36,000-b/d HCU in West Plant
sent for 18 days of work in Feb.
Valero Norco, LA 250.0 Upgrade project to build 2012
a new diesel hydrotreater
unit moved from 2010 to
4Q 2012.
Turnaround at crude/ coker unit 1Q
set for 36 days in Jan.
Entire Plant
to be shut for work.
The coker will operate at
50% of capacity when
restarted due to poor
economics.
Valero Port Arthur 325.0 77,000-b/d FCCU at reduced n/a
TX rates since mid-Dec for
economic reasons.
45,000 b/d HCU to undergo Spring
38 days of work in March.
Valero Sunray, TX 170.0 55,000-b/d FCCU at reduced n/a
rates since mid-Dec for
economic reasons.
Valero Three Rivers 95.0 Plant-wide 24-day turnaround Oct. 2
WEST COAST
BP Carson, CA 265.0 Flaring on Oct. 26-Nov.1 is
related to planned maintenance
of its hydrotreater.
Valero Wilmington, Ca 96.86 56,000 b/d FCC/alky to be shut Dec.
in Nov. for 39 days of work.
The entire plant will be shut down during
the turnaround.