The following table lists planned and unplanned production outages at U.S. refineries as reported by Dow Jones Newswires. The information is compiled from both official and unofficial refining sources and doesn't purport to be a comprehensive list.

Valero Energy Corp. (VLO) said the FCC at its Port Arthur, Texas, refinery will begin a shutdown July 11 so work can take place to address recent outages.

A small crude distillation unit was taken down for planned repairs at BP PLC's (BP) Whiting, Ind., refinery, a person familiar with the refinery's operation said July 11.

Motiva LLC's Port Arthur, Texas, refinery shut down one of its units due to an operational issue, a spokesman for Royal Dutch Shell Plc. (RDSA) said Thursday. The planned shutdown initiated July 10 was performed safely, spokesman Kimberly Windon said.

Valero Energy said July 10 the process of starting a newly constructed hydrocracker at its St. Charles Refinery in Norco, La., is under way. The construction of the 57,000-barrel-a-day unit, which began in the fourth quarter of 2012, was completed by the end of June. The start-up procedures will progress over the next several days.

BP-Husky (BP, BP.LN, HSE.T) started planned work at the smaller of two coker units at its Toledo Refinery, located in Oregon, Ohio, on July 8, a person familiar with operations at the plant said July 10. It wasn't immediately known how long it will take to overhaul the 7,500-barrel-a-day unit. A 27,500-barrel-a-day coker unit continues to operate, the person said.

Tesoro Corp. (TSO) on July 9 said planned flaring, not associated with equipment breakdown, would occur at its newly acquired refinery in Carson, Calif., starting at 6 a.m. PDT on July 10. The source of the emissions wasn't specified.

Exxon Mobil Corp. (XOM) on July 8 reported emissions and a flare event lasting less than four hours due to equipment breakdown at its Torrance Refinery in California. The report to local regulators didn't specify what unit or units were involved, but a spokeswoman said there is no impact to production. "ExxonMobil expects to meet its contractual commitments," she added.

For more detailed information, search Dow Jones Newswires using the code N/REF.

 
Operator   Refinery    Capacity   Description                    Restart 
                       (in 000s 
                       bbl/day) 
UNPLANNED 
 
CANADA 
 
CARIBBEAN 
 
EAST COAST 
 
 
GULF COAST 
 
Valero   Port Arthur,  310.0  FCCU-1241 in circulation the co. 
Energy   TX                   said on July 9. The same unit 
                              experienced an upset on July 7. 
                              The unit's return to normal 
                              operation is not known. 
 
                              Upsets at SRU, SCOT units 1 
                              and 2 and two tail gas incin- 
                              erators on July 7 had no 
                              material impact to production 
                              the company said on July 8. 
 
Motiva   Port Arthur   600    Unit taken down for operational 
         TX                   issues July 10. 
 
MIDWEST 
 
ROCKIES 
 
WEST COAST 
 
Exxon    Torrance,     155.0  Unspecified equipment breakdown 
Mobil    CA                   on July 8 resulted in less than 
                              four hours of flaring. No material 
                              impact to production, the co. said. 
 
 
PLANNED 
 
CANADA 
 
CARIBBEAN 
 
Valero   Aruba                Refinery will be converted to a 
                              terminal while the company con- 
                              tinues to seek a buyer. 
 
EAST COAST 
 
PBF      Delaware     182.2   Work will be done on fluid coker   4Q 
Energy   City, DE             during the 4Q 2013.                2013 
 
         Paulsboro,   160.0   Crude unit maintenance in 4Q       4Q 
         NJ                   2013.                              2013 
 
 
GULF COAST 
 
Valero   Norco, LA     270.0  Newly-constructed hydrocracker 
Energy                        in start-up the co. said on 
                              July 10. It take several days 
                              to complete. 
 
MIDWEST 
 
BP       Whiting, IN   336.0  Small CDU taken down for planned 
                              work July 10. 
 
BP-      Toledo, OH    160.0  Planned maintenance under way 
Husky                         at smaller of two coker units. 
                              since July 8. Duration of work 
                              not known. 
 
Husky    Lima, OH      160.0  45 days of major turnaround 
                              scheduled in 2014; 70% of units 
                              involved. Remaining 30% will 
                              undergo major turnaround in 2015, 
                              the company said Feb. 9. 
 
Northern St. Paul Pk    84.5  FCCU maintenance is planned in 
Tier     MN                   October for most of the month. 
 
ROCKIES 
 
WEST COAST 
 
Alon     Bakersfield    94.0  Company purchasing asphalt to 
Calif.   Long Beach           supply 2013 asphalt season. Re- 
Complex  Paramount            fining complex operations still 
         CA                   suspended. Seeking permit to build 
                              rail line to supply midcontinent 
                              crude, the company said on March 8. 
 
Exxon    Torrance,     155.0  Reported possible flaring due to 
Mobil    CA                   planned work on July 1. No production 
                              impact expected. 
 
Tesoro   Carson, CA    266.0  Flare event, not associated with 
Corp.                         equipment breakdown will occur 
                              for 24 hours starting at 6 a.m. 
                              PDT on July 10. 
 
 

Subscribe to WSJ: http://online.wsj.com?mod=djnwires

Alon (NYSE:ALJ)
Historical Stock Chart
From Mar 2024 to Apr 2024 Click Here for more Alon Charts.
Alon (NYSE:ALJ)
Historical Stock Chart
From Apr 2023 to Apr 2024 Click Here for more Alon Charts.