US Refinery Status: Husky Restarts Ohio Refinery

Date : 11/23/2009 @ 9:18AM
Source : Dow Jones News
Stock : BP PLC (ADS) (BP)
Quote : 58.15  0.0 (0.00%) @ 7:55PM
<< BackQuote Chart Financials
Free BP PLC (ADS) Annual Company Report

 

US Refinery Status: Husky Restarts Ohio Refinery

DOW JONES NEWSWIRES

The following table lists unplanned and planned production outages at U.S. refineries as reported by Dow Jones Newswires. The information is compiled from both official and unofficial refining sources and doesn't purport to be a comprehensive list.

Husky Energy Inc. (HSE.T) is in the process of restarting its refinery in Lima, Ohio, the state environmental protection agency said Friday.

BP PLC (BP) reported Friday that its Texas City, Texas, refinery experienced flaring at its ultracracker, according to a filing with state environmental regulators.

The cause of the emissions event, which lasted for about one hour Friday afternoon, "is still unknown and under investigation," the filing stated. The company couldn't be immediately reached for comment.

Valero Energy Corp. (VLO) announced Friday that it is shutting down its Delaware City, Del., refinery permanently due to poor economics. On Thursday, the company's Texas City, TX, plant reported flaring due to a snag at boilers in complex 4 and restarted one of three modules that were shut earlier in the week for repairs.

For more detailed information, search Dow Jones Newswires using the code N/REF.

 
 
Operator   Refinery    Capacity   Description                  Restart 
                       (in 000s 
                       bbl/day) 
 
UNPLANNED 
 
CANADA 
 
 
Suncor     Sarnia      85.0    Hydrocracker unit shut Oct           n/a 
           Ontario             11 due to fire at associated 
                               compressor; no  restart esti- 
                               mate available. 
 
EAST COAST 
 
Conoco     Linden    238.0     Officials consider run cuts      n/a 
           N.J.                due to slack demand, a per- 
                               son familiar with operations 
                               said on July 17. 
 
CARIBBEAN 
 
CPC     Bayamon        48.0  Explosion, fire at facility     n/a 
        Puerto Rico          early on Oct. 23. 11 out of 
                             30 storage tanks exploded. 
 
GULF COAST 
 
BP      Texas City    455.8  SRU hit snag Oct. 26, back to normal Oct. 27 
                             Co. restarts Ultraformer #4 Nov. 1 
                             BP restarting ultracracker on 
                             Nov. 7-19. Flares at Ultracracker 
                             Nov. 20 
 
Citgo      Corpus     163.0  Alkylation unit shut July 19        end-Oct 
           Christi, TX      by near-fatal explosion to 
                             return to service by end-Oct. 
                             The restart was delayed from 
                             early-Oct due to safety issues. 
                             FCCU, restarted Oct. 29 
 
 
Valero    Texas City  199.5   FCCU operating at normal rates Nov. 17 
                             after being restarted over the weekend; 
                             shut Oct. 25 to repair a slide valve. 
 
                             Snag involving three boilers at 
                             complex 4 resulted in flaring, Nov. 19. 
 
Western El Paso, TX   125.0  FCCU wet gas compressor restarting 
                             Nov. 19 after tripping offline. 
 
Flint      Corpus     288.1  Found and fixed a pinhole gas leak 
Hills      Christi, TX       in a crude unit pipe Nov. 19. 
 
MIDWEST 
 
ROCKY MOUNTAINS 
 
Holly     Wood Cross    25.0  Brief power outage shuts units Nov. 4. 
          Utah                Restarted same day. 
 
Flying J  Salt Lake     29.4  Brief power outage shuts units Nov. 4. 
          Utah                Restarted same day. 
 
WEST COAST 
Chevron   Richmond, CA   240.0  Reported mechanical snag Nov. 18; 
                                warned it could result in flaring 
 
Tesoro    Wilmington     100.0  Fuel gas system upset Nov. 14 
          CA                    caused boilers, process heaters 
                                and co-gen unit to release emissions. 
 
Conoco   Rodeo, CA       120.2  Reported flaring due to a unit 
                                shutdown Nov. 17; no more details. 
 
Exxon   Torrance,CA      149.5  Reported flaring from system upset 
                                Nov. 18; operations normal 
 
 
PLANNED 
 
CANADA 
 
Irving OIl Saint John   300.0   Completed $220 million investments 
                                upgrades including FCCU, diesel 
                                hydrotreater, crude unit, amine units, 
                                hydrogen plant, more piping, and fresh 
                                catalysts, among others things, Co. said 
                                Nov. 17. 
 
CARIBBEAN 
 
Valero     Aruba         235.0  The refinery that was shut 
                                in June for 2-3 months for 
                                economic reasons is being 
                                closed indefinitely. 
 
EAST COAST 
 
Sunoco    Westville, NJ  145.0  Idling all refining              Mid-Nov 
                                operations indefinitely due 
                                to poor economics, Co. said 
                                Oct. 6. It will take 4-6 
                                weeks to work through crude 
                                stocks to shut down. 
 
                                Reformer unit shut in Girard     n/a 
                                Point section in early Oct 
                                for economic reasons. Shutdown 
                                to last 1-6 months. 
 
Valero     Delaware City 210.0 Plant to be permanently shut due 
                               to poor economics, announced 
                               Nov. 20. Delaware Official said 
                               it would be shut on Nov. 22. 
 
 
Western    Yorktown       64.5  Planned work scheduled 1Q 2010. 
           Va. 
 
MIDWEST 
Frontier   Kansas         130.0  Extended FCCU work by several 
                                 days will reduce charge 
                                 rates to 76,000 bbls/day from 
                                 81,500 bbls/day. 
 
Husky     Lima Ohio         160.0  Plant Restarting.             Nov. 20 
 
ROCKY MOUNTAIn 
 
Western    Bloomfield,     16.8  Co. announced plans Nov. 9 
           NM                    to idle plant and shift 
                                 production to Gallup plant. 
 
Western    Gallup,         20.8  Utilization will be boosted 
           NM                    to near full capacity with 
                                 Bloomfield shutdown, from 
                                 about half, Co. said Nov. 9. 
 
Tesoro    Salt Lake City,  58.0  Planned turnaround in 2010; 
          Utah                   no timetable disclosed. 
 
Tesoro    Mandan, N.D.     58.0  Planned turnaround in 2010; 
                                 no timetable disclosed. 
 
Exxon     Joliet, Ill.    238.6  Vacuum distillation unit restarted 
                                 earlier this week after planned 
                                 work, Co. said Nov. 11. 
 
GULF COAST 
 
Alon       Krotz Springs  80.0  Plantwide turnaround starts      Nov. Dec. 
           LA.                  In Nov. 
 
Alon       Big Spring,    67.0  Restarted SRU on Nov. 6. 
           TX 
 
Chevron    Pascagoula,   330.0  Pre-commercial heavy oil         2010 
           Miss.                conversion project delayed 
                                from 2008 to 2010 due to 
                                economic factors. 
 
Conoco    Borger, TX     146.0  Unidentified units shut for 
                                planned turnaround, Co. said 
                                Oct. 9. No further details. 
                                Shut amine unit for planned     Oct. 24 
                                maintenance Oct. 9-24. 
 
                                Shut Unit 34 SRU and tail gas   Nov. 15 
                                treatment unit for planned 
                                repairs Nov. 12-15. 
 
Conoco     Sweeny, TX    247.0  Six weeks of turnaround work     Oct 30 
                                starts Sept. 14 at Units 14, 
                                9, 38 and 27, which is an 
                                FCCU. 
 
                                FCCU leak being repaired Nov. 12. 
 
                                Tail gas incinerator shut during  Nov. 1 
                                fall turnaround Sept. 30 
 
Exxon      Baytown       572.5  FCCU No. 3 shut Sep 15. for 
           TX                   planned maintenance. 
 
Flint      Corpus        288.1  $250 mln project for new         Spr 
Hills      Christi, TX          diesel desulfurization,          2010 
                                sulfur recovery unit to begin 
                                in Fall 2008. Construction 
                                to last 18 months. 
 
Marathon   Garyville     245.0  Project to increase crude oil    4Q 
           LA                   refining capacity by 180,000-    2009 
                                b/d 85% complete, as of end 
                                April. New units expected 
                                start up in 4Q 2009. Entire 
                                refinery reaches full capacity 2Q'10 
 
Motiva     Port Arthur   285.0  Expansion project to increase    1Q 
           TX                   throughput capacity by 325,000   2012 
                                b/d, to 610,000-b/d, slowed. 
                                Completion now seen 1Q 
                                2012, from 2010. 
 
 
 
Valero   Port Arthur  310.0    Shut all three modules of 105,000 
         TX                    bpd coker to repair cracks in coke 
                               drums, and to be returned to service 
                               over next several days Co. said 
 
 

BP PLC (ADS) Historical Chart BP PLC (ADS) Intraday Chart  
Period


LSE and PLUS quotes are live. NYSE and AMEX quotes are delayed by at least 20 minutes.
All other quotes are delayed by at least 15 minutes unless otherwise stated.
The Spread Bet Centre :: The CFD Centre :: Financial Glossary :: Forex Rates, Charts & News
By accessing the services available at ADVFN you are agreeing to be bound by ADVFN's Terms & Conditions :: Contact Us :: Request an Exchange :: Affiliate Scheme
Copyright 1999-2010 ADVFN PLC. Copyright Notice & Privacy Policy :: Privacy Policy :: Investment Warning :: Advertise with us :: Data accreditations :: Investor Relations :: Press office :: Jobs
32 site:2us 100318 23:06