The following table lists unplanned and planned production outages at U.S. refineries as reported by Dow Jones Newswires. The information is compiled from both official and unofficial refining sources and doesn't purport to be a comprehensive list.

BP PlC (BP) reported that an ultracracker at its Texas City, Texas refinery will restart Tuesday, according to an environmental filing.

Alon USA Energy (ALJ) Inc. said Wednesday that it will begin the turnaround for its Krotz Springs, La., refinery in November 2009 instead of the first quarter of 2010.

A power outage Wednesday in the Utah caused refineries there including Holly Corp.'s (HOC) Wood Cross facility and Flying J's Salt Lake City plant to briefly shutdown and then restart.

For more detailed information, search Dow Jones Newswires using the code N/REF.

 
 
Operator   Refinery    Capacity   Description                  Restart 
                       (in 000s 
                       bbl/day) 
 
UNPLANNED 
 
CANADA 
 
Suncor     Alberta             One of two oil sands up-             n/a 
                               graders is back to normal 
                               rates, co said Nov. 2 
                               following a minor fire on Oct 12. 
 
Suncor     Sarnia      85.0    Hydrocracker unit shut Oct           n/a 
           Ontario             11 due to fire at associated 
                               compressor; no  restart esti- 
                               mate available. 
 
EAST COAST 
 
Conoco     Linden    238.0     Officials consider run cuts      n/a 
           N.J.                due to slack demand, a per- 
                               son familiar with operations 
                               said on July 17. 
 
CARIBBEAN 
 
CPC     Bayamon        48.0  Explosion, fire at facility     n/a 
        Puerto Rico          early on Oct. 23. 11 out of 
                             30 storage tanks exploded. 
 
Hovensa St. Croix  500.00    Shuts FCCU unit for repairs.   Nov. 6 
 
GULF COAST 
 
BP      Texas City    455.8  SRU hit snag Oct. 26, back to normal Oct. 27 
                             Co. restarts Ultraformer #4 Nov. 1 
 
Citgo      Corpus     163.0  Alkylation unit shut July 19        end-Oct 
           Christi, TX      by near-fatal explosion to 
                             return to service by end-Oct. 
                             The restart was delayed from 
                             early-Oct due to safety issues. 
                             FCCU, restarted Oct. 29 
 
Motiva   Port Arthur 285.0   FCCU hits snag on Oct. 31. 
         TX 
 
Valero     Corpus    142.0   Restarting West Plant Hydrocracker 
                             unit Oct. 25 that was shut Oct. 7 
                             due to small fire. An SMR unit was shut 
                             for maintenance after the 
                             fire; restart Oct. 10. 
                             West Plant stabilizer tower shut 
                             for maintenance Oct. 26-27. 
                             Restarting East Plant's Tank 79 
                             on Oct. 9. 
 
Valero    Texas City  199.5  Experienced flaring at Complex 1 
                             tower on Oct. 23. 
                             Shut the FCCU Oct. 25 to repair 
                             a slide valve; no restart estimate 
 
Total   Port Arthur   232.0  Operations being restored 
        TX                   on Oct. 22 following plant 
                             wide power failure earlier 
                             in the day. 
                             A fire occurred in a heavy oil    n/a 
                             line between the crude unit and 
                             the tank farm on Oct 13 during 
                             the restart of several process 
                             units that were knocked off-line 
                             earlier that day by a power snag. 
                             Identifying a leaky exchanger that 
                             is causing a cooling tower Oct. 26. 
 
                             Co. restarts 3 units Oct. 29, after 
                             brief shutodwn. 
 
Chevron Pascagoula,   330.0  A blown cap as plant prepared to 
        MS                   to transfer molten sulfur to a 
                             barge released the compound into 
                             the water Oct. 25. 
 
 
MIDWEST 
 
ROCKY MOUNTAINS 
Exxon     Billings, MT  60.0  Operations returned to normal 
                              after a brief power outage hit 
                              the area Oct. 23. 
 
Conoco    Billings, MT  58.0  A brief area power outage Oct. 23 
                              impacted operations, local reports. 
 
CHS       Laurel, MT    55.0  Operations returned to normal 
                              after a brief power outage Oct. 23. 
 
Holly     Wood Cross    25.0  Brief power outage shuts units Nov. 4. 
          Utah                Restarted same day. 
 
Flying J  Salt Lake     29.4  Brief power outage shuts units Nov. 4. 
          Utah                Restarted same day. 
 
WEST COAST 
 
Chevron    El Segundo    274.0  Reported flaring at hydrocracker 
           CA                   site on Oct. 24. 
                                A brief period of flaring        n/a 
                                on Oct 14 is reported to 
                                state regulators. Filing 
                                lists cause as "breakdown." 
 
PLANNED 
 
CANADA 
 
CARIBBEAN 
 
Valero     Aruba         235.0  The refinery that was shut 
                                in June for 2-3 months for 
                                economic reasons is being 
                                closed indefinitely. 
 
EAST COAST 
 
Sunoco    Westville, NJ  145.0  Idling all refining              Mid-Nov 
                                operations indefinitely due 
                                to poor economics, Co. said 
                                Oct. 6. It will take 4-6 
                                weeks to work through crude 
                                stocks to shut down. 
 
 
                                Reformer unit shut in Girard     n/a 
                                Point section in early Oct 
                                for economic reasons. Shutdown 
                                to last 1-6 months. 
 
Valero     Delaware City 210.0  Coker Unit shut Oct 3-4 and      n/a 
           DE                   related gasifier unit to shut 
                                within a few days for economic 
                                reasons. 
                                Maintenance at 80,000-b/d 
                                FCCU/akly delayed to Nov./Dec. 
                                Entire plant to be shut down. 
 
Western    Yorktown       64.5  Planned work scheduled 1Q 2010. 
           Va. 
 
 
GULF COAST 
 
Alon       Krotz Springs  80.0  Plantwide turnaround starts      Nov. Dec. 
           LA.                  In Nov. 
 
 
Chevron    Pascagoula,   330.0  Pre-commercial heavy oil         2010 
           Miss.                conversion project delayed 
                                from 2008 to 2010 due to 
                                economic factors. 
 
Conoco    Borger, TX     146.0  Unidentified units shut for 
                                planned turnaround, Co. said 
                                Oct. 9. No further details. 
                                Shut amine unit for planned     Oct. 24 
                                maintenance Oct. 9-24. 
 
Conoco     Sweeny, TX    247.0  Six weeks of turnaround work     Oct 30 
                                starts Sept. 14 at Units 14, 
                                9, 38 and 27, which is an 
                                FCCU. 
 
                                Tail gas incinerator shut during  Nov. 1 
                                fall turnaround Sept. 30 
 
Exxon      Baytown       572.5  FCCU No. 3 shut Sep 15. for 
           TX                   planned maintenance. 
 
Flint      Corpus        288.1  $250 mln project for new         Spr 
Hills      Christi, TX          diesel desulfurization,          2010 
                                sulfur recovery unit to begin 
                                in Fall 2008. Construction 
                                to last 18 months. 
 
Marathon   Garyville     245.0  Project to increase crude oil    4Q 
           LA                   refining capacity by 180,000-    2009 
                                b/d 85% complete, as of end 
                                April. New units expected 
                                start up in 4Q 2009. Entire 
                                refinery reaches full capacity 2Q'10 
 
Motiva     Port Arthur   285.0  Expansion project to increase    1Q 
           TX                   throughput capacity by 325,000   2012 
                                b/d, to 610,000-b/d, slowed. 
                                Completion now seen 1Q 
                                2012, from 2010. 
 
Shell      Deer Park,    340.0  Hydroprocessing unit, cata-      Oct 24 
                                lytic cracker unit and alky- 
                                lation shut between Oct 1 and 
                                Oct 24 for fall turnaround 
                                maintenance. 
Valero     Corpus        340.0  Coker unit shutdown for econo-   n/a 
           Christi, TX          mic reasons and planned work; 
                                delayed to June 19 from June 
                                12. The 20,000-b/d unit will 
                                remain off line through July 
                                but could restart at any time 
 
 
                                if margins improve. 
 
                                20,000-b/d FCCU in East          n/a 
                                Plant shut; West Plant 
                                50,000-b/d FCCU at reduced 
                                rates since mid-Dec for 
                                economic reasons. 
 
                                15,000-b/d HCU in East Plant 
                                set for 18 days of work in Jan. 
 
                                36,000-b/d HCU in West Plant 
                                sent for 18 days of work in Feb. 
 
Valero     Norco, LA     250.0  Upgrade project to build         2012 
                                a new diesel hydrotreater 
                                unit moved from 2010 to 
                                4Q 2012. 
 
                                Turnaround at crude/ coker unit    1Q 
                                set for 36 days in Jan. 
                                Entire Plant 
                                to be shut for work. 
 
                                 The coker will operate at 
                                50% of capacity when 
                                restarted due to poor 
                                economics. 
 
Valero     Port Arthur   325.0  77,000-b/d FCCU at reduced       n/a 
           TX                   rates since mid-Dec for 
                                economic reasons. 
 
                                45,000 b/d HCU to undergo        Spring 
                                38 days of work in March. 
 
Valero     Sunray, TX    170.0  55,000-b/d FCCU at reduced       n/a 
                                rates since mid-Dec for 
                                economic reasons. 
 
Valero     Three Rivers   95.0  Plant-wide 24-day turnaround     Oct. 2 
 
 
 
WEST COAST 
 
BP         Carson, CA    265.0  Flaring on Oct. 26-Nov.1 is 
                                related to planned maintenance 
                                of its hydrotreater. 
 
Valero     Wilmington, Ca 96.86 56,000 b/d FCC/alky to be shut    Dec. 
                                in Nov. for 39 days of work. 
                                The entire plant will be shut down during 
                                the turnaround. 
 

Order free Annual Report for BP plc

Visit http://djnewswires.ar.wilink.com/?link=BP or call 1-888-301-0513

Order free Annual Report for ConocoPhillips

Visit http://djnewswires.ar.wilink.com/?link=COP or call 1-888-301-0513

Order free Annual Report for Chevron Corporation

Visit http://djnewswires.ar.wilink.com/?link=CVX or call 1-888-301-0513

Order free Annual Report for Marathon Oil Corporation

Visit http://djnewswires.ar.wilink.com/?link=MRO or call 1-888-301-0513

Order free Annual Report for Exxon Mobil Corporation

Visit http://djnewswires.ar.wilink.com/?link=XOM or call 1-888-301-0513

 
 

<< Back


BP PLC (ADS) Historical Chart BP PLC (ADS) Intraday Chart  
Period


LSE and PLUS quotes are live. NYSE and AMEX quotes are delayed by at least 20 minutes.
All other quotes are delayed by at least 15 minutes unless otherwise stated.
By accessing the services available at ADVFN you are agreeing to be bound by ADVFN's Terms & Conditions :: Contact Us :: Request an Exchange :: Affiliate Scheme
Copyright1999-2009 ADVFN PLC. Copyright and limited reproduction :: Privacy Policy :: Investment Warning :: Advertise with us :: Data accreditations :: Investor Relations :: Press office :: Jobs
ADDITIONAL SERVICES AVAILABLE FROM ADVFN
Upgrade - Click here for more information on ADVFN premium services Money Words - ADVFN Financial Glossary Investor Training ADVFN Financial Bookshop Online Training Academy
32 site:2us 091124 05:37 Stock Message Boards ( 2001 | 2002 | 2003 | 2004 | 2005 | 2006 | 2007 )