TIDMKAZ

RNS Number : 6429U

KAZ Minerals PLC

26 October 2017

 
 
     KAZ MINERALS 
     PLC 
     6(TH) FLOOR 
     CARDINAL PLACE 
     100 VICTORIA 
     STREET 
     LONDON SW1E 5JL 
     Tel: +44 (0) 
     20 7901 7800 
  ================== 
 

26 October 2017

KAZ MINERALS GROUP PRODUCTION REPORT FOR NINE MONTHS AND THE THIRD QUARTERED 30 SEPTEMBER 2017 AND INTERIM MANAGEMENT STATEMENT

l Operational highlights

-- Copper production(1) increased by 14% to 75 kt in Q3 (Q2 2017: 66 kt) as Aktogay ramps up

-- Full year copper production(1) guidance increased to 250-270 kt

-- Gold production guidance raised to 160-180 koz

l Bozshakol approaching design capacity

-- Copper production(2) of 27 kt in Q3 (Q2 2017: 29 kt)

-- Sulphide plant operated at 100% of design throughput in August (Q3 2017: 93%)

-- Q3 copper output impacted by expected reduction in copper grade

-- Clay plant achieved 81% of design throughput in Q3 (Q2 2017: 69%)

-- Gold guidance for 2017 raised to 110-120 koz, following strong year to date output

l Aktogay copper guidance increased to 85-95 kt

-- Copper production(1) of 31 kt in Q3 (Q2 2017: 21 kt)

-- Sulphide copper production(2) was 23 kt in Q3 (Q2: 15 kt) and operations declared commercial from October

-- Oxide copper cathode production of 8 kt in Q3 (Q2 2017: 6 kt)

l East Region and Bozymchak

-- Q3 2017 copper production(2) of 17 kt (Q2 2017: 16 kt), on track for full year guidance of around 65 kt

-- High zinc grade areas in East Region not yet accessed, full year zinc guidance revised to 60-65 kt

-- On track for top end of gold guidance range of 50-60 koz and silver guidance increased to 2,600-2,850 koz

l Financial update

-- Net debt of $2,220 million at 30 September 2017 (30 June 2017: $2,442 million)

-- $1,684 million of available liquidity including cash and cash equivalents of $1,352 million and $332 million of undrawn facilities

-- $74 million of VAT refunds in relation to project capital expenditure received in Q3

(1) Payable metal in concentrate and copper cathode from Aktogay oxide ore.

(2) Payable metal in concentrate.

Oleg Novachuk, Chief Executive, said: "Following another strong quarter from our new sulphide operations at Aktogay we have raised the Group's copper production guidance for 2017 to 250-270 kt. Aktogay's sulphide concentrator reached commercial levels of production at the end of Q3 and we expect to reach full capacity during 2018. At Bozshakol, the main concentrator operated at 100% of design throughput in August. KAZ Minerals is rapidly improving its gearing metrics as we deliver against our operational targets in an improving market for copper."

For further information please contact:

 
 KAZ Minerals 
  PLC 
====================  ==========================  ================= 
 Chris Bucknall        Investor Relations,         Tel: +44 20 7901 
                        London                                 7882 
                       Investor Relations,         Tel: +44 20 7901 
 Anna Mallere           London                                 7814 
 Maksut Zhapabayev     Corporate Communications,    Tel: +7 727 244 
                        Almaty                                03 53 
====================  ==========================  ================= 
 Instinctif Partners 
====================  ==========================  ================= 
                                                   Tel: +44 20 7457 
 David Simonson                                                2020 
====================  ==========================  ================= 
 

REGISTERED OFFICE

6th Floor, Cardinal Place, 100 Victoria Street, London SW1E 5JL, United Kingdom.

NOTES TO EDITORS

KAZ Minerals PLC ("KAZ Minerals" or "the Group") is a high growth copper company focused on large scale, low cost, open pit mining in Kazakhstan. It operates the Bozshakol and Aktogay open pit copper mines in the Pavlodar and East regions of Kazakhstan, three underground mines and associated concentrators in the East Region of Kazakhstan and the Bozymchak copper-gold mine in Kyrgyzstan. In 2016, total copper cathode equivalent output was 140 kt with by-products of 75 kt of zinc in concentrate, 120 koz of gold bar equivalent and 3,103 koz of silver bar equivalent.

The Group's new operations at Bozshakol and Aktogay are delivering one of the highest growth rates in the industry and transforming KAZ Minerals into a company dominated by world class, open pit copper mines.

Bozshakol is a first quartile asset on the global cost curve and will have an annual ore processing capacity of 30 million tonnes when fully ramped up and a mine life of 40 years at a copper grade of 0.36%. The mine and processing facilities will produce an average of 100 kt of copper cathode equivalent and 120 koz of gold in concentrate per year over the first 10 years of operations.

Aktogay is a large scale, open pit mine similar to Bozshakol, with a mine life of more than 50 years and average copper grades of 0.37% (oxide) and 0.33% (sulphide). Aktogay commenced production of copper cathode from oxide ore in December 2015 and copper in concentrate production from sulphide ore commenced in February 2017. The sulphide concentrator will have an annual ore processing capacity of 25 million tonnes when fully ramped up. Aktogay is competitively positioned on the global cost curve and will produce an average of 90 kt of copper cathode equivalent from sulphide ore and around 20 kt of copper cathode from oxide ore per year over the first 10 years of operations.

KAZ Minerals is listed on the London Stock Exchange, the Kazakhstan Stock Exchange and the Hong Kong Stock Exchange and employs around 13,000 people, principally in Kazakhstan.

This announcement contains inside information.

GROUP PRODUCTION SUMMARY

 
                                           9m       9m        Q3       Q2       Q3 
                                         2017     2016      2017     2017     2016 
 ==================================  ========  =======  ========  =======  ======= 
 Ore extraction                  kt    51,380   35,764    16,959   17,537   13,665 
============================  =====  ========  =======  ========  =======  ======= 
 Ore processed                   kt    30,254    9,717    12,025   10,529    4,969 
============================  =====  ========  =======  ========  =======  ======= 
 Average copper 
  grade processed                 %      0.73     1.07      0.68     0.73     0.88 
============================  =====  ========  =======  ========  =======  ======= 
 
 Ore to leach pads               kt    10,867   12,742     2,570    4,084    4,063 
============================  =====  ========  =======  ========  =======  ======= 
 
 Copper production(1)            kt     193.3     98.6      75.3     65.9     42.3 
============================  =====  ========  =======  ========  =======  ======= 
    Bozshakol                    kt      78.8     26.8      26.8     29.1     16.7 
============================  =====  ========  =======  ========  =======  ======= 
    Aktogay sulphide             kt      45.8        -      23.2     15.4        - 
============================  =====  ========  =======  ========  =======  ======= 
    Aktogay oxide                kt      18.4     12.0       8.0      5.7      6.6 
============================  =====  ========  =======  ========  =======  ======= 
    East Region & Bozymchak      kt      50.3     59.8      17.3     15.7     19.0 
============================  =====  ========  =======  ========  =======  ======= 
 
 Zinc in concentrate             kt      45.8     56.2      13.5     16.8     16.6 
============================  =====  ========  =======  ========  =======  ======= 
 Gold production(2)             koz     137.8     85.7      44.8     50.4     40.6 
============================  =====  ========  =======  ========  =======  ======= 
 Silver production(2)           koz     2,708    2,299       952      961      739 
============================  =====  ========  =======  ========  =======  ======= 
 

(1) Payable metal in concentrate and copper cathode from Aktogay oxide ore.

(2) Payable metal in concentrate.

Copper production increased by 14% to 75.3 kt in Q3 from 65.9 kt in Q2 2017, as the Aktogay sulphide concentrator continued its successful ramp up, supported by seasonally higher output from the oxide operations. Copper production also increased in the East Region and Bozymchak by 1.6 kt compared to the previous quarter as ore stockpiled in Q2 was processed. In the nine months to 30 September 2017, copper production almost doubled to 193.3 kt from 98.6 kt in the prior year period due to the contribution from sulphide operations at Bozshakol and Aktogay. Following a strong performance from the Aktogay sulphide concentrator in the year to date, supported by a higher than anticipated copper grade, Group copper production guidance has been raised to 250-270 kt.

Ore extraction in Q3 reduced by 3% to 17.0 million tonnes from 17.5 million tonnes in the previous quarter mainly due to reduced mining of oxide ore at Aktogay, partially offset by the increased extraction of sulphide ore. Ore extraction in the nine months to 30 September 2017 was 44% higher than the prior year period, reflecting the increased mining activity at Bozshakol and Aktogay.

Ore processed increased to 12.0 million tonnes in Q3 from 10.5 million tonnes in the previous quarter, as the Aktogay concentrator raised throughput volumes. In the nine months to 30 September 2017 processing volumes rose by over three times compared to the prior year period, due to the higher volumes processed at Bozshakol and the start-up of the Aktogay sulphide concentrator.

The average grade of copper ore processed in Q3 reduced to 0.68% from 0.73% in the prior quarter as grades at Bozshakol and Aktogay were slightly lower, in particular as a reduced proportion of high grade supergene enriched ore was processed at Aktogay, as expected. Processing feed grades of 0.73% in the nine months to 30 September 2017 compare to 1.07% in the prior year period, when a greater proportion of ore processed by the Group was accounted for by the higher grade underground mines in the East Region.

Lower zinc grades in the East Region resulted in a 20% reduction in output compared to the previous quarter, to 13.5 kt. Zinc output in the nine months to 30 September was 19% lower than in the prior year period due to the closure of the Yubileyno-Snegirikhinsky mine and the temporary adoption of a six day week at the Orlovsky mine for maintenance works. At the Artemyevsky mine, extraction has not moved to higher grade zinc areas as planned in the second half of 2017 and accordingly guidance for zinc output in 2017 is revised to 60-65 kt.

As anticipated, gold output in Q3 was 11% lower compared to the previous quarter, with gold grades at Bozshakol reducing from the temporarily elevated levels in the first half of the year. Silver production was in line with the previous quarter.

Gold production for the first nine months of 2017 was 61% higher than the prior year period, and silver production was 18% higher, due to increased production at Bozshakol. Strong gold and silver output in the year to date results in increased Group guidance for 2017, to 160-180 koz of gold production and 3,450-3,700 koz of silver production.

BOZSHAKOL

 
                                       9m       9m      Q3      Q2      Q3 
                                     2017     2016    2017    2017    2016 
 ===============================  =======  =======  ======  ======  ====== 
 Ore extraction               kt   28,660   19,482   9,234   9,522   8,466 
=========================  =====  =======  =======  ======  ======  ====== 
    Sulphide                  kt   14,462    8,894   5,429   4,778   4,325 
=========================  =====  =======  =======  ======  ======  ====== 
    Clay                      kt   14,198   10,588   3,805   4,744   4,141 
=========================  =====  =======  =======  ======  ======  ====== 
 
 Ore processed                kt   18,498    6,152   6,808   6,630   3,862 
=========================  =====  =======  =======  ======  ======  ====== 
 
 Copper 
================================  =======  =======  ======  ======  ====== 
 Average copper 
  grade processed              %     0.54     0.56    0.51    0.56    0.56 
=========================  =====  =======  =======  ======  ======  ====== 
 Copper in ore processed      kt    100.1     34.4    34.5    37.0    21.6 
=========================  =====  =======  =======  ======  ======  ====== 
 Copper recovery 
  rate                         %     82.4     81.5    81.3    82.4    80.9 
=========================  =====  =======  =======  ======  ======  ====== 
 Copper in concentrate        kt     82.5     28.1    28.1    30.4    17.5 
=========================  =====  =======  =======  ======  ======  ====== 
 Copper production(1)         kt     78.8     26.8    26.8    29.1    16.7 
=========================  =====  =======  =======  ======  ======  ====== 
 
 Gold 
================================  =======  =======  ======  ======  ====== 
 Average gold grade 
  processed                  g/t     0.28     0.34    0.25    0.29    0.37 
=========================  =====  =======  =======  ======  ======  ====== 
 Gold recovery rate            %     57.6     59.0    55.5    59.3    58.3 
=========================  =====  =======  =======  ======  ======  ====== 
 Gold in concentrate         koz     97.4     39.6    30.2    36.7    26.6 
=========================  =====  =======  =======  ======  ======  ====== 
 Gold production(1)          koz     91.1     37.7    28.2    34.4    25.4 
=========================  =====  =======  =======  ======  ======  ====== 
 
 Silver production(1)        koz      517      158     156     200     100 
=========================  =====  =======  =======  ======  ======  ====== 
 

(1) Payable metal in concentrate.

Ore extraction at Bozshakol reduced slightly compared to the previous quarter but continued to be ahead of the rate required to feed the sulphide and clay ore concentrators, with 9.2 million tonnes of ore extracted and 6.8 million tonnes processed in the period. Ore extraction of 28.7 million tonnes in the first nine months of 2017 was 47% higher than the 19.5 million tonnes mined in the prior year period, when the sulphide plant first commenced production.

The quantity of ore processed increased at both concentrators quarter on quarter. The sulphide plant operated at 93% of ore throughput capacity over the quarter and achieved 100% of design capacity in the month of August. The clay plant continued its successful ramp up, reaching 81% of design throughput in Q3 (Q2 2017: 69%). In the first nine months of 2017, ore processed was three times higher than the prior year period, when the ramp up of the sulphide plant commenced.

Copper production reduced slightly in Q3 to 26.8 kt, from 29.1 kt in the previous quarter, as a lower copper grade was only partially offset by the increase in volume processed. The average grade processed in Q3 was 9% lower at 0.51% (Q2 2017: 0.56%) and was 0.49% in the main sulphide plant (Q2 2017: 0.54%). Average recovery rates reduced slightly to 81.3%, partly reflecting the higher proportion of volumes attributable to clay operations, which recorded a recovery rate of 71.3%. Copper production in the nine months to 30 September 2017 was 78.8 kt, almost three times higher than the prior year period, in line with the increase in ore processed.

Gold and silver production in Q3 2017 reduced by 18% and 22% respectively versus Q2, mainly due to a reduction in grades, following temporarily elevated levels in the first half of the year. The gold recovery rate reduced to 55.5%, partly reflecting the lower recoveries from the clay plant during ramp up. Gold production in the nine months to 30 September 2017 was 2.4 times higher than the prior year period when the sulphide concentrator was in the first year of its ramp up.

Bozshakol's Q4 production will be impacted by a maintenance shut down scheduled to take place in November, however it remains on track for 2017 copper production within the guidance range of 100-110 kt. Despite lower gold grades anticipated in Q4 2017, gold production is expected to be 10 koz higher than previously guided, at 110-120 koz.

AKTOGAY

 
                                      9m       9m      Q3      Q2      Q3 
                                    2017     2016    2017    2017    2016 
 ==============================  =======  =======  ======  ======  ====== 
 Ore extraction              kt   19,778   12,742   6,756   7,003   4,063 
=========================  ====  =======  =======  ======  ======  ====== 
    Oxide                    kt   10,867   12,742   2,570   4,084   4,063 
=========================  ====  =======  =======  ======  ======  ====== 
    Sulphide                 kt    8,911        -   4,186   2,919       - 
=========================  ====  =======  =======  ======  ======  ====== 
 
 Oxide 
===============================  =======  =======  ======  ======  ====== 
 Oxide ore to leach 
  pads                       kt   10,867   12,742   2,570   4,084   4,063 
=========================  ====  =======  =======  ======  ======  ====== 
 Grade                        %     0.38     0.40    0.27    0.39    0.38 
=========================  ====  =======  =======  ======  ======  ====== 
 Copper cathode              kt     18.4     12.0     8.0     5.7     6.6 
=========================  ====  =======  =======  ======  ======  ====== 
 
 Sulphide 
===============================  =======  =======  ======  ======  ====== 
 Sulphide ore processed      kt    8,676        -   4,102   2,937       - 
=========================  ====  =======  =======  ======  ======  ====== 
 Average grade processed      %     0.70        -    0.65    0.72       - 
=========================  ====  =======  =======  ======  ======  ====== 
 Recovery rate                %     78.7        -    90.7    76.5       - 
=========================  ====  =======  =======  ======  ======  ====== 
 Copper in concentrate       kt     48.0        -    24.3    16.2       - 
=========================  ====  =======  =======  ======  ======  ====== 
 Copper production(1)        kt     45.8        -    23.2    15.4       - 
=========================  ====  =======  =======  ======  ======  ====== 
 
 Total copper production     kt     64.2     12.0    31.2    21.1     6.6 
=========================  ====  =======  =======  ======  ======  ====== 
 

(1) Payable metal in concentrate.

Sulphide ore extraction at Aktogay rose by 43% in Q3 to 4.2 million tonnes, compared to 2.9 million tonnes in the previous quarter, to feed the ramp up of the sulphide concentrator. Oxide ore extraction reduced to 2.6 million tonnes (Q2 2017: 4.1 million tonnes), in line with requirements, as the oxide leach pads were adequately supplied in prior periods. The copper grade of oxide ore placed on leach pads in the quarter reduced to 0.27% (Q2 2017: 0.39%) due to the planned mining of lower grade sections. Total ore extraction in the nine months to 30 September 2017 was 55% higher than the prior year period, reflecting the commencement of sulphide ore mining in 2017.

Copper cathode production at the SX/EW plant increased to 8.0 kt (Q2 2017: 5.7 kt) due to higher ambient temperatures in the summer period and efficiencies in the SX/EW process, with improved equipment availability rates and high levels of copper in solution. Cathode production in the nine months to 30 September 2017 was 18.4 kt (nine months to 30 September 2016: 12.0 kt). Q4 oxide production will be impacted by colder conditions, with full year production expected to be up to 25 kt.

The sulphide concentrator commenced production in February 2017 and following a successful ramp up during the quarter, was declared commercial at the start of October 2017. Ore processed was 66% of design capacity over Q3 2017, 40% above the previous quarter. A scheduled shut down for maintenance including the replacement of mill linings was successfully completed in September 2017.

Copper production from sulphide ore increased by 51% to 23.2 kt in Q3 2017 as the increase in ore throughput was partially offset by an expected reduction in the copper grade. The grade of copper in sulphide ore processed reduced to 0.65% in Q3 from 0.72% in the previous quarter, when copper volumes benefited from a higher proportion of material from a layer of supergene enriched material at the top of the ore body.

With higher oxide production of up to 25 kt expected for the full year, and following good progress in the ramp up of the sulphide plant, overall copper production guidance for Aktogay in 2017 is increased to 85-95 kt.

EAST REGION & BOZYMCHAK

Copper

 
                                             9m      9m      Q3      Q2      Q3 
                                           2017    2016    2017    2017    2016 
 ======================================  ======  ======  ======  ======  ====== 
 Ore extraction                      kt   2,942   3,540     969   1,012   1,136 
==============================  =======  ======  ======  ======  ======  ====== 
 
 Ore processed                       kt   3,080   3,565   1,115     962   1,107 
==============================  =======  ======  ======  ======  ======  ====== 
    Orlovsky concentrator            kt     795     972     249     270     290 
==============================  =======  ======  ======  ======  ======  ====== 
                                  grade 
                                    (%)    3.69    3.59    3.63    3.57    3.81 
 ======================================  ======  ======  ======  ======  ====== 
    Nikolayevsky concentrator        kt   1,045   1,311     451     275     403 
==============================  =======  ======  ======  ======  ======  ====== 
                                  grade 
                                    (%)    1.50    1.56    1.50    1.47    1.54 
 ======================================  ======  ======  ======  ======  ====== 
    Belousovsky concentrator         kt     476     491     159     162     155 
==============================  =======  ======  ======  ======  ======  ====== 
                                  grade 
                                    (%)    1.55    1.55    1.51    1.62    1.59 
 ======================================  ======  ======  ======  ======  ====== 
    Bozymchak concentrator           kt     764     791     256     255     259 
==============================  =======  ======  ======  ======  ======  ====== 
                                  grade 
                                    (%)    0.89    0.88    0.89    0.89    0.92 
 ======================================  ======  ======  ======  ======  ====== 
 Average grade processed              %    1.92    1.96    1.84    1.93    1.99 
==============================  =======  ======  ======  ======  ======  ====== 
 Average recovery 
  rate                                %    89.9    89.3    89.4    89.2    89.4 
==============================  =======  ======  ======  ======  ======  ====== 
 
 Copper in concentrate               kt    53.2    62.4    18.3    16.6    19.7 
==============================  =======  ======  ======  ======  ======  ====== 
    Orlovsky concentrator            kt    26.7    31.3     8.2     8.7     9.9 
==============================  =======  ======  ======  ======  ======  ====== 
    Nikolayevsky concentrator        kt    14.1    18.3     6.1     3.6     5.6 
==============================  =======  ======  ======  ======  ======  ====== 
    Belousovsky concentrator         kt     6.4     6.5     2.0     2.3     2.1 
==============================  =======  ======  ======  ======  ======  ====== 
    Bozymchak concentrator           kt     6.0     6.3     2.0     2.0     2.1 
==============================  =======  ======  ======  ======  ======  ====== 
 
 Copper production(1)                kt    50.3    59.8    17.3    15.7    19.0 
==============================  =======  ======  ======  ======  ======  ====== 
 

(1) Payable metal in concentrate.

Ore extraction in the East Region and Bozymchak was 4% lower in Q3 compared to the previous quarter, although the quantity of ore processed increased by 16% due to the processing of stockpiled material at the Nikolayevsky concentrator from the Artemyevsky mine. In the nine months to 30 September 2017, ore extraction was 17% lower and ore processed was 14% lower than in the prior year period due to the closure of the Yubileyno-Snegirikhinsky mine at the end of 2016 and the adoption of a six day week at the Orlovsky mine for ventilation works from the second half of 2016.

Due to the processing of stockpiled ore from the Artemyevsky mine, volumes at the Nikolayevsky concentrator increased by 64% to 451 kt in Q3 compared to Q2 2017 whilst volumes at the other three concentrators were similar to the previous quarter. The average copper grade processed reduced slightly from 1.93% in Q2 2017 to 1.84% in Q3, mainly due to the increased volumes of lower grade ore processed at the Nikolayevsky concentrator.

The average grade of copper in ore processed in the nine months to 30 September 2017 reduced slightly to 1.92% due to lower volumes from the copper rich Orlovsky mine, where a six day week was adopted from the second half of 2016, leading to an 18% reduction in processing volumes.

Copper production increased by 10% to 17.3 kt in Q3 compared to the previous quarter, reflecting the additional volumes processed at Nikolayevsky. Copper production for the first nine months of 2017 of 50.3 kt was 16% lower than the prior year period due to the closure of the Yubileyno-Snegirikhinsky mine and lower output at Orlovsky.

Copper production in the East Region and Bozymchak is on track to meet the 2017 full year guidance of around 65 kt.

By-products

 
                                      9m      9m      Q3      Q2      Q3 
 Zinc                               2017    2016    2017    2017    2016 
================================  ======  ======  ======  ======  ====== 
 Zinc bearing ore 
  processed                   kt   2,316   2,774     859     707     848 
=========================  =====  ======  ======  ======  ======  ====== 
 Average grade processed       %    2.82    2.87    2.40    3.27    2.82 
=========================  =====  ======  ======  ======  ======  ====== 
 Average recovery 
  rate                         %    70.0    70.6    65.3    72.7    69.5 
=========================  =====  ======  ======  ======  ======  ====== 
 Zinc in concentrate          kt    45.8    56.2    13.5    16.8    16.6 
=========================  =====  ======  ======  ======  ======  ====== 
 
 Gold 
================================  ======  ======  ======  ======  ====== 
 Gold bearing ore 
  processed                   kt   3,080   3,565   1,115     962   1,107 
=========================  =====  ======  ======  ======  ======  ====== 
 Average grade processed     g/t    0.80    0.81    0.77    0.87    0.80 
=========================  =====  ======  ======  ======  ======  ====== 
 Average recovery 
  rate                         %    61.4    55.4    62.6    62.3    57.2 
=========================  =====  ======  ======  ======  ======  ====== 
 Gold in concentrate         koz    48.8    51.1    17.2    16.7    16.3 
=========================  =====  ======  ======  ======  ======  ====== 
 Gold production(1)          koz    45.9    48.0    16.2    15.7    15.2 
=========================  =====  ======  ======  ======  ======  ====== 
 
 Silver 
================================  ======  ======  ======  ======  ====== 
 Silver bearing 
  ore processed               kt   3,080   3,565   1,115     962   1,107 
=========================  =====  ======  ======  ======  ======  ====== 
 Average grade processed     g/t    35.5    36.3    34.9    40.3    34.2 
=========================  =====  ======  ======  ======  ======  ====== 
 Average recovery 
  rate                         %    62.5    55.3    63.1    60.5    55.9 
=========================  =====  ======  ======  ======  ======  ====== 
 Silver in concentrate       koz   2,198   2,302     789     754     680 
=========================  =====  ======  ======  ======  ======  ====== 
 Silver production(1)        koz   2,000   2,141     718     686     639 
=========================  =====  ======  ======  ======  ======  ====== 
 

Payable metal in concentrate.

While zinc bearing ore processing volumes increased in Q3 2017 compared to the previous quarter, zinc in concentrate production of 13.5 kt was 20% lower due to delayed access to higher zinc grade areas at Artemyevsky. The zinc grade processed at Orlovsky also reduced to 3.01% in Q3 from 3.76% in Q2 2017. In the nine months to 30 September 2017 zinc in concentrate production reduced by 19% compared to the prior year period, mainly due to lower output from the Orlovsky mine. Following the delayed access to higher zinc grade areas at Artemyevsky in Q3, guidance for zinc output in 2017 has been revised to 60-65 kt.

Gold production in Q3 increased by 3% from the previous quarter as higher processing volumes offset a lower average gold grade of 0.77 g/t (Q2 2017: 0.87 g/t). Gold production in the first nine months of 2017 was 4% below the prior year period as a result of lower output from Orlovsky and the closure of the Yubileyno-Snegirikhinsky mine, offset by an increased average recovery rate of 61% (nine months to 30 September 2016: 55%).

Silver production increased by 5% in Q3 compared to Q2 2017 due to higher recovery rates, but decreased by 7% in the nine months to 30 September 2017 compared to the prior year period due to the closure of the Yubileyno-Snegirikhinsky mine and reduced output from Orlovsky.

Strong production in the year to date is expected to result in gold output from the East Region and Bozymchak being towards the upper end of the 50-60 koz range for 2017 and silver guidance is increased to 2,600-2,850 koz.

INTERIM MANAGEMENT STATEMENT

Financial performance

Sales Volumes

The following table sets out the sales volumes of the Group's major products and includes pre-commercial sales volumes.

 
                                       9m      9m 
                                     2017    2016 
 ================================  ======  ====== 
 Copper cathode                kt    85.4    68.2 
==========================  =====  ======  ====== 
 Copper in concentrate(1)      kt   107.8    27.1 
==========================  =====  ======  ====== 
 Zinc in concentrate           kt    45.4    56.3 
==========================  =====  ======  ====== 
 Gold bar                     koz    43.1    41.0 
==========================  =====  ======  ====== 
 Gold in concentrate(1)       koz    84.1    39.0 
==========================  =====  ======  ====== 
 Silver bar                   koz   2,158   2,118 
==========================  =====  ======  ====== 
 Silver in concentrate(1)     koz     578     204 
==========================  =====  ======  ====== 
 

(1) Shown as payable metal in concentrate.

Copper sales totalled 193.2 kt in the nine months to 30 September 2017, an increase of 97.9 kt over the prior year period as the Bozshakol sulphide plant approached its design capacity and the Aktogay sulphide plant achieved commercial production. Copper cathode sales increased by 25% compared to the prior year period due to higher output from the Aktogay oxide plant and from toll processing of copper in concentrate from Bozshakol (9.1 kt) and Aktogay sulphide (7.7 kt) at the Balkhash smelter. These increases were partly offset by lower cathode sales from the East Region and Bozymchak operations in line with lower production. Copper in concentrate sales increased to 107.8 kt, comprised of 70.2 kt from Bozshakol, 35.9 kt from the Aktogay sulphide plant, and 1.8 kt from the East Region and Bozymchak.

Zinc in concentrate sales in the nine months to 30 September 2017 were 19% below the prior year period reflecting lower production.

Gold sales of 127.1 koz in the nine months to 30 September 2017 represent an increase of 47.1 koz from the prior year period when the sulphide concentrator was in the first year of its ramp up. The increased sales reflect higher output from Bozshakol sulphide as it approached design capacity in the current year and higher volumes from East Region and Bozymchak following a release of work-in-progress in 2017 from the Balkhash smelter. Gold bar sales were lower than production in the current year period due to the timing of sales to the National Bank of Kazakhstan.

Silver sales of 2,736 koz in the first nine months of the year were 414 koz higher compared to the prior year period due to increased production from Bozshakol. Silver bar sales were 14% higher than production in the period due to a reduction in finished goods inventory.

The Aktogay sulphide plant has been declared commercial from 1 October 2017, from which date all revenues and operating costs are recorded in the income statement.

Commodity Prices

The following table sets out the average realised prices for the Group's major products including pre-commercial sales from the Aktogay sulphide project for the current period and for the Aktogay oxide and Bozshakol sulphide projects in the comparative prior period:

 
                                           9m      9m 
                                         2017    2016 
 ====================================  ======  ====== 
 Copper cathode               $/tonne   6,020   4,743 
==========================  =========  ======  ====== 
 Copper in concentrate(1)     $/tonne   5,525   4,095 
==========================  =========  ======  ====== 
 Zinc in concentrate(1)       $/tonne   1,923   1,131 
==========================  =========  ======  ====== 
 Gold bar                     $/tr.oz   1,260   1,271 
==========================  =========  ======  ====== 
 Gold in concentrate(1)       $/tr.oz   1,278   1,313 
==========================  =========  ======  ====== 
 Silver bar                   $/tr.oz      17      17 
==========================  =========  ======  ====== 
 Silver in concentrate(1)     $/tr.oz      16      19 
==========================  =========  ======  ====== 
 

(1) The realised price for metal in concentrate is shown after the deduction of any applicable treatment and refining costs.

The following table sets out the average LME/LBMA prices:

 
                         9m      9m 
                       2017    2016 
 ==================  ======  ====== 
 Copper     $/tonne   5,953   4,725 
========  =========  ======  ====== 
 Zinc       $/tonne   2,783   1,955 
========  =========  ======  ====== 
 Gold       $/tr.oz   1,261   1,260 
========  =========  ======  ====== 
 Silver     $/tr.oz      17      17 
========  =========  ======  ====== 
 

The realised prices for the products sold will differ from the average LME/LBMA prices during the period due to sales not being made evenly over the period. Premiums or discounts to metal exchange prices negotiated with customers also impact average realised prices.

Most of the Group's sales agreements are based on provisional pricing with the final pricing usually determined by the average market price of the respective metal in the month (for silver), the month following (for copper cathode and zinc concentrate) or the second month following (for copper concentrate including by-products) dispatch to the customer. The volume of goods sold under quotational pricing has significantly increased due to higher concentrate sales volumes while the increase in copper and zinc prices has resulted in positive provisional pricing adjustments being recognised in the period in respect of copper and zinc concentrate sales made in late 2016, raising the reported realised prices. At 30 September 2017, the Group's provisionally priced volumes and their respective average provisional prices were:

 
                                      Q3 2017 
=======================  ================================= 
                                 Volumes     Provisional 
                                                price 
=======================  =====  ========  ================ 
 Copper cathode            kt        2.8   $/tonne   6,508 
=======================  =====  ========  ========  ====== 
 Copper in concentrate     kt       31.0   $/tonne   5,788 
=======================  =====  ========  ========  ====== 
 Zinc in concentrate       kt        5.2   $/tonne   1,867 
=======================  =====  ========  ========  ====== 
 Gold                     koz       23.7   $/tr.oz   1,287 
=======================  =====  ========  ========  ====== 
 Silver                   koz         90   $/tr.oz    17 
=======================  =====  ========  ========  ====== 
 

Commodity Hedging

At 30 September 2017, there were no commodity hedges in place.

Exchange Rates

The KZT/$ exchange rate at 30 September 2017 was KZT/$ 341.19 compared to KZT/$ 321.46 at 30 June 2017. The average exchange rate for the first nine months of 2017 was KZT/$ 323.20, compared to an average rate of KZT/$ 344.57 for the same period last year.

Net debt and cash position

Net debt decreased to $2,220 million at 30 September 2017 from $2,442 million at 30 June 2017 due to strong operating cash flows and the receipt of $74 million project VAT related to Bozshakol and Aktogay, partly offset by interest paid of $92 million under the Group debt facilities. Mineral extraction tax and royalty payments of $35 million and income tax payments of $22 million were made during the quarter. Expansionary capex at Bozshakol and Aktogay was limited as final retention payments have been postponed and may be deferred further into 2018. In addition, there have been no payments at Aktogay to purchase rather than lease rail wagons, as it has now been determined that these are not required. Total cash and cash equivalents at 30 September 2017 amounted to $1,352 million, an increase from $1,223 million at 30 June 2017.

At 30 September 2017, gross debt (before amortised fees) was $3,606 million compared to $3,700 million at 30 June 2017, following the scheduled repayments on the CDB Bozshakol/Bozymchak facilities of $91 million and the CDB Aktogay CNY facility of $6 million. Of the gross debt (before amortised fees) at 30 September 2017, $1,540 million related to the CDB Bozshakol/Bozymchak facilities, $1,466 million to the CDB Aktogay facilities, $300 million to the Development Bank of Kazakhstan (DBK) facility and $300 million to the PXF facility.

APPIX - GROUP PRODUCTION SUMMARY

Copper mining & processing

 
                                       9m       9m        Q3       Q2       Q3 
                                     2017     2016      2017     2017     2016 
 ==============================  ========  =======  ========  =======  ======= 
 Ore extraction              kt    51,380   35,764    16,959   17,537   13,665 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozshakol                kt    28,660   19,482     9,234    9,522    8,466 
=========================  ====  ========  =======  ========  =======  ======= 
    Aktogay                  kt    19,778   12,742     6,756    7,003    4,063 
=========================  ====  ========  =======  ========  =======  ======= 
    East Region              kt     2,246    2,824       743      777      920 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozymchak                kt       696      716       226      235      216 
=========================  ====  ========  =======  ========  =======  ======= 
 Average grade mined          %      0.62     0.66      0.59     0.61     0.67 
=========================  ====  ========  =======  ========  =======  ======= 
 Copper in ore mined         kt     318.3    235.6      99.6    107.7     91.0 
=========================  ====  ========  =======  ========  =======  ======= 
 
 Ore processed               kt    30,254    9,717    12,025   10,529    4,969 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozshakol                kt    18,498    6,152     6,808    6,630    3,862 
=========================  ====  ========  =======  ========  =======  ======= 
    Aktogay (sulphide)       kt     8,676        -     4,102    2,937        - 
=========================  ====  ========  =======  ========  =======  ======= 
    East Region              kt     2,316    2,774       859      707      848 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozymchak                kt       764      791       256      255      259 
=========================  ====  ========  =======  ========  =======  ======= 
 Average grade processed      %      0.73     1.07      0.68     0.73     0.88 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozshakol                 %      0.54     0.56      0.51     0.56     0.56 
=========================  ====  ========  =======  ========  =======  ======= 
    Aktogay (sulphide)        %      0.70        -      0.65     0.72        - 
=========================  ====  ========  =======  ========  =======  ======= 
    East Region               %      2.26     2.27      2.12     2.31     2.32 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozymchak                 %      0.89     0.88      0.89     0.89     0.92 
=========================  ====  ========  =======  ========  =======  ======= 
 Copper in ore processed     kt     220.3    104.3      81.8     76.7     43.6 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozshakol                kt     100.1     34.4      34.5     37.0     21.6 
=========================  ====  ========  =======  ========  =======  ======= 
    Aktogay (sulphide)       kt      61.0        -      26.8     21.2        - 
=========================  ====  ========  =======  ========  =======  ======= 
    East Region              kt      52.4     62.9      18.2     16.3     19.6 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozymchak                kt       6.8      7.0       2.3      2.2      2.4 
=========================  ====  ========  =======  ========  =======  ======= 
 Average recovery 
  rate                        %      83.4     86.7      86.4     82.4     85.2 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozshakol                 %      82.4     81.5      81.3     82.4     80.9 
=========================  ====  ========  =======  ========  =======  ======= 
    Aktogay (sulphide)        %      78.7        -      90.7     76.5        - 
=========================  ====  ========  =======  ========  =======  ======= 
    East Region               %      90.0     89.2      89.4     89.3     89.3 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozymchak                 %      89.3     90.9      89.6     88.6     90.6 
=========================  ====  ========  =======  ========  =======  ======= 
 
 Aktogay oxide ore 
  to leach pads              kt    10,867   12,742     2,570    4,084    4,063 
=========================  ====  ========  =======  ========  =======  ======= 
    Grade                     %      0.38     0.40      0.27     0.39     0.38 
=========================  ====  ========  =======  ========  =======  ======= 
 

Copper production

 
                                        9m      9m      Q3      Q2      Q3 
 Bozshakol                            2017    2016    2017    2017    2016 
=================================  =======  ======  ======  ======  ====== 
    Copper concentrate         kt    370.8   117.3   127.1   136.5    72.1 
==========================  =====  =======  ======  ======  ======  ====== 
    Copper in concentrate      kt     82.5    28.1    28.1    30.4    17.5 
==========================  =====  =======  ======  ======  ======  ====== 
 Aktogay Sulphide 
=================================  =======  ======  ======  ======  ====== 
    Copper concentrate         kt    202.7       -   108.2    67.0       - 
==========================  =====  =======  ======  ======  ======  ====== 
    Copper in concentrate      kt     48.0       -    24.3    16.2       - 
==========================  =====  =======  ======  ======  ======  ====== 
 East Region 
=================================  =======  ======  ======  ======  ====== 
    Copper concentrate         kt    225.4   280.1    76.0    69.0    84.5 
==========================  =====  =======  ======  ======  ======  ====== 
    Copper in concentrate      kt     47.2    56.1    16.3    14.6    17.6 
==========================  =====  =======  ======  ======  ======  ====== 
 Bozymchak 
=================================  =======  ======  ======  ======  ====== 
    Copper concentrate         kt     25.6    25.7     8.6     8.4     9.0 
==========================  =====  =======  ======  ======  ======  ====== 
    Copper in concentrate      kt      6.0     6.3     2.0     2.0     2.1 
==========================  =====  =======  ======  ======  ======  ====== 
 
 Total copper concentrate      kt    824.5   423.1   319.9   280.9   165.6 
==========================  =====  =======  ======  ======  ======  ====== 
 Total copper in 
  concentrate                  kt    183.7    90.5    70.7    63.2    37.2 
==========================  =====  =======  ======  ======  ======  ====== 
 
 Copper production(1)          kt    193.3    98.6    75.3    65.9    42.3 
==========================  =====  =======  ======  ======  ======  ====== 
    Bozshakol                  kt     78.8    26.8    26.8    29.1    16.7 
==========================  =====  =======  ======  ======  ======  ====== 
    Aktogay sulphide           kt     45.8       -    23.2    15.4       - 
==========================  =====  =======  ======  ======  ======  ====== 
    Aktogay oxide              kt     18.4    12.0     8.0     5.7     6.6 
==========================  =====  =======  ======  ======  ======  ====== 
    East Region                kt     44.6    53.7    15.4    13.8    16.9 
==========================  =====  =======  ======  ======  ======  ====== 
    Bozymchak                  kt      5.7     6.1     1.9     1.9     2.1 
==========================  =====  =======  ======  ======  ======  ====== 
 
 Copper cathodes               kt     85.8    70.0    31.4    28.8    26.1 
==========================  =====  =======  ======  ======  ======  ====== 
    Bozshakol (toll 
     processed)                kt      9.3       -     4.7     3.7       - 
==========================  =====  =======  ======  ======  ======  ====== 
    Aktogay sulphide 
     (toll processed)          kt      8.9       -     4.8     3.6       - 
===========================  ====  =======  ======  ======  ======  ====== 
    Aktogay oxide              kt     18.4    12.0     8.0     5.7     6.6 
==========================  =====  =======  ======  ======  ======  ====== 
    East Region (toll 
     processed)                kt     42.6    53.0    11.4    14.0    17.4 
==========================  =====  =======  ======  ======  ======  ====== 
    Bozymchak (toll 
     processed)                kt      6.6     5.0     2.5     1.8     2.1 
==========================  =====  =======  ======  ======  ======  ====== 
 
 

(1) Payable metal in concentrate and copper cathode from Aktogay oxide ore.

Zinc

 
                                              9m      9m      Q3      Q2      Q3 
                                            2017    2016    2017    2017    2016 
 ======================================  =======  ======  ======  ======  ====== 
 Zinc bearing ore 
  mined                              kt    2,246   2,824     743     777     920 
==============================  =======  =======  ======  ======  ======  ====== 
    Orlovsky                         kt      799     973     254     270     294 
==============================  =======  =======  ======  ======  ======  ====== 
    Artemyevsky                      kt      977     986     332     351     340 
==============================  =======  =======  ======  ======  ======  ====== 
    Irtyshsky                        kt      470     473     157     156     157 
==============================  =======  =======  ======  ======  ======  ====== 
    Yubileyno-Snegirikhinsky         kt        -     392       -       -     129 
==============================  =======  =======  ======  ======  ======  ====== 
 Zinc bearing ore 
  processed                          kt    2,316   2,774     859     707     848 
==============================  =======  =======  ======  ======  ======  ====== 
    Orlovsky concentrator            kt      795     972     249     270     290 
==============================  =======  =======  ======  ======  ======  ====== 
                                  grade 
                                    (%)     3.60    4.38    3.01    3.76    4.19 
 ======================================  =======  ======  ======  ======  ====== 
    Nikolayevsky concentrator        kt    1,045   1,311     451     275     403 
==============================  =======  =======  ======  ======  ======  ====== 
                                  grade 
                                    (%)     1.94    1.69    1.71    2.48    1.64 
 ======================================  =======  ======  ======  ======  ====== 
    Belousovsky concentrator         kt      476     491     159     162     155 
==============================  =======  =======  ======  ======  ======  ====== 
                                  grade 
                                    (%)     3.47    3.03    3.40    3.80    3.33 
 ======================================  =======  ======  ======  ======  ====== 
 Average grade 
  processed                           %     2.82    2.87    2.40    3.27    2.82 
==============================  =======  =======  ======  ======  ======  ====== 
 
 Zinc metal in 
  ore processed                      kt     65.4    79.7    20.6    23.1    23.9 
==============================  =======  =======  ======  ======  ======  ====== 
    Orlovsky concentrator            kt     28.6    42.6     7.5    10.1    12.1 
==============================  =======  =======  ======  ======  ======  ====== 
    Nikolayevsky concentrator        kt     20.2    22.2     7.7     6.8     6.6 
==============================  =======  =======  ======  ======  ======  ====== 
    Belousovsky concentrator         kt     16.5    14.9     5.3     6.2     5.2 
==============================  =======  =======  ======  ======  ======  ====== 
 Average recovery 
  rate                                %     70.0    70.6    65.3    72.7    69.5 
==============================  =======  =======  ======  ======  ======  ====== 
    Orlovsky concentrator             %     66.1    71.6    52.8    69.0    69.0 
==============================  =======  =======  ======  ======  ======  ====== 
    Nikolayevsky concentrator         %     75.2    70.5    73.6    80.6    72.4 
==============================  =======  =======  ======  ======  ======  ====== 
    Belousovsky concentrator          %     70.4    67.7    70.9    69.9    67.1 
==============================  =======  =======  ======  ======  ======  ====== 
 
 Zinc in concentrate                 kt     45.8    56.2    13.5    16.8    16.6 
==============================  =======  =======  ======  ======  ======  ====== 
    Orlovsky concentrator            kt     19.0    30.5     4.0     7.0     8.4 
==============================  =======  =======  ======  ======  ======  ====== 
    Nikolayevsky concentrator        kt     15.2    15.7     5.7     5.5     4.8 
==============================  =======  =======  ======  ======  ======  ====== 
    Belousovsky concentrator         kt     11.6    10.0     3.8     4.3     3.4 
==============================  =======  =======  ======  ======  ======  ====== 
 

Gold

 
                                              9m       9m       Q3        Q2      Q3 
                                            2017     2016     2017      2017    2016 
===========================  =========  ========  =======  =======  ========  ====== 
 Gold bearing ore 
  mined                             kt    31,602   23,022   10,203    10,534   9,602 
===========================  =========  ========  =======  =======  ========  ====== 
    Bozshakol                       kt    28,660   19,482    9,234     9,522   8,466 
===========================  =========  ========  =======  =======  ========  ====== 
    East Region                     kt     2,246    2,824      743       777     920 
===========================  =========  ========  =======  =======  ========  ====== 
    Bozymchak                       kt       696      716      226       235     216 
===========================  =========  ========  =======  =======  ========  ====== 
 Gold bearing ore 
  processed                         kt    21,578    9,717    7,923     7,592   4,969 
===========================  =========  ========  =======  =======  ========  ====== 
    Bozshakol                       kt    18,498    6,152    6,808     6,630   3,862 
===========================  =========  ========  =======  =======  ========  ====== 
                                 grade 
                                 (g/t)      0.28     0.34     0.25      0.29    0.37 
 =====================================  ========  =======  =======  ========  ====== 
    East Region                     kt     2,316    2,774      859       707     848 
===========================  =========  ========  =======  =======  ========  ====== 
                                 grade 
                                 (g/t)      0.52     0.56     0.49      0.57    0.53 
===========================  =========  ========  =======  =======  ========  ====== 
    Bozymchak                       kt       764      791      256       255     259 
===========================  =========  ========  =======  =======  ========  ====== 
                                 grade 
                                 (g/t)      1.67     1.68     1.68      1.69    1.68 
===========================  =========  ========  =======  =======  ========  ====== 
 Average grade processed           g/t      0.35     0.51     0.32      0.36    0.46 
===========================  =========  ========  =======  =======  ========  ====== 
 
 Gold in ore processed             koz     248.8    159.5     81.9      88.8    74.1 
===========================  =========  ========  =======  =======  ========  ====== 
    Bozshakol                      koz     169.3     67.3     54.4      62.0    45.7 
===========================  =========  ========  =======  =======  ========  ====== 
    East Region                    koz      38.5     49.4     13.6      12.9    14.4 
===========================  =========  ========  =======  =======  ========  ====== 
    Bozymchak                      koz      41.0     42.8     13.9      13.9    14.0 
===========================  =========  ========  =======  =======  ========  ====== 
 Average recovery 
  rate                               %      58.8     56.9     57.9      60.2    57.9 
===========================  =========  ========  =======  =======  ========  ====== 
    Bozshakol                        %      57.6     59.0     55.5      59.3    58.3 
===========================  =========  ========  =======  =======  ========  ====== 
    East Region                      %      38.7     32.1     41.0      40.1    30.7 
===========================  =========  ========  =======  =======  ========  ====== 
    Bozymchak                        %      82.8     82.2     83.8      83.1    84.5 
===========================  =========  ========  =======  =======  ========  ====== 
 Gold in concentrate               koz     146.2     90.7     47.4      53.4      42.9 
===========================  =========  ========  =======  =======  ========  ======== 
    Bozshakol                      koz      97.4     39.6     30.2      36.7      26.6 
===========================  =========  ========  =======  =======  ========  ======== 
    East Region                    koz      14.9     15.9      5.6       5.2       4.4 
===========================  =========  ========  =======  =======  ========  ======== 
    Bozymchak                      koz      33.9     35.2     11.6      11.5      11.9 
===========================  =========  ========  =======  =======  ========  ======== 
 
 Gold production(1)                koz     137.8     85.7     44.8      50.4      40.6 
===========================  =========  ========  =======  =======  ========  ======== 
    Bozshakol                      koz      91.1     37.7     28.2      34.4      25.4 
===========================  =========  ========  =======  =======  ========  ======== 
    Aktogay (sulphide) 
     (2)                           koz       0.8        -      0.4       0.3         - 
===========================  =========  ========  =======  =======  ========  ======== 
    East Region                    koz      14.0     14.9      5.2       4.9       4.1 
===========================  =========  ========  =======  =======  ========  ======== 
    Bozymchak                      koz      31.9     33.1     11.0      10.8      11.1 
===========================  =========  ========  =======  =======  ========  ======== 
 
 Gold bar produced 
  (toll processed)                 koz      52.3     41.0     23.7      13.6      15.7 
============================  ========  ========  =======  =======  ========  ======== 
    Bozshakol                      koz       8.8        -      5.2       3.6         - 
============================  ========  ========  =======  =======  ========  ======== 
    Aktogay (sulphide)(2)          koz       0.4        -      0.4         -         - 
===========================  =========  ========  =======  =======  ========  ======== 
    East Region                    koz      12.7     16.8      5.7       2.4       4.7 
===========================  =========  ========  =======  =======  ========  ======== 
    Bozymchak                      koz      30.4     24.2     12.4       7.6      11.0 
===========================  =========  ========  =======  =======  ========  ======== 
 
 

(1) Payable metal in concentrate.

(2) Minimal volume recovered from Aktogay material.

Silver

 
                                                9m        9m       Q3        Q2      Q3 
                                              2017      2016     2017      2017    2016 
 ============                             ========  ========  =======  ========  ====== 
 Silver bearing 
  ore mined                           kt    31,602    23,022   10,203    10,534   9,602 
==========================  ============  ========  ========  =======  ========  ====== 
    Bozshakol                         kt    28,660    19,482    9,234     9,522   8,466 
==========================  ============  ========  ========  =======  ========  ====== 
    East Region                       kt     2,246     2,824      743       777     920 
==========================  ============  ========  ========  =======  ========  ====== 
    Bozymchak                         kt       696       716      226       235     216 
==========================  ============  ========  ========  =======  ========  ====== 
 Silver bearing 
  ore processed                       kt    21,578     9,717    7,923     7,592   4,969 
==========================  ============  ========  ========  =======  ========  ====== 
    Bozshakol                         kt    18,498     6,152    6,808     6,630   3,862 
==========================  ============  ========  ========  =======  ========  ====== 
                                   grade 
                                   (g/t)      1.45      1.63     1.22      1.51    1.56 
 ============                             ========  ========  =======  ========  ====== 
    East Region                       kt     2,316     2,774      859       707     848 
==========================  ============  ========  ========  =======  ========  ====== 
                                   grade 
                                   (g/t)      43.5      43.2     41.9      50.6    41.2 
 ============                             ========  ========  =======  ========  ====== 
    Bozymchak                         kt       764       791      256       255     259 
==========================  ============  ========  ========  =======  ========  ====== 
                                   grade 
                                   (g/t)      11.4      12.1     11.3      11.8    11.2 
 ============                             ========  ========  =======  ========  ====== 
 Average grade 
  processed                          g/t       6.3      14.4      6.0       6.4     8.8 
==========================  ============  ========  ========  =======  ========  ====== 
 
 Silver in ore 
  processed                          koz     4,380     4,486    1,518     1,569   1,410 
==========================  ============  ========  ========  =======  ========  ====== 
    Bozshakol                        koz       863       323      268       322     194 
==========================  ============  ========  ========  =======  ========  ====== 
    East Region                      koz     3,236     3,856    1,156     1,151   1,123 
==========================  ============  ========  ========  =======  ========  ====== 
    Bozymchak                        koz       281       307       94        96      93 
==========================  ============  ========  ========  =======  ========  ====== 
 Average recovery 
  rate                                 %      63.3      55.2     63.4      62.3    56.1 
==========================  ============  ========  ========  =======  ========  ====== 
    Bozshakol                          %      66.6      54.4     64.8      69.0    57.1 
==========================  ============  ========  ========  =======  ========  ====== 
    East Region                        %      61.4      53.6     62.1      59.3    54.0 
==========================  ============  ========  ========  =======  ========  ====== 
    Bozymchak                          %      75.5      76.9     75.0      75.0    78.6 
==========================  ============  ========  ========  =======  ========  ====== 
 Silver in concentrate               koz     2,773     2,478      962       977     791 
==========================  ============  ========  ========  =======  ========  ====== 
    Bozshakol                        koz       575       176      173       223     111 
==========================  ============  ========  ========  =======  ========  ====== 
    East Region                      koz     1,986     2,066      719       682     607 
==========================  ============  ========  ========  =======  ========  ====== 
    Bozymchak                        koz       212       236       70        72      73 
==========================  ============  ========  ========  =======  ========  ====== 
 
 Silver production(1)                koz     2,708     2,299      952       961     739 
==========================  ============  ========  ========  =======  ========  ====== 
    Bozshakol                        koz       517       158      156       200     100 
==========================  ============  ========  ========  =======  ========  ====== 
    Aktogay (sulphide)(2)            koz       191         -       78        75       - 
==========================  ============  ========  ========  =======  ========  ====== 
    East Region                      koz     1,807     1,921      654       621     570 
==========================  ============  ========  ========  =======  ========  ====== 
    Bozymchak                        koz       193       220       64        65      69 
==========================  ============  ========  ========  =======  ========  ====== 
 
 Silver bar produced 
  (toll processed)                   koz     1,972     2,031      602       585     676 
===========================  ===========  ========  ========  =======  ========  ====== 
    Bozshakol                        koz        45         -       26        13       - 
==========================  ============  ========  ========  =======  ========  ====== 
    Aktogay (sulphide)(2)            koz        34         -       15        19       - 
==========================  ============  ========  ========  =======  ========  ====== 
    East Region                      koz     1,688     1,872      488       485     604 
==========================  ============  ========  ========  =======  ========  ====== 
    Bozymchak                        koz       205       159       73        68      72 
==========================  ============  ========  ========  =======  ========  ====== 
 
 

(1) Payable metal in concentrate.

(2) Minimal volume recovered from Aktogay material.

This information is provided by RNS

The company news service from the London Stock Exchange

END

MSCLLFFDIILEFID

(END) Dow Jones Newswires

October 26, 2017 02:00 ET (06:00 GMT)

Kaz Minerals (LSE:KAZ)
Historical Stock Chart
From Mar 2024 to Apr 2024 Click Here for more Kaz Minerals Charts.
Kaz Minerals (LSE:KAZ)
Historical Stock Chart
From Apr 2023 to Apr 2024 Click Here for more Kaz Minerals Charts.