TIDMKAZ

RNS Number : 2095M

KAZ Minerals PLC

27 July 2017

 
 
     KAZ MINERALS 
     PLC 
     6(TH) FLOOR 
     CARDINAL PLACE 
     100 VICTORIA 
     STREET 
     LONDON SW1E 5JL 
     Tel: +44 (0) 
     20 7901 7800 
  ================== 
 

27 July 2017

KAZ MINERALS GROUP Production Report for six months and THE second QUARTER Ended 30 June 2017

l H1 2017 copper production(1) more than doubled to 118 kt (H1 2016: 56 kt), on track for full year guidance of 225-260 kt

l Ramp up of new operations continues to deliver quarterly growth in copper production, Q2 2017: 66 kt (Q1 2017: 52 kt)

l Strong first half gold output of 93 koz (H1 2016: 45 koz)

l Bozshakol on track to achieve 2017 copper guidance and top end of gold guidance

-- H1 2017 copper production(2) of 52 kt (H1 2016: 10 kt) and gold production(2) of 63 koz (H1 2016: 12 koz), lower gold grades expected in H2

-- Sulphide plant at 93% of design ore throughput in Q2, full capacity expected in H2 2017

-- Clay plant continuing to ramp up in line with expectations, ore throughput at 69% in Q2

l Aktogay ramp up progressing well

-- Copper production(1) of 33 kt in H1 2017 (H1 2016: 5 kt)

-- Sulphide copper production(2) increased to 15 kt in Q2 (Q1 2017: 7 kt)

-- Concentrator ramping up faster than Bozshakol due to experience gained at identical operations and benefit of high grade supergene ore

-- On course to achieve 2017 guidance of 65-85 kt as concentrator ramps up to commercial levels in H2

l East Region and Bozymchak on track for copper production target

-- Copper production(2) of 33 kt in H1 2017 (H1 2016: 41 kt)

-- H1 zinc in concentrate production of 32 kt (H1 2016: 40 kt)

-- Full year gold and silver production expected to be towards the upper end of guidance

(1) Payable metal in concentrate and copper cathode from Aktogay oxide ore.

(2) Payable metal in concentrate.

Oleg Novachuk, Chief Executive, said: "I am pleased to report good progress in the ramp up of the new sulphide concentrator at Aktogay and a strong operational performance from our other assets. At Bozshakol, we expect to achieve 100% of design capacity in the second half of this year as planned. The operational performance has had a positive impact on unit costs supported by limited domestic inflation, with Aktogay and the East Region currently tracking below the guided full year cost range."

For further information please contact:

 
 KAZ Minerals 
  PLC 
====================  ==========================  ================= 
 Chris Bucknall        Investor Relations,         Tel: +44 20 7901 
                        London                                 7882 
                       Investor Relations,         Tel: +44 20 7901 
 Anna Mallere           London                                 7814 
 Maksut Zhapabayev     Corporate Communications,    Tel: +7 727 244 
                        Almaty                                03 53 
====================  ==========================  ================= 
 Instinctif Partners 
====================  ==========================  ================= 
                                                   Tel: +44 20 7457 
 David Simonson                                                2020 
====================  ==========================  ================= 
 

REGISTERED OFFICE

6th Floor, Cardinal Place, 100 Victoria Street, London SW1E 5JL, United Kingdom.

NOTES TO EDITORS

KAZ Minerals PLC ("KAZ Minerals" or "the Group") is a high growth copper company focused on large scale, low cost, open pit mining in Kazakhstan. It operates the Bozshakol and Aktogay open pit copper mines in the Pavlodar and East regions of Kazakhstan, three underground mines and associated concentrators in the East Region of Kazakhstan and the Bozymchak copper-gold mine in Kyrgyzstan. In 2016, total copper cathode equivalent output was 140 kt with by-products of 75 kt of zinc in concentrate, 120 koz of gold bar equivalent and 3,103 koz of silver bar equivalent.

The Group's new operations at Bozshakol and Aktogay are delivering one of the highest growth rates in the industry and transforming KAZ Minerals into a company dominated by world class, open pit copper mines.

Bozshakol is a first quartile asset on the global cost curve and will have an annual ore processing capacity of 30 million tonnes when fully ramped up and a mine life of 40 years at a copper grade of 0.36%. The mine and processing facilities will produce an average of 100 kt of copper cathode equivalent and 120 koz of gold in concentrate per year over the first 10 years of operations.

Aktogay is a large scale, open pit mine similar to Bozshakol, with a mine life of more than 50 years and average copper grades of 0.37% (oxide) and 0.33% (sulphide). Aktogay commenced production of copper cathode from oxide ore in December 2015 and copper in concentrate production from sulphide ore commenced in February 2017. The sulphide concentrator will have an annual ore processing capacity of 25 million tonnes when fully ramped up. Aktogay is competitively positioned on the global cost curve and will produce an average of 90 kt of copper cathode equivalent from sulphide ore and 20 kt of copper cathode from oxide ore per year over the first 10 years of operations.

KAZ Minerals is listed on the London Stock Exchange, the Kazakhstan Stock Exchange and the Hong Kong Stock Exchange and employs around 13,000 people, principally in Kazakhstan.

This announcement contains inside information.

GROUP PRODUCTION SUMMARY

 
                                          6m       6m       Q2        Q1       Q2 
                                        2017     2016     2017      2017     2016 
 ==================================  =======  =======  =======  ========  ======= 
 Ore extraction                  kt   34,421   22,099   17,537    16,884   11,494 
============================  =====  =======  =======  =======  ========  ======= 
 Ore processed                   kt   18,229    4,748   10,529     7,700    3,230 
============================  =====  =======  =======  =======  ========  ======= 
 Average copper 
  grade processed                 %     0.76     1.28     0.73      0.80     1.09 
============================  =====  =======  =======  =======  ========  ======= 
 
 Ore to leach pads               kt    8,297    8,679    4,084     4,213    4,319 
============================  =====  =======  =======  =======  ========  ======= 
 
 Copper production(1)            kt    118.0     56.3     65.9      52.1     33.6 
============================  =====  =======  =======  =======  ========  ======= 
    Bozshakol                    kt     52.0     10.1     29.1      22.9      9.1 
============================  =====  =======  =======  =======  ========  ======= 
    Aktogay sulphide             kt     22.6        -     15.4       7.2        - 
============================  =====  =======  =======  =======  ========  ======= 
    Aktogay oxide                kt     10.4      5.4      5.7       4.7      3.9 
============================  =====  =======  =======  =======  ========  ======= 
    East Region & Bozymchak      kt     33.0     40.8     15.7      17.3     20.6 
============================  =====  =======  =======  =======  ========  ======= 
 
 Zinc in concentrate             kt     32.3     39.6     16.8      15.5     19.7 
============================  =====  =======  =======  =======  ========  ======= 
 Gold production(2)             koz     93.0     45.1     50.4   42.6(3)     27.4 
============================  =====  =======  =======  =======  ========  ======= 
 Silver production(2)           koz    1,756    1,560      961    795(3)      854 
============================  =====  =======  =======  =======  ========  ======= 
 

(1) Payable metal in concentrate and copper cathode from Aktogay oxide ore.

(2) Payable metal in concentrate.

(3) Restated to include silver and gold production from Aktogay.

Copper production in H1 2017 increased by 110% to 118.0 kt from 56.3 kt in H1 2016, as Bozshakol and Aktogay raised ore throughput levels. Aktogay output benefited from the processing of higher grade sulphide material from a supergene enriched level at the top of the ore body. Copper production in Q2 2017 of 65.9 kt was 26% higher than Q1 2017 as both the new open pit mines raised output.

Ore extraction increased by 56% in H1 2017 compared to the prior year period, to 34.4 million tonnes (H1 2016: 22.1 million tonnes), in line with increased processing at Bozshakol and Aktogay.

Ore processed increased by 3.8 times in H1 2017 compared to the prior year period and processing volumes in Q2 2017 were 37% higher than the previous quarter due to rising throughput at the Bozshakol and the Aktogay sulphide concentrators, with Aktogay operating for its first full quarter. 34.4 million tonnes of ore were extracted in H1 2017, with 8.3 million tonnes of oxide ore placed on leach pads at Aktogay, 9.0 million tonnes of clay ore stockpiled at Bozshakol and the remainder processed through the Group's sulphide concentrators.

The average copper grade processed of 0.76% in H1 2017 compares to a grade of 1.28% in H1 2016, when the majority of the Group's production came from the higher grade underground mines in the East Region. The grade of ore processed decreased from 0.80% in Q1 2017 to 0.73% in Q2 2017 as the proportion of ore processed at Bozshakol increased, with a grade of 0.56%.

Zinc in concentrate output of 32.3 kt in H1 2017 was 18% below the prior year period following the closure of the Yubileyno-Snegirikhinsky mine at the end of 2016 and the six day week adopted at Orlovsky from H2 2016. Zinc in concentrate output of 16.8 kt in Q2 2017 increased by 8% compared to the prior quarter as zinc grades recovered from temporarily lower levels at Artemyevsky.

Gold production in H1 2017 increased to 93.0 koz, double the prior year period due to the ramp up of Bozshakol. Higher output from Bozshakol also drove an 18% increase in Q2 production to 50.4 koz, compared to 42.6 koz in Q1 2017. The material extracted in H1 2017 at Bozshakol had a higher than anticipated gold grade which is expected to decline from July 2017.

Silver production increased to 1,756 koz in H1 2017 from 1,560 in H1 2016, mainly due to the ramp up of Bozshakol. In Q2 2017, silver output grew to 961 koz from 795 koz in Q1 2017 as grades increased in the East Region and due to a higher contribution from Bozshakol.

BOZSHAKOL

 
                                       6m       6m      Q2      Q1      Q2 
                                     2017     2016    2017    2017    2016 
 ===============================  =======  =======  ======  ======  ====== 
 Ore extraction               kt   19,426   11,016   9,522   9,904   6,007 
=========================  =====  =======  =======  ======  ======  ====== 
    Sulphide                  kt    9,033    4,569   4,778   4,255   3,015 
=========================  =====  =======  =======  ======  ======  ====== 
    Clay                      kt   10,393    6,447   4,744   5,649   2,992 
=========================  =====  =======  =======  ======  ======  ====== 
 
 Ore processed                kt   11,690    2,290   6,630   5,060   1,989 
=========================  =====  =======  =======  ======  ======  ====== 
 
 Copper 
================================  =======  =======  ======  ======  ====== 
 Average copper 
  grade processed              %     0.56     0.56    0.56    0.57    0.57 
=========================  =====  =======  =======  ======  ======  ====== 
 Copper in ore processed      kt     65.6     12.8    37.0    28.6    11.3 
=========================  =====  =======  =======  ======  ======  ====== 
 Copper recovery 
  rate                         %     83.0     82.4    82.4    83.7    83.9 
=========================  =====  =======  =======  ======  ======  ====== 
 Copper in concentrate        kt     54.4     10.6    30.4    24.0     9.5 
=========================  =====  =======  =======  ======  ======  ====== 
 Copper production(1)         kt     52.0     10.1    29.1    22.9     9.1 
=========================  =====  =======  =======  ======  ======  ====== 
 
 Gold 
================================  =======  =======  ======  ======  ====== 
 Average gold grade 
  processed                  g/t     0.31     0.29    0.29    0.33    0.29 
=========================  =====  =======  =======  ======  ======  ====== 
 Gold recovery rate            %     58.5     60.4    59.3    57.6    62.5 
=========================  =====  =======  =======  ======  ======  ====== 
 Gold in concentrate         koz     67.2     13.0    36.7    30.5    11.7 
=========================  =====  =======  =======  ======  ======  ====== 
 Gold production(1)          koz     62.9     12.3    34.4    28.5    11.1 
=========================  =====  =======  =======  ======  ======  ====== 
 
 Silver production(1)        koz      361       58     200     161      51 
=========================  =====  =======  =======  ======  ======  ====== 
 

(1) Payable metal in concentrate.

Ore extraction at Bozshakol of 19.4 million tonnes was 76% higher in H1 2017 than the prior year period when the sulphide concentrator was in the early stages of commissioning. Ore extraction in Q2 2017 reduced by 4% compared to the previous quarter, to 9.5 million tonnes (Q1 2017: 9.9 million tonnes), as 0.9 million tonnes less clay bearing material was mined. Sulphide mining volumes in Q2 2017 continued to increase to support the ramp up of the main concentrator.

Ore processing volumes in H1 2017 of 11.7 million tonnes were significantly above the prior year period when the sulphide plant was in the early stages of commissioning and the clay plant was not yet in operation. In Q2 2017, ore processing volumes increased by 31% compared to the previous quarter, to 6.6 million tonnes, as the main sulphide concentrator increased throughput levels to 93% of design capacity from 74% in Q1 2017, partly assisted by less downtime for scheduled maintenance. The clay plant increased ore throughput to 69% of capacity in Q2 2017 compared to 40% in Q1 2017. The ramp up of both concentrators is proceeding in line with expectations and Bozshakol remains on track to achieve full design capacity in the second half of 2017.

In line with the increase in processing volumes, copper production(1) in H1 of 52.0 kt was more than five times higher than the prior year period, with the copper grade remaining constant at 0.56% and recovery rates increasing slightly to 83.0% (H1 2016: 82.4%). In Q2 2017, copper production(1) increased by 27% to 29.1 kt from 22.9 kt in the prior quarter, driven by increased throughput at both processing plants. Copper recovery rates in Q2 2017 decreased slightly to 82.4% from 83.7% in the previous quarter, mainly due to the increased contribution from the clay plant which is at an earlier stage of ramp up compared to the main sulphide concentrator. The clay plant processed 862 kt of ore in Q2 2017 with a recovery rate of 78.8%, compared to 495 kt processed in Q1 2017 at a recovery rate of 75.5%.

Consistent with copper, gold production also increased significantly compared to the prior year period with output of 62.9 koz in H1 2017. In Q2 2017, gold production increased to 34.4 koz from 28.5 koz in Q1 2017 following the higher volume of ore processed. The grade of gold in ore processed remained elevated at 0.29 g/t in Q2 2017, although this was lower than the 0.33 g/t grade processed in the prior quarter.

Silver production in H1 2017 increased compared to the prior year period and was 200 koz in Q2 2017, up from 161 koz in Q1 2017, reflecting the ramp up in processing volumes and improving silver recovery rates.

During H1 2017, 7.5 kt of copper in concentrate was sent for toll processing at the Balkhash smelter in Kazakhstan, where additional capacity on attractive terms was available for Bozshakol concentrate.

Following first half copper production of 52.0 kt, Bozshakol is on track to achieve 2017 guidance of 95-110 kt. Gold production of 62.9 koz in the first six months has been assisted by the extraction of higher gold content material. The gold content of material extracted fell somewhat in Q2 2017 and continued to reduce in July 2017. However, it is now expected that Bozshakol gold output will be towards the upper end of the full year guidance range of 85-110 koz.

AKTOGAY

 
                                      6m      6m      Q2      Q1      Q2 
                                    2017    2016    2017    2017    2016 
 ==============================  =======  ======  ======  ======  ====== 
 Ore extraction              kt   13,022   8,679   7,003   6,019   4,319 
=========================  ====  =======  ======  ======  ======  ====== 
    Oxide                    kt    8,297   8,679   4,084   4,213   4,319 
=========================  ====  =======  ======  ======  ======  ====== 
    Sulphide                 kt    4,725       -   2,919   1,806       - 
=========================  ====  =======  ======  ======  ======  ====== 
 
 Oxide 
===============================  =======  ======  ======  ======  ====== 
 Oxide ore to leach 
  pads                       kt    8,297   8,679   4,084   4,213   4,319 
=========================  ====  =======  ======  ======  ======  ====== 
 Grade                        %     0.42    0.41    0.39    0.44    0.44 
=========================  ====  =======  ======  ======  ======  ====== 
 Copper cathode              kt     10.4     5.4     5.7     4.7     3.9 
=========================  ====  =======  ======  ======  ======  ====== 
 
 Sulphide 
===============================  =======  ======  ======  ======  ====== 
 Sulphide ore processed      kt    4,574       -   2,937   1,637       - 
=========================  ====  =======  ======  ======  ======  ====== 
 Average grade processed      %     0.75       -    0.72    0.80       - 
=========================  ====  =======  ======  ======  ======  ====== 
 Recovery rate                %     69.3       -    76.5    57.7       - 
=========================  ====  =======  ======  ======  ======  ====== 
 Copper in concentrate       kt     23.7       -    16.2     7.5       - 
=========================  ====  =======  ======  ======  ======  ====== 
 Copper production(1)        kt     22.6       -    15.4     7.2       - 
=========================  ====  =======  ======  ======  ======  ====== 
 
 Total copper production     kt     33.0     5.4    21.1    11.9     3.9 
=========================  ====  =======  ======  ======  ======  ====== 
 

(1) Payable metal in concentrate.

The results for H1 2017 include output from the Aktogay sulphide plant which recorded its initial production in February 2017 and the cathodes from the oxide plant. Together the assets contributed copper production of 33.0 kt in H1 2017.

With cathode production from oxide at Aktogay now fully ramped up, the mining of oxide ore was stable at 8.3 million tonnes in H1 2017, representing a small decrease of 4% compared to H1 2016. Copper cathode output increased to 10.4 kt, compared to 5.4 kt in H1 2016 when the SX/EW facility was in the early stages of ramp up. Q2 2017 cathode production increased to 5.7 kt from 4.7 kt in the previous quarter, as the seasonal effect of higher temperatures resulted in improved output. Copper cathode production from oxide ore remains on track to achieve guidance of around 20 kt in 2017.

The sulphide concentrator completed its first full quarter of operations in Q2 2017 after commencing production midway through Q1 2017, achieving an ore throughput level of 47% of design capacity, ahead of the 32% of ore throughput achieved by Bozshakol in Q2 2016. The commissioning of the Aktogay sulphide concentrator led to mined volumes increasing by 62% to 2.9 million tonnes in Q2 2017 compared to 1.8 million tonnes in the previous quarter and processing increasing by 79% to 2.9 million tonnes.

The average copper grade of sulphide ore processed at Aktogay continued at an elevated level of 0.72% in Q2 2017, above expectations, due to the mining of a layer of supergene enriched ore. As mining operations continue over the remainder of the year the proportion of supergene enriched ore processed of overall volumes is expected to reduce and the average grade will therefore decline from the current level.

In H1 2017, 5.4 kt of copper in concentrate was dispatched for toll processing at the Balkhash smelter in Kazakhstan, with the remaining concentrate output exported to China based smelters.

Assisted by high grades and a full quarter of operations, copper production from sulphide ore increased to 15.4 kt in Q2 2017 compared to 7.2 kt from six weeks of operations in the prior quarter. With 33 kt of copper production delivered in the first half and further progress in throughput ramp up in the second half expected to offset lower grades, Aktogay is now well placed to achieve the 2017 guidance of 65-85 kt, consisting of around 20 kt from oxide ore and 45-65 kt from sulphide ore.

EAST REGION & BOZYMCHAK

Copper

 
                                              6m      6m      Q2      Q1      Q2 
                                            2017    2016    2017    2017    2016 
 ======================================  =======  ======  ======  ======  ====== 
 Ore extraction                      kt    1,973   2,404   1,012     961   1,168 
==============================  =======  =======  ======  ======  ======  ====== 
 
 Ore processed                       kt    1,965   2,458     962   1,003   1,241 
==============================  =======  =======  ======  ======  ======  ====== 
    Orlovsky concentrator            kt      546     682     270     276     339 
==============================  =======  =======  ======  ======  ======  ====== 
                                  grade 
                                    (%)     3.72    3.50    3.57    3.87    3.51 
 ======================================  =======  ======  ======  ======  ====== 
    Nikolayevsky concentrator        kt      594     908     275     319     474 
==============================  =======  =======  ======  ======  ======  ====== 
                                  grade 
                                    (%)     1.50    1.57    1.47    1.52    1.54 
 ======================================  =======  ======  ======  ======  ====== 
    Belousovsky concentrator         kt      317     336     162     155     163 
==============================  =======  =======  ======  ======  ======  ====== 
                                  grade 
                                    (%)     1.56    1.53    1.62    1.50    1.50 
 ======================================  =======  ======  ======  ======  ====== 
    Bozymchak concentrator           kt      508     532     255     253     265 
==============================  =======  =======  ======  ======  ======  ====== 
                                  grade 
                                    (%)     0.90    0.86    0.89    0.90    0.87 
 ======================================  =======  ======  ======  ======  ====== 
 Average grade processed              %     1.97    1.95    1.93    2.01    1.93 
==============================  =======  =======  ======  ======  ======  ====== 
 Average recovery 
  rate                                %     90.2    89.3    89.2    91.0    89.3 
==============================  =======  =======  ======  ======  ======  ====== 
 
 Copper in concentrate               kt     34.9    42.7    16.6    18.3    21.4 
==============================  =======  =======  ======  ======  ======  ====== 
    Orlovsky concentrator            kt     18.5    21.4     8.7     9.8    10.7 
==============================  =======  =======  ======  ======  ======  ====== 
    Nikolayevsky concentrator        kt      8.0    12.7     3.6     4.4     6.5 
==============================  =======  =======  ======  ======  ======  ====== 
    Belousovsky concentrator         kt      4.4     4.4     2.3     2.1     2.1 
==============================  =======  =======  ======  ======  ======  ====== 
    Bozymchak concentrator           kt      4.0     4.2     2.0     2.0     2.1 
==============================  =======  =======  ======  ======  ======  ====== 
 
 Copper production(1)                kt     33.0    40.8    15.7    17.3    20.6 
==============================  =======  =======  ======  ======  ======  ====== 
 

(1) Payable metal in concentrate.

Copper production in the East Region and Bozymchak reduced by 19% to 33.0 kt in H1 2017, compared to 40.8 kt in H1 2016, due to the closure of the Yubileyno-Snegirikhinsky mine at the end of 2016 and the adoption of a six day week at Orlovsky from H2 2016 to allow for ventilation maintenance. Bozymchak operated at design capacity throughout the first half of 2017.

Copper production decreased by 9% in Q2 2017 compared to the previous quarter, to 15.7 kt (Q1 2017: 17.3 kt) as a result of lower output from the Orlovsky and Nikolayevsky concentrators. The copper grade of ore processed at Orlovsky was temporarily elevated in Q1 2017 at 3.87% and was 3.57% in Q2, while the processing feed grade also reduced at Nikolayevsky. Production in Q1 2017 at Nikolayevsky was supported by the processing of 80 kt of ore (1.1 kt copper production) from the closed Yubileyno-Snegirikhinsky mine, with minimal volumes processed in Q2 2017.

By-products

 
                                       6m      6m      Q2      Q1      Q2 
 Zinc                                2017    2016    2017    2017    2016 
================================  =======  ======  ======  ======  ====== 
 Zinc bearing ore 
  processed                   kt    1,457   1,926     707     750     976 
=========================  =====  =======  ======  ======  ======  ====== 
 Average grade processed       %     3.07    2.89    3.27    2.89    2.82 
=========================  =====  =======  ======  ======  ======  ====== 
 
 Average recovery 
  rate                         %     72.2    71.0    72.7    71.8    71.6 
=========================  =====  =======  ======  ======  ======  ====== 
 Zinc in concentrate          kt     32.3    39.6    16.8    15.5    19.7 
=========================  =====  =======  ======  ======  ======  ====== 
 
 Gold 
================================  =======  ======  ======  ======  ====== 
 Gold bearing ore 
  processed                   kt    1,965   2,458     962   1,003   1,241 
=========================  =====  =======  ======  ======  ======  ====== 
 Average grade processed     g/t     0.82    0.81    0.87    0.78    0.81 
=========================  =====  =======  ======  ======  ======  ====== 
 Average recovery 
  rate                         %     60.8    54.5    62.3    59.2    53.6 
=========================  =====  =======  ======  ======  ======  ====== 
 Gold in concentrate         koz     31.6    34.8    16.7    14.9    17.3 
=========================  =====  =======  ======  ======  ======  ====== 
 Gold production(1)          koz     29.7    32.8    15.7    14.0    16.3 
=========================  =====  =======  ======  ======  ======  ====== 
 
 Silver 
================================  =======  ======  ======  ======  ====== 
 Silver bearing 
  ore processed               kt    1,965   2,458     962   1,003   1,241 
=========================  =====  =======  ======  ======  ======  ====== 
 Average grade processed     g/t     35.9    37.3    40.3    31.6    38.2 
=========================  =====  =======  ======  ======  ======  ====== 
 Average recovery 
  rate                         %     62.2    55.0    60.5    64.2    56.1 
=========================  =====  =======  ======  ======  ======  ====== 
 Silver in concentrate       koz    1,409   1,622     754     655     854 
=========================  =====  =======  ======  ======  ======  ====== 
 Silver production(1)        koz    1,282   1,502     686     596     803 
=========================  =====  =======  ======  ======  ======  ====== 
 

(1) Payable metal in concentrate.

In line with expectations, by-product output in the East Region and Bozymchak was lower in H1 2017 compared to the prior year period due to the closure of the Yubileyno-Snegirikhinsky mine at the end of 2016 and the introduction of the six day week at Orlovsky from H2 2016.

Zinc in concentrate output reduced by 18% to 32.3 koz in H1 2017 (H1 2016: 39.6 koz), with the reduction in ore processing volumes only partially offset by higher grades and recovery rates. In Q2 2017, zinc in concentrate output increased by 8% to 16.8 kt (Q1 2017: 15.5 kt) with grades recovering following the mining of low grade sections at the Artemyevsky mine at the start of the year.

H1 2017 gold output decreased to 29.7 koz, a 9% reduction compared to H1 2016 due to lower ore processing volumes. Gold output was less impacted than zinc and silver by the reduction of processing volumes in the East Region as the majority of production is supplied by Bozymchak, where production reduced by only 5% to 20.9 koz (H1 2016: 22.0 koz). Ore volumes at Bozymchak were 4.5% lower in H1 2017 compared to H1 2016 and the gold grade of ore processed reduced slightly from 1.69 to 1.66 g/t, in line with the mine plan.

Silver production in H1 2017 of 1,282 koz represents a reduction of 15% compared to H1 2016 due to lower ore processing volumes in the East Region. Q2 2017 output grew to 686 koz from 596 koz in Q1 2017 as silver processing grades increased to 40.3 g/t from 31.6 g/t.

Strong gold and silver output in the year to date should result in output from the East Region and Bozymchak being towards the upper end of the 50-60 koz gold and 2,250-2,500 koz silver ranges for 2017. Achieving full year zinc in concentrate production of 70-75 kt is dependent on the confirmation of higher zinc grades in the second half of the year.

APPIX - GROUP PRODUCTION SUMMARY

Copper mining & processing

 
                                       6m       6m        Q2       Q1       Q2 
                                     2017     2016      2017     2017     2016 
 ==============================  ========  =======  ========  =======  ======= 
 Ore extraction              kt    34,421   22,099    17,537   16,884   11,494 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozshakol                kt    19,426   11,016     9,522    9,904    6,007 
=========================  ====  ========  =======  ========  =======  ======= 
    Aktogay                  kt    13,022    8,679     7,003    6,019    4,319 
=========================  ====  ========  =======  ========  =======  ======= 
    East Region              kt     1,503    1,904       777      726      952 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozymchak                kt       470      500       235      235      216 
=========================  ====  ========  =======  ========  =======  ======= 
 Average grade mined          %      0.64     0.65      0.61     0.66     0.66 
=========================  ====  ========  =======  ========  =======  ======= 
 Copper in ore mined         kt     218.7    144.6     107.7    111.0     75.9 
=========================  ====  ========  =======  ========  =======  ======= 
 
 Ore processed               kt    18,229    4,748    10,529    7,700    3,230 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozshakol                kt    11,690    2,290     6,630    5,060    1,989 
=========================  ====  ========  =======  ========  =======  ======= 
    Aktogay (sulphide)       kt     4,574        -     2,937    1,637        - 
=========================  ====  ========  =======  ========  =======  ======= 
    East Region              kt     1,457    1,926       707      750      976 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozymchak                kt       508      532       255      253      265 
=========================  ====  ========  =======  ========  =======  ======= 
 Average grade processed      %      0.76     1.28      0.73     0.80     1.09 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozshakol                 %      0.56     0.56      0.56     0.57     0.57 
=========================  ====  ========  =======  ========  =======  ======= 
    Aktogay (sulphide)        %      0.75        -      0.72     0.80        - 
=========================  ====  ========  =======  ========  =======  ======= 
    East Region               %      2.34     2.24      2.31     2.38     2.22 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozymchak                 %      0.90     0.86      0.89     0.90     0.87 
=========================  ====  ========  =======  ========  =======  ======= 
 Copper in ore processed     kt     138.5     60.7      76.7     61.8     35.3 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozshakol                kt      65.6     12.8      37.0     28.6     11.3 
=========================  ====  ========  =======  ========  =======  ======= 
    Aktogay (sulphide)       kt      34.2        -      21.2     13.0        - 
=========================  ====  ========  =======  ========  =======  ======= 
    East Region              kt      34.2     43.3      16.3     17.9     21.7 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozymchak                kt       4.5      4.6       2.2      2.3      2.3 
=========================  ====  ========  =======  ========  =======  ======= 
 Average recovery 
  rate                        %      81.6     87.8      82.4     80.6     87.6 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozshakol                 %      83.0     82.4      82.4     83.7     83.9 
=========================  ====  ========  =======  ========  =======  ======= 
    Aktogay (sulphide)        %      69.3        -      76.5     57.7        - 
=========================  ====  ========  =======  ========  =======  ======= 
    East Region               %      90.3     89.1      89.3     91.2     89.2 
=========================  ====  ========  =======  ========  =======  ======= 
    Bozymchak                 %      89.1     91.0      88.6     89.6     90.4 
=========================  ====  ========  =======  ========  =======  ======= 
 
 Aktogay oxide ore 
  to leach pads              kt     8,297    8,679     4,084    4,213    4,319 
=========================  ====  ========  =======  ========  =======  ======= 
 Grade                        %      0.42     0.41      0.39     0.44     0.44 
=========================  ====  ========  =======  ========  =======  ======= 
 

Copper production

 
                                        6m      6m       Q2      Q1      Q2 
 Bozshakol                            2017    2016     2017    2017    2016 
=================================  =======  ======  =======  ======  ====== 
    Copper concentrate         kt    243.7    45.2    136.5   107.2    38.6 
==========================  =====  =======  ======  =======  ======  ====== 
    Copper in concentrate      kt     54.4    10.6     30.4    24.0     9.5 
==========================  =====  =======  ======  =======  ======  ====== 
 Aktogay sulphide 
=================================  =======  ======  =======  ======  ====== 
    Copper concentrate         kt     94.5       -     67.0    27.5       - 
==========================  =====  =======  ======  =======  ======  ====== 
    Copper in concentrate      kt     23.7       -     16.2     7.5       - 
==========================  =====  =======  ======  =======  ======  ====== 
 East Region 
=================================  =======  ======  =======  ======  ====== 
    Copper concentrate         kt    149.4   195.6     69.0    80.4    93.2 
==========================  =====  =======  ======  =======  ======  ====== 
    Copper in concentrate      kt     30.9    38.5     14.6    16.3    19.3 
==========================  =====  =======  ======  =======  ======  ====== 
 Bozymchak 
=================================  =======  ======  =======  ======  ====== 
    Copper concentrate         kt     17.0    16.7      8.4     8.6     8.5 
==========================  =====  =======  ======  =======  ======  ====== 
    Copper in concentrate      kt      4.0     4.2      2.0     2.0     2.1 
==========================  =====  =======  ======  =======  ======  ====== 
 
 Total copper concentrate      kt    504.6   257.5    280.9   223.7   140.3 
==========================  =====  =======  ======  =======  ======  ====== 
 Total copper in 
  concentrate                  kt    113.0    53.3     63.2    49.8    30.9 
==========================  =====  =======  ======  =======  ======  ====== 
 
 Copper production(1)          kt    118.0    56.3     65.9    52.1    33.6 
==========================  =====  =======  ======  =======  ======  ====== 
    Bozshakol                  kt     52.0    10.1     29.1    22.9     9.1 
==========================  =====  =======  ======  =======  ======  ====== 
    Aktogay sulphide           kt     22.6       -     15.4     7.2       - 
==========================  =====  =======  ======  =======  ======  ====== 
    Aktogay oxide              kt     10.4     5.4      5.7     4.7     3.9 
==========================  =====  =======  ======  =======  ======  ====== 
    East Region                kt     29.2    36.8     13.8    15.4    18.6 
==========================  =====  =======  ======  =======  ======  ====== 
    Bozymchak                  kt      3.8     4.0      1.9     1.9     2.0 
==========================  =====  =======  ======  =======  ======  ====== 
 
 Copper cathodes               kt     54.4    43.9     28.8    25.6    23.6 
==========================  =====  =======  ======  =======  ======  ====== 
    Bozshakol (toll 
     processed)                kt      4.6       -      3.7     0.9       - 
==========================  =====  =======  ======  =======  ======  ====== 
    Aktogay sulphide 
     (toll processed)          kt      4.1       -      3.6     0.5       - 
===========================  ====  =======  ======  =======  ======  ====== 
    Aktogay oxide              kt     10.4     5.4      5.7     4.7     3.9 
==========================  =====  =======  ======  =======  ======  ====== 
    East Region (toll 
     processed)                kt     31.2    35.6     14.0    17.2    17.5 
==========================  =====  =======  ======  =======  ======  ====== 
    Bozymchak (toll 
     processed)                kt      4.1     2.9      1.8     2.3     2.2 
==========================  =====  =======  ======  =======  ======  ====== 
 
 

(1) Payable metal in concentrate and copper cathode from Aktogay oxide ore.

Zinc

 
                                              6m      6m      Q2      Q1      Q2 
                                            2017    2016    2017    2017    2016 
 ======================================  =======  ======  ======  ======  ====== 
 Zinc bearing ore 
  mined                              kt    1,503   1,904     777     726     952 
==============================  =======  =======  ======  ======  ======  ====== 
    Orlovsky                         kt      545     679     270     275     337 
==============================  =======  =======  ======  ======  ======  ====== 
    Artemyevsky                      kt      645     646     351     294     327 
==============================  =======  =======  ======  ======  ======  ====== 
    Irtyshsky                        kt      313     316     156     157     157 
==============================  =======  =======  ======  ======  ======  ====== 
    Yubileyno-Snegirikhinsky         kt        -     263       -       -     131 
==============================  =======  =======  ======  ======  ======  ====== 
 Zinc bearing ore 
  processed                          kt    1,457   1,926     707     750     976 
==============================  =======  =======  ======  ======  ======  ====== 
 
    Orlovsky concentrator            kt      546     682     270     276     339 
==============================  =======  =======  ======  ======  ======  ====== 
                                  grade 
                                    (%)     3.88    4.46    3.76    3.99    4.13 
 ======================================  =======  ======  ======  ======  ====== 
    Nikolayevsky concentrator        kt      594     908     275     319     474 
==============================  =======  =======  ======  ======  ======  ====== 
                                  grade 
                                    (%)     2.11    1.72    2.48    1.78    1.89 
 ======================================  =======  ======  ======  ======  ====== 
    Belousovsky concentrator         kt      317     336     162     155     163 
==============================  =======  =======  ======  ======  ======  ====== 
                                  grade 
                                    (%)     3.50    2.89    3.80    3.20    2.81 
 ======================================  =======  ======  ======  ======  ====== 
 Average grade 
  processed                           %     3.07    2.89    3.27    2.89    2.82 
==============================  =======  =======  ======  ======  ======  ====== 
 
 Zinc metal in 
  ore processed                      kt     44.8    55.8    23.1    21.7    27.5 
==============================  =======  =======  ======  ======  ======  ====== 
    Orlovsky concentrator            kt     21.1    30.5    10.1    11.0    14.0 
==============================  =======  =======  ======  ======  ======  ====== 
    Nikolayevsky concentrator        kt     12.5    15.6     6.8     5.7     8.9 
==============================  =======  =======  ======  ======  ======  ====== 
    Belousovsky concentrator         kt     11.2     9.7     6.2     5.0     4.6 
==============================  =======  =======  ======  ======  ======  ====== 
 Average recovery 
  rate                                %     72.2    71.0    72.7    71.8    71.6 
==============================  =======  =======  ======  ======  ======  ====== 
    Orlovsky concentrator             %     70.9    72.7    69.0    72.6    73.2 
==============================  =======  =======  ======  ======  ======  ====== 
    Nikolayevsky concentrator         %     76.3    69.7    80.6    71.0    71.3 
==============================  =======  =======  ======  ======  ======  ====== 
    Belousovsky concentrator          %     70.2    68.0    69.9    70.6    67.1 
==============================  =======  =======  ======  ======  ======  ====== 
 
 Zinc in concentrate                 kt     32.3    39.6    16.8    15.5    19.7 
==============================  =======  =======  ======  ======  ======  ====== 
    Orlovsky concentrator            kt     15.0    22.1     7.0     8.0    10.2 
==============================  =======  =======  ======  ======  ======  ====== 
    Nikolayevsky concentrator        kt      9.5    10.9     5.5     4.0     6.4 
==============================  =======  =======  ======  ======  ======  ====== 
    Belousovsky concentrator         kt      7.8     6.6     4.3     3.5     3.1 
==============================  =======  =======  ======  ======  ======  ====== 
 

Gold

 
                                                   6m       6m        Q2       Q1      Q2 
                                                 2017     2016      2017     2017    2016 
===========================  ==============  ========  =======  ========  =======  ====== 
 Gold bearing ore 
  mined                                  kt    21,399   13,420    10,534   10,865   7,175 
===========================  ==============  ========  =======  ========  =======  ====== 
    Bozshakol                            kt    19,426   11,016     9,522    9,904   6,007 
===========================  ==============  ========  =======  ========  =======  ====== 
    East Region                          kt     1,503    1,904       777      726     952 
===========================  ==============  ========  =======  ========  =======  ====== 
    Bozymchak                            kt       470      500       235      235     216 
===========================  ==============  ========  =======  ========  =======  ====== 
 Gold bearing ore 
  processed                              kt    13,655    4,748     7,592    6,063   3,230 
===========================  ==============  ========  =======  ========  =======  ====== 
    Bozshakol                            kt    11,690    2,290     6,630    5,060   1,989 
===========================  ==============  ========  =======  ========  =======  ====== 
                                      grade 
                                      (g/t)      0.31     0.29      0.29     0.33    0.29 
 ==========================================  ========  =======  ========  =======  ====== 
    East Region                          kt     1,457    1,926       707      750     976 
===========================  ==============  ========  =======  ========  =======  ====== 
                                      grade 
                                      (g/t)      0.53     0.57      0.57     0.50    0.57 
===========================  ==============  ========  =======  ========  =======  ====== 
    Bozymchak                            kt       508      532       255      253     265 
===========================  ==============  ========  =======  ========  =======  ====== 
                                      grade 
                                      (g/t)      1.66     1.69      1.69     1.63    1.69 
===========================  ==============  ========  =======  ========  =======  ====== 
 
 Average grade processed                g/t      0.38     0.56      0.36     0.40    0.49 
===========================  ==============  ========  =======  ========  =======  ====== 
 
 
 Gold in ore processed                  koz     166.9     85.4      88.8     78.1    51.0 
===========================  ==============  ========  =======  ========  =======  ====== 
    Bozshakol                           koz     114.9     21.6      62.0     52.9    18.7 
===========================  ==============  ========  =======  ========  =======  ====== 
    East Region                         koz      24.9     35.0      12.9     12.0    17.9 
===========================  ==============  ========  =======  ========  =======  ====== 
    Bozymchak                           koz      27.1     28.8      13.9     13.2    14.4 
===========================  ==============  ========  =======  ========  =======  ====== 
 Average recovery 
  rate                                    %      59.2     56.0      60.2     58.2    56.9 
===========================  ==============  ========  =======  ========  =======  ====== 
    Bozshakol                             %      58.5     60.4      59.3     57.6    62.5 
===========================  ==============  ========  =======  ========  =======  ====== 
    East Region                           %      37.4     32.7      40.1     34.5    32.8 
===========================  ==============  ========  =======  ========  =======  ====== 
    Bozymchak                             %      82.3     81.1      83.1     81.5    79.7 
===========================  ==============  ========  =======  ========  =======  ====== 
 
 Gold in concentrate                    koz      98.8     47.8      53.4     45.4      29.0 
===========================  ==============  ========  =======  ========  =======  ======== 
    Bozshakol                           koz      67.2     13.0      36.7     30.5      11.7 
===========================  ==============  ========  =======  ========  =======  ======== 
    East Region                         koz       9.3     11.5       5.2      4.1       5.9 
===========================  ==============  ========  =======  ========  =======  ======== 
    Bozymchak                           koz      22.3     23.3      11.5     10.8      11.4 
===========================  ==============  ========  =======  ========  =======  ======== 
 
 
 Gold production(1)                     koz      93.0     45.1      50.4     42.6      27.4 
===========================  ==============  ========  =======  ========  =======  ======== 
    Bozshakol                           koz      62.9     12.3      34.4     28.5      11.1 
===========================  ==============  ========  =======  ========  =======  ======== 
    Aktogay (sulphide) 
     (2)                                koz       0.4        -       0.3      0.1         - 
===========================  ==============  ========  =======  ========  =======  ======== 
    East Region                         koz       8.8     10.8       4.9      3.9       5.5 
===========================  ==============  ========  =======  ========  =======  ======== 
    Bozymchak                           koz      20.9     22.0      10.8     10.1      10.8 
===========================  ==============  ========  =======  ========  =======  ======== 
 
 Gold bar produced 
  (toll processed)                      koz      28.6     25.3      13.6     15.0      17.3 
============================  =============  ========  =======  ========  =======  ======== 
    Bozshakol                           koz       3.6        -       3.6        -         - 
============================  =============  ========  =======  ========  =======  ======== 
    Aktogay (sulphide)(2)               koz         -        -         -        -         - 
===========================  ==============  ========  =======  ========  =======  ======== 
    East Region                         koz       7.0     12.1       2.4      4.6       5.3 
===========================  ==============  ========  =======  ========  =======  ======== 
    Bozymchak                           koz      18.0     13.2       7.6     10.4      12.0 
===========================  ==============  ========  =======  ========  =======  ======== 
 
 

(1) Payable metal in concentrate.

(2) Minimal volume recovered from Aktogay material.

Silver

 
                                                6m       6m        Q2       Q1      Q2 
                                              2017     2016      2017     2017    2016 
 ============                             ========  =======  ========  =======  ====== 
 Silver bearing 
  ore mined                           kt    21,399   13,420    10,534   10,865   7,175 
==========================  ============  ========  =======  ========  =======  ====== 
    Bozshakol                         kt    19,426   11,016     9,522    9,904   6,007 
==========================  ============  ========  =======  ========  =======  ====== 
    East Region                       kt     1,503    1,904       777      726     952 
==========================  ============  ========  =======  ========  =======  ====== 
    Bozymchak                         kt       470      500       235      235     216 
==========================  ============  ========  =======  ========  =======  ====== 
 Silver bearing 
  ore processed                       kt    13,655    4,748     7,592    6,063   3,230 
==========================  ============  ========  =======  ========  =======  ====== 
    Bozshakol                         kt    11,690    2,290     6,630    5,060   1,989 
==========================  ============  ========  =======  ========  =======  ====== 
                                   grade 
                                   (g/t)      1.58     1.75      1.51     1.68    1.72 
 ============                             ========  =======  ========  =======  ====== 
    East Region                       kt     1,457    1,926       707      750     976 
==========================  ============  ========  =======  ========  =======  ====== 
                                   grade 
                                   (g/t)      44.4     44.1      50.6     38.5    45.1 
 ============                             ========  =======  ========  =======  ====== 
    Bozymchak                         kt       508      532       255      253     265 
==========================  ============  ========  =======  ========  =======  ====== 
                                   grade 
                                   (g/t)      11.5     12.5      11.8     11.2    12.9 
 ============                             ========  =======  ========  =======  ====== 
 Average grade 
  processed                          g/t       6.5     20.1       6.4      6.6    15.7 
==========================  ============  ========  =======  ========  =======  ====== 
 
 Silver in ore 
  processed                          koz     2,862    3,076     1,569    1,293   1,633 
==========================  ============  ========  =======  ========  =======  ====== 
    Bozshakol                        koz       595      129       322      273     110 
==========================  ============  ========  =======  ========  =======  ====== 
    East Region                      koz     2,080    2,733     1,151      929   1,413 
==========================  ============  ========  =======  ========  =======  ====== 
    Bozymchak                        koz       187      214        96       91     110 
==========================  ============  ========  =======  ========  =======  ====== 
 Average recovery 
  rate                                 %      63.3     54.8      62.3     64.5    55.8 
==========================  ============  ========  =======  ========  =======  ====== 
    Bozshakol                          %      67.4     50.3      69.0     65.5    51.5 
==========================  ============  ========  =======  ========  =======  ====== 
    East Region                        %      60.9     53.4      59.3     63.0    54.5 
==========================  ============  ========  =======  ========  =======  ====== 
    Bozymchak                          %      75.7     76.2      75.0     76.4    76.7 
==========================  ============  ========  =======  ========  =======  ====== 
 Silver in concentrate               koz     1,811    1,687       977      834     911 
==========================  ============  ========  =======  ========  =======  ====== 
    Bozshakol                        koz       402       65       223      179      57 
==========================  ============  ========  =======  ========  =======  ====== 
    East Region                      koz     1,267    1,459       682      585     770 
==========================  ============  ========  =======  ========  =======  ====== 
    Bozymchak                        koz       142      163        72       70      84 
==========================  ============  ========  =======  ========  =======  ====== 
 
 Silver production(1)                koz     1,756    1,560       961      795     854 
==========================  ============  ========  =======  ========  =======  ====== 
    Bozshakol                        koz       361       58       200      161      51 
==========================  ============  ========  =======  ========  =======  ====== 
    Aktogay (sulphide)(2)            koz       113        -        75       38       - 
==========================  ============  ========  =======  ========  =======  ====== 
    East Region                      koz     1,153    1,351       621      532     724 
==========================  ============  ========  =======  ========  =======  ====== 
    Bozymchak                        koz       129      151        65       64      79 
==========================  ============  ========  =======  ========  =======  ====== 
 
 Silver bar produced 
  (toll processed)                   koz     1,370    1,355       585      785     636 
===========================  ===========  ========  =======  ========  =======  ====== 
 
    Bozshakol                        koz        19        -        13        6       - 
==========================  ============  ========  =======  ========  =======  ====== 
    Aktogay (sulphide)(2)            koz        19        -        19        -       - 
==========================  ============  ========  =======  ========  =======  ====== 
    East Region                      koz     1,200    1,268       485      715     558 
==========================  ============  ========  =======  ========  =======  ====== 
    Bozymchak                        koz       132       87        68       64      78 
==========================  ============  ========  =======  ========  =======  ====== 
 
 

(1) Payable metal in concentrate.

(2) Minimal volume recovered from Aktogay material.

This information is provided by RNS

The company news service from the London Stock Exchange

END

UPDSEMFMMFWSEEW

(END) Dow Jones Newswires

July 27, 2017 02:00 ET (06:00 GMT)

Kaz Minerals (LSE:KAZ)
Historical Stock Chart
From Mar 2024 to Apr 2024 Click Here for more Kaz Minerals Charts.
Kaz Minerals (LSE:KAZ)
Historical Stock Chart
From Apr 2023 to Apr 2024 Click Here for more Kaz Minerals Charts.