Petrofac Limited Update on Laggan-Tormore Project (6446K)
April 20 2015 - 2:00AM
UK Regulatory
TIDMPFC
RNS Number : 6446K
Petrofac Limited
20 April 2015
Press Release
19 April 2015
PETROFAC LIMITED
UPDATE ON LAGGAN-TORMORE PROJECT
The Company is entering the final stages of the Laggan-Tormore
gas plant project on Shetland in the UK.
As we noted in our full year results announcement issued on 25
February 2015, in line with our latest assessment of schedule and
cost-to-complete for the Laggan-Tormore project, and the final
commercial settlement agreed with our client, Total, the Group had
recognised a loss on the project of US$230 million(1) in the year
ended 31 December 2014. We also stated in the results announcement
that we expected to recognise no further profit or loss on the
project over the remainder of the contract duration with completion
expected in the third quarter of 2015.
During late March and early April, activity on the
Laggan-Tormore site has ramped up substantially as we have moved
into the final construction and commissioning phases of the
project. Continued adverse weather conditions during March on
Shetland and industrial action has delayed this ramp up by almost a
month from our original expectations. As the activity levels have
increased, it has become apparent that we will need to expend
significantly more man-hours to complete the project than
anticipated as a result of low manpower productivity levels as the
project nears completion, a greater level of rectification and
reinstatement work than expected, coupled with the failure of one
of our sub-contractors to deliver in line with their agreed
scope.
In light of these issues, we have just completed a full
re-assessment of the schedule and cost-to-complete estimate for the
Laggan-Tormore project. Whilst we still anticipate project
completion in the third quarter of 2015, as a result of the
significant amount of additional man-hours and associated support
costs required over the remaining months of project execution, we
now expect to recognise a further pre-tax loss on the project of
around GBP130 million (US$195 million at current exchange rates) in
2015. The additional costs we expect to incur reflect our firm
intention to devote all the necessary resources to the project to
meet the delivery commitments we have made to our client. We
anticipate that construction activity on the site will be
substantially complete by mid-June and we intend to provide an
update to the market on the status of the Laggan-Tormore project
with our trading statement scheduled for 23 June 2015.
Ayman Asfari, Petrofac's Group Chief Executive commented:
"We are deeply disappointed by this additional cost to complete
on the Laggan-Tormore project. As we noted in our year-end results
announcement, given the extent of direct construction involved in
the project, Laggan-Tormore is different from the rest of our EPC
project portfolio, where we typically utilise sub-contractors to
deliver construction services. We had to take on this level of
direct construction responsibility when some of our sub-contractors
failed to deliver in line with their agreed scopes. Our lack of
experience of operating a direct construction model in a wholly new
geography for our Onshore Engineering & Construction (OEC)
business, particularly in a location where labour costs are much
higher and productivity much lower than we are used to, has cost us
dearly.
"We have already affirmed that we will no longer take
construction risk on large lump-sum projects within the UK to avoid
a similar experience to Laggan-Tormore moving forward. For now, my
senior management team and I are focused on delivering the project
in line with the revised schedule agreed with our client. As such,
we have refreshed the site leadership team and further strengthened
it with key members of our Sharjah-based OEC team and have changed
a number of elements of our working practices to drive the project
through to completion.
"Putting the challenges we are facing on this project to one
side, the rest of our portfolio continues to perform in line with
expectations."
Notes
(1) The Group recognised a loss on the Laggan-Tormore project of
US$230 million in the year ended 31 December 2014. With around
US$50 million of profits having been recognised on the project in
previous years, overall the Group had recorded a cumulative loss on
Laggan-Tormore by 31 December 2014 of around US$180 million.
Conference call:
A conference call for analysts and investors will be held at
7:30am on Monday 20 April. The participant details are as
follows:
UK: 0808 237 0060
International: +44 203 426 2886
No passcode required
A playback facility will be available as follows:
UK: 0808 237 0026
International: +44 203 426 2807
Passcode: 656978#
Ends
Disclaimer:
This announcement contains forward-looking statements relating
to the business, financial performance and results of Petrofac and
the industry in which Petrofac operates. These statements may be
identified by words such as "expect", "believe", "estimate",
"plan", "target", or "forecast" and similar expressions, or by
their context. These statements are made on the basis of current
knowledge and assumptions and involve risks and uncertainties.
Various factors could cause actual future results, performance or
events to differ materially from those described in these
statements and neither Petrofac nor any other person accepts any
responsibility for the accuracy of the opinions expressed in this
presentation or the underlying assumptions. No obligation is
assumed to update any forward-looking statements.
For further information contact:
Petrofac Limited
Jonathan Low, Head of Investor Relations +44 (0) 207 811 4930
Jonathan Edwards, Investor Relations Officer +44 (0) 207 811 4936
Alison Flynn, Head of Media Relations +44 (0) 207 811 4913
Tulchan Communications Group Ltd +44 (0) 207 353 4200
Stephen Malthouse
Martin Robinson
petrofac@tulchangroup.com
Notes to Editors
Petrofac
Petrofac is a leading international service provider to the oil
& gas production and processing industry, with a diverse
customer portfolio including many of the world's leading
integrated, independent and national oil & gas companies.
Petrofac is quoted on the London Stock Exchange (symbol: PFC).
Petrofac designs and builds oil & gas facilities; operates,
maintains and manages facilities and trains personnel; enhances
production; and, where it can leverage its service capability,
develops and co-invests in upstream and infrastructure projects.
Petrofac's range of services meets its clients' needs across the
full life cycle of oil & gas assets.
With around 20,000 employees, Petrofac operates out of seven
strategically located operational centres, in Aberdeen, Sharjah,
Abu Dhabi, Woking, Chennai, Mumbai and Kuala Lumpur and has a
further 24 offices worldwide.
For additional information, please refer to the Petrofac website
at www.petrofac.com.
This information is provided by RNS
The company news service from the London Stock Exchange
END
DRLGGUWWCUPAPPB
Petrofac (LSE:PFC)
Historical Stock Chart
From Mar 2024 to Apr 2024
Petrofac (LSE:PFC)
Historical Stock Chart
From Apr 2023 to Apr 2024