29,250 28,293
Ore mined Kt 10,425 6,207 4,745
Strip ratio 6.2 4.7 6.0
Silver grade mined g/t 93 97 95
Lead grade mined % 0.2 0.4 0.3
Zinc grade mined % 0.5 1.4 0.8
Lead concentrate Kt 17 42 18
Zinc concentrate Kt 30 119 46
Silver recovery % 66.7 83.1 69.6
Lead recovery % 49.0 75.2 57.4
Zinc recovery % 46.8 78.7 61.3
----------------------------------------------------------------------------
Silver produced Koz 14,090 15,852 10,102
----------------------------------------------------------------------------
- Dore Koz 5,659 2,587 3,591
- Concentrate Koz 8,431 13,265 6,511
Lead produced Klbs 15,044 43,639 17,633
Zinc produced Klbs 30,355 136,947 50,572
----------------------------------------------------------------------------
Note: Life of project averages calculated over the 32-year life of the
Project.
The potential to mine Mineral Resources located below the open
pit was not evaluated in the Pitarrilla Feasibility Study, but may
be evaluated later in the Project's lifecycle.
Capital cost
All Project costs incurred prior to the declaration of
commercial production are considered capital costs. The leach
circuit commences commissioning 26 months after the construction
decision, and achieves commercial production within ten months. The
total capital required to construct the mine is $741 million.
Table 5: Summary of anticipated capital costs (including contingency)
----------------------------------------------------------------------------
Capital costs Millions
----------------------------------------------------------------------------
Mine development and mobile equipment $155.7
Plant $308.3
Infrastructure $51.4
----------------------------------------------------------------------------
Direct costs $515.4
----------------------------------------------------------------------------
Indirect costs $80.9
Owners costs $37.3
----------------------------------------------------------------------------
Total indirect costs $118.2
----------------------------------------------------------------------------
Contingency $81.5
----------------------------------------------------------------------------
Construction capital $715.1
----------------------------------------------------------------------------
Pre-operating mine, plant and G&A $156.5
Pre-operating net revenue ($130.9)
----------------------------------------------------------------------------
Total pre-operating capital $740.6
----------------------------------------------------------------------------
Notes: (1) A contingency of 5% has been applied to mine equipment and to
light vehicles. (2) A contingency of 15% has been applied to all other
expenditures during the first two years of the pre-production period, with
the exception of capitalized operating mining cost which has the 15%
contingency applied only to the first year of pre-production. (3) The
capital cost estimates are based on second quarter 2012 pricing and will be
subject to inflation that may occur prior to the construction decision and
during the construction period.
Capital costs incurred after the start of commercial production
are considered sustaining capital costs. The sustaining capital for
the project is expected to be $404 million, including a $25 million
contingency. Sustaining capital for the plant is included in plant
operating costs, with the exception of a planned $45 million
flotation plant upgrade in year 16.
Table 6: Summary of sustaining capital costs
----------------------------------------------------------------------------
Sustaining capital costs Millions
Plant and infrastructure $6.1
Flotation plant upgrade $44.5
Mine equipment $254.0
Mine equipment - major components $50.2
Tailings impoundment sustaining capital $37.3
Vehicles/topsoil/water management $11.8
----------------------------------------------------------------------------
Total sustaining capital $403.9
----------------------------------------------------------------------------
Notes: (1) A contingency of 5% has been applied to mine equipment and to
light vehicles. (2) Sustaining capital for the plant is included in
operating costs, with the exception of a planned $45 million expansion of
the flotation plant in year 16.
Operating cost
Total operating costs on a per tonne of ore milled basis are
presented in Table 7.
Table 7: Summary of operating costs per tonne of ore milled
----------------------------------------------------------------------------
Operating costs Cost per tonne of ore
----------------------------------------------------------------------------
Mine operations $10.04
Mill operations $15.45
General administration $1.80
----------------------------------------------------------------------------
Total operating cost $27.29
----------------------------------------------------------------------------
Notes: Unit costs are expressed as dollars per tonne of combined ore milled.
The total cash operating cost includes mine operations, process
plant operations, general and administrative costs, smelting and
refining charges, and transportation charges. Total cash costs
(which also include direct process plant costs, administrative
costs, and other charges) average $10.01 per ounce of payable
silver (net of by-product revenues) over the Project's life. Total
production costs (which also include depreciation and amortization,
asset retirement obligations, and capitalized mine development and
pre-operating costs) average $15.91 per ounce of payable silver
over the Project's life. The cash costs are presented in Table
8.
Table 8: Total cash cost per payable ounce of silver
----------------------------------------------------------------------------
Annual Annual Annual
average average average
Operating costs (years 1-9) (years 10-18) (life of project)
----------------------------------------------------------------------------
Direct Mining
Cost $/oz Payable $3.91 $2.77 $2.93
Direct Process
Plant $/oz Payable $6.29 $6.32 $7.82
G&A $/oz Payable $0.67 $0.60 $0.81
----------------------------------------------------------------------------
Cash Operating
Cost $/oz Payable $10.87 $9.69 $11.56
----------------------------------------------------------------------------
Shipping and
Selling $/oz Payable $0.51 $1.60 $1.00
Treatment and
Refining $/oz Payable $1.91 $4.26 $2.91
By-Product
Credits $/oz Payable ($2.51) ($9.32) ($5.46)
----------------------------------------------------------------------------
Total Cash Cost $/oz Payable $10.78 $6.24 $10.01
----------------------------------------------------------------------------
Non-Cash Costs $/oz Payable $4.81 $8.37 $5.90
----------------------------------------------------------------------------
Total Production
Cost $/oz Payable $15.59 $14.61 $15.91
----------------------------------------------------------------------------
Notes: (1) Non-cash costs include a period of depreciation and amortization
of physical plant and equipment, asset retirement obligation assets, and
capitalized mine development and pre-operating costs. The depreciation is
compliant with IFRIC 20 relating to deferred stripping. (2) Life of project
averages calculated over the full 32 year life of the Project.
Environmental, permitting and social responsibility
Pitarrilla has been designed to comply with Mexican mining
regulations. An Environmental Impact Assessment (EIA) is expected
to be completed and ready for submission to Mexico's environmental
agency in the first half of 2013. Studies conducted at Pitarrilla
during the EIA preparation process include characterization of the
topography, geomorphology, geology, soils, water (surface water and
groundwater), climate, air quality, and flora and fauna. Several
environmental, land use, and operating permits and agreements are
required before construction begins.
Silver Standard has implemented a community relations program
that includes environmental, medical, educational, infrastructure
development, and social support services. This year, the Company
provided medical assistance to members of local communities,
completed clean-up projects around local rivers, planted trees and
completed construction projects to improve infrastructure
(including the installation of livestock fences, improvements to a
suspension bridge, improvements to a water well and the
installation of a media room at a local high school).
Next steps
Going forward, Silver Standard is focused on a number of key
activities to position the Project for a 2013 construction
decision. The Company will use the Feasibility Study as the basis
for further discussions with financial institutions and potential
partners. The Company will also continue to obtain the remaining
surface access rights necessary for the permitting, construction
and operation of the Pitarrilla Project. Applications for the
required mining or operating permits will be submitted after
receiving clear title or access agreements to all required land. At
the same time, the Company will continue optimizing the Project
through further engineering design and process development work.
Infrastructure for the Project, including access roads, a
communications system and ground water resources, will also be
developed during 2013.
Qualified Persons
The scientific and technical data contained in this news release
pertaining to Pitarrilla has been reviewed and approved by the
following Qualified Persons ("QP") under National Instrument 43-101
who consent to having their names included in this news
release.
-- Andrew W. Sharp, BEng., FAusIMM: Mr. Andrew W. Sharp, the QP who
completed the Mineral Reserve estimate, has been employed by the Company
as Vice President of Technical Services since September, 2011.
-- Jeremy D. Vincent, B.Sc. (Hons), P.Geo.: Mr. Jeremy D. Vincent, the QP
who completed the Mineral Resource estimate reported here, has been
employed by the Company as Senior Geologist since September, 2011.
-- Kelly Boychuk, MBA, P. Eng.: Mr. Kelly G. Boychuk, the QP who reviewed
the Tailings Design/Surface Geotechnical and Water Balance sections of
the Feasibility Study, has been employed by the Company as Director of
Project Engineering since May, 2012.
-- Trevor J. Yeomans, B.Sc. (Hons), ASCM, P. Eng.: Mr. Trevor J. Yeomans,
the QP who completed the metallurgical sections of the Feasibility
Study, has been employed by the Company as Director of Metallurgy since
April, 2011.
Detailed report
A National Instrument 43-101 compliant technical report will be
filed on SEDAR within 45 days of this news release and will be
available at that time on the corporate website.
SOURCE: Silver Standard Resources Inc.
Cautionary Statements on Forward-Looking Information: Statements
in this news release are forward-looking statements within the
meaning of the United States Private Securities Litigation Reform
Act of 1995 and forward- looking information within the meaning of
Canadian securities laws (collectively "forward-looking
statements"). All statements, other than statements of historical
fact, are forward-looking statements. Generally, forward-looking
statements can be identified by the use of words or phrases such
as; "expects", "anticipates", "plans", projects", "estimates",
"assumes", "intends", "strategy", "goals", "objectives",
"potential" or variations thereof, or stating that certain actions,
events or results "may", "could", "would", "might" or "will" be
taken, occur or be achieved, or the negative of any of these terms
or similar expressions. These forward-looking statements are
subject to a variety of known and unknown risks, uncertainties and
other factors that could cause actual events or results to differ
from those expressed or implied, including, without limitation,
risks relating to: the interpretation of drill results and the
geology, grade and continuity of the Company's mineral deposits;
technological and operational difficulties or the delay,
non-compliance or inability to obtain permits encountered in
connection with development of the Pitarrilla Project;
uncertainties related to title to the Company's mineral properties;
the Company's ability to obtain the necessary surface rights for
the lands required for successful project permitting, construction
and operation of the Pitarrilla Project; changes in economic
conditions or financial markets; changes in prices for the
Company's mineral products or increases in input costs; uncertainty
of production and cost estimates for the Pitarrilla Project; risks
and uncertainties associated with new mining operations including
start-up delays and operational issues; litigation, legislative,
tax (including employee profit sharing arrangements), environmental
and other judicial, regulatory, political and competitive
developments in Canada, Mexico, the United States and other
jurisdictions in which the Company may carry on business; labour
relations matters; and foreign exchange rate fluctuations, as well
as other factors described in the Company's most recent Form 20-F
filed with the United States Securities and Exchange Commission and
Canadian regulatory authorities.
This list is not exhaustive of the factors that may affect any
of the Company's forward-looking statements. The Company's
forward-looking statements are based on what the Company's
management considers to be reasonable assumptions, beliefs,
expectations and opinions based on information currently available
to management. We cannot assure you that actual events, performance
or results will be consistent with these forward looking
statements, and management's assumptions may prove to be incorrect.
Assumptions have been made regarding, among other things, the
Company's ability to carry on its exploration and development
activities, the Company's ability to meet its obligations under its
property agreements, the timing and results of drilling programs,
the discovery of mineral resources and mineral reserves on the
Company's mineral properties, the timely receipt of required
approvals including obtaining the necessary surface rights for the
lands required for successful project permitting, construction and
operation of the Pitarrilla project, the price of the minerals the
Company produces, the costs of operating and exploration
expenditures, the Company's ability to operate in a safe, efficient
and effective manner and the Company's ability to obtain financing
as and when required and on reasonable terms. You are cautioned
that the foregoing list is not exhaustive of all factors and
assumptions which may have been used. The Company's forward looking
statements reflect current expectations regarding future events and
operating performance and speak only as of the date hereof and the
Company does not assume any obligation to update forward-looking
statements if circumstances or management's beliefs, expectations
or opinions should change other than as required by applicable law.
For the reasons set forth above, you should not place undue
reliance on forward-looking statements.
Cautionary Note to U.S. Investors. Technical disclosure included
herein has not been prepared in accordance with the requirements of
United States securities laws. Without limiting the foregoing, the
technical disclosure uses terms that comply with reporting
standards in Canada and certain estimates are made in accordance
with National Instrument 43-101 - Standards of Disclosure for
Mineral Projects. National Instrument 43-101 is a rule developed by
the Canadian Securities Administrators that establishes standards
for all public disclosure an issuer makes of scientific and
technical information concerning mineral projects. Canadian
standards, including National Instrument 43-101, differ
significantly from the requirements of the SEC, and mineral reserve
and resource information contained in this news release may not be
comparable to similar information disclosed by U.S. companies.
This news release uses the terms "Measured Mineral Resource" and
"Indicated Mineral Resource." U.S. investors are advised that while
such terms are recognized and required under Canadian regulations,
the SEC does not recognize them. Under U.S. standards
mineralization may not be classified as a "reserve" unless the
determination has been made that the mineralization could be
economically produced or extracted at the time the reserve
determination is made. U.S. investors are cautioned not to assume
that any part or all of the Mineral Resources in these categories
will ever be converted into Mineral Reserves.
This news release uses the term "Inferred Mineral Resources."
U.S. investors are advised that while such term is recognized and
required under Canadian regulations, the SEC does not recognize it.
"Inferred Mineral Resources" have a great amount of uncertainty as
to their existence, and great uncertainty as to their economic and
legal feasibility. It cannot be assumed that all or any part of an
Inferred Mineral Resource will ever be upgraded to a higher
category. Under Canadian rules, estimates of Inferred Mineral
Resources may not generally form the basis of feasibility or other
economic studies. U.S. investors are cautioned not to assume that
any part or all of an Inferred Mineral Resource exists, or is
economically or legally mineable.
To receive Silver Standard's news releases by e-mail, please
register using the Silver Standard website,
www.silverstandard.com.
The TSX has neither approved nor disapproved of the information
contained herein.
Contacts: Silver Standard Resources Inc. (604) 484-8216 or N.A.
Toll Free: (888) 338-0046invest@silverstandard.com
www.silverstandard.com