Placing of shares

Date : 08/21/2009 @ 7:00AM
Source : UK Regulatory (RNS & others)
Stock : Pantheon Resources (PANR)
Quote : 32.0  0.0 (0.00%) @ 3:43AM
<< BackQuote Chart

 

Placing of shares

 

TIDMPANR 
 
RNS Number : 8280X 
Pantheon Resources PLC 
21 August 2009 
 
? 
 
 
 
 
+----------------------------------+-------------------------------------+ 
| Press release                    |                Date: 21 August 2009 | 
+----------------------------------+-------------------------------------+ 
 
 
Placing of Shares 
 
 
Pantheon Resources plc ("Pantheon" or "the Company"), the AIM-quoted oil and gas 
exploration  company active in Louisiana and Texas, announces that it has today 
conditionally placed with  investors 4,554,600 new ordinary shares of 1 pence 
each in the Company ("the Placing Shares") at an issue price of 12 pence per 
share to raise GBP0.507million  after expenses ("the Placing"). Application has 
been made for the Placing Shares to be admitted to trading on the AIM market of 
the London Stock Exchange plc ("Admission"). The Placing is conditional, inter 
alia, upon Admission which is expected to be on 24 August 2009. 
 
 
The net proceeds of the Placing will be used to fund the estimated costs for the 
proposed remedial operations on the Vision Rice University #1 ("VRU#1") well on 
the Tyler County project, and for general working capital. As previously 
announced, these remedial actions follow extensive drilling and testing 
delays at the VRU#1 well. Specific details of the proposed remedial work at the 
well were announced on 13 August 2009. 
 
 
As previously announced, the drilling and testing delays at both the Bullseye 
and Tyler County projects have also resulted in additional costs becoming 
payable by the Company. These additional costs have been met through Pantheon's 
existing cash resources and the  proposed bridging finance facilities of up to 
GBP1.45m announced on 29 April 2009 and 25 June 2009, of which a total of 
GBP1.13m has been drawn down to date. Following the completion of the Placing 
there is no intention for the Company to draw down the remaining balance of the 
bridging finance facilities. 
 
 
The delays at the VRU#1 well relate primarily to mechanical difficulties 
encountered whilst drilling and do not reflect the potential prospectivity of 
the project. Specific difficulties encountered include much higher than expected 
reservoir pressures and the unexpected presence of an "unconsolidated rubble 
zone". Despite the mechanical challenges caused by these unexpected features, 
both features are considered to be beneficial for the project overall. In Austin 
Chalk wells, higher pressure is generally regarded as a positive as it usually 
indicates higher potential reserves and productivity. Unconsolidated rubble 
zones typically exhibit higher porosity and permeability, and should lead to 
enhanced recovery and flow rate per well if confirmed. 
 
 
Previously Pantheon has advised that the Company is in discussions for the 
provision of a possible debt-based facility to fund the development of both its 
Bullseye and Tyler County projects. The Board continues to believe that a 
debt-based facility for the remainder of both programmes is preferable to 
issuing additional equity, in order to minimise dilution to existing 
shareholders. A decision is expected to be made on this possible facility 
subsequent to the completion of this well. Should the VRU#1 well be completed 
successfully and brought into production then the Company is optimistic about 
securing a debt-based facility. Should however the remedial operations be 
unsuccessful or a debt-based facility not be agreed, the Company may be required 
to explore other alternatives for future funding of its assets. 
 
 
Following completion of the Placing, the Company will have 44,391,730 ordinary 
shares of 1 pence each ("Ordinary Shares") in issue. The Placing Shares will 
rank pari passu in all respects with the Company's existing Ordinary Shares. 
These Placing Shares will represent approximately 10.26% percent of the enlarged 
issued share capital of the Company on Admission. 
 
 
 
 
 
 
 
 
Jay Cheatham CEO of Pantheon Resources, stated, 
 
 
"I am very pleased with the response to the private placing and the confidence 
shown in the Company's future. This placing was constrained in order to minimise 
dilution to existing shareholders, and should allow the Company to complete the 
proposed remedial actions for the well." 
 
 
"I remain very excited by the potential for this well and for the entire 
project. I believe it is extremely important to recognise that the difficulties 
experienced in this well are for engineering and mechanical reasons, and not 
because of the absence of hydrocarbons. Put simply, the well was not originally 
engineered for the features encountered. Ironically, these very features are 
potentially materially beneficial for the remainder of the project. We are 
delighted to have a 25% stake in this joint venture, and our challenge is to 
maintain that interest with a minimum dilution to existing shareholders". 
 
 
 
 
 
 
 
 
For further information on Pantheon Resources plc, see the website at 
www.pantheonresources.com 
 
Further information: 
 
 
Pantheon Resources plc 
+-----------------------------------------------------+------------------+ 
| Justin Hondris, Director, Finance and Corporate     | +44 20 7484 5359 | 
| Development                                         |                  | 
+-----------------------------------------------------+------------------+ 
 
 
Oriel Securities Limited (Nominated Adviser) 
+-----------------------------------------------------+------------------+ 
| Michael Shaw / Daniel Conti                         |      +44 20 7710 | 
|                                                     |             7600 | 
+-----------------------------------------------------+------------------+ 
 
 
 
 
 
Background on Vision Rice University #1 ("VRU#1") Well 
 
 
The first well on this Tyler County project commenced on 12 November 2008 with 
the spudding of the Vision Rice University #1 ("VRU#1") well. In February 2009 
the completion assembly was run. Reservoir pressure was materially higher both 
than that seen in the Anadarko/Ergon wells located to the north. The operator 
had already engineered the well in the expectation that the reservoir pressure 
would be higher than those encountered in the Anadarko/Ergon wells. However the 
pressure encountered exceeded even its pre-drill estimates. This higher pressure 
caused the operator to complete the well with a shorter lateral (horizontal) 
section than originally planned. However fractures were cut with commensurate 
natural gas shows. 
 
 
After setting a slotted liner in the horizontal segment of the wellbore, service 
company personnel failed to set a production packer, on two separate occasions. 
On the third attempt, a packer and production tubing were successfully 
installed. During subsequent clean-up operations the well bore became blocked. 
This caused further delays. 
 
 
The operator utilised a coiled tubing unit in an attempt to remove the 
blockages. During these procedures, small pieces of formation flowed through the 
slotted liner into the well bore resulting in a new obstruction. This occurred 
each time the well was cleaned out. Such experiences are consistent with the 
presence of an unconsolidated rubble formation. Eventually the blockages 
prevented the extraction of the coiled tubing from the hole. 
 
 
The presence of a potential unconsolidated rubble zone was imperceptible on the 
seismic available to the joint venture prior to drilling. Such zones are known 
to exist elsewhere in the Austin Chalk. The existence of an unconsolidated 
rubble zone would be extremely encouraging for the project. Such zones typically 
exhibit higher permeability and porosity. These usually lead to both enhanced 
recovery and flow rate per well. If confirmed, these factors would have a 
significant and beneficial impact on the project's economics. Additionally, 
during the very limited testing operations performed, the well produced natural 
gas, condensate and black oil. 
 
 
The information gathered from the current well should facilitate the drilling of 
any future wells on the project. In particular, it should result in subsequent 
wells being drilled at a lower cost than originally expected, despite the 
mechanical problems contributing towards additional time and cost overruns in 
this well. Lower potential future drilling costs would also enhance the 
project's economics. 
 
 
Remedial operations planned by the operator will utilise a high pressure 
snubbing unit in an attempt to remove the stuck coiled tubing. The plan is to 
then cement the upper zone to prevent further migration of pebbles and fine 
sediments into the well bore, before undertaking clean-out and completion 
operations. This operation is estimated to take two to three weeks on a trouble 
free basis to complete once the snubbing unit is on location. 
 
 
 
 
 
 
This information is provided by RNS 
            The company news service from the London Stock Exchange 
   END 
 
 MSCBFLFLKVBEBBF 
 


Pantheon Resources Historical Chart Pantheon Resources Intraday Chart  
Period


LSE and PLUS quotes are live. NYSE and AMEX quotes are delayed by at least 20 minutes.
All other quotes are delayed by at least 15 minutes unless otherwise stated.
The Spread Bet Centre :: The CFD Centre :: Financial Glossary :: Forex Rates, Charts & News
By accessing the services available at ADVFN you are agreeing to be bound by ADVFN's Terms & Conditions :: Contact Us :: Request an Exchange :: Affiliate Scheme
Copyright 1999-2010 ADVFN PLC. Copyright Notice & Privacy Policy :: Privacy Policy :: Investment Warning :: Advertise with us :: Data accreditations :: Investor Relations :: Press office :: Jobs
41 site:2us 100321 17:43