Fourth Quarter 2008 Production Results (Aquarius Platinum)

Date : 07/24/2008 @ 2:00AM
Source : UK Regulatory (RNS and others)
Stock : Aquarius Platinum (AQP)
Quote : 129.5  0.25 (0.19%) @ 11:35AM
<< BackQuote Chart

 



Fourth Quarter 2008 Production Results (Aquarius Platinum)

    Aquarius Platinum

Fourth Quarter 2008 Production Results

 

Highlights of the Quarter

* Record achieved average PGM basket price at all operations

* Quarterly attributable mine production falls marginally to 109,863 PGM ounces

* Annual group attributable PGM production in line with revised target at 500,203
  ounces

* Buyback completion of Implats stakes in Aquarius and AQPSA creates significant
  value

Commenting on the results, Stuart Murray, CEO of Aquarius Platinum said:
 "Production during the quarter was hampered by industrial relations issues at
our operations.  This situation necessitated significant intervention and
activism by AQPSA management, largely in respect of dealing with the
relationships between mining contractors and their employees.  As a consequence
AQPSA entered into contract renegotiations with the major mining contractor at
Kroondal and Marikana which saw AQPSA taking over key mining and finance
positions on the mines.  These changes to the company's contracting model in
South Africa, whilst disruptive to implement, are necessary, and I am confident
will bear fruit in the future.  Lifting volumes is paramount if margins are to
be maintained in light of significant cost pressures, as we all continue
grapple with significant escalation in prices for electricity, diesel, steel,
chemicals, labour and explosives.  Record prices during the quarter went
someway to offsetting the impact of higher costs, though not enough to lift
margins as in previous quarters."

P&SA1 at Kroondal

* PGM production of 83,062 PGM ounces, down 17% quarter on quarter (Aquarius
  attributable 41,531 PGM ounces)

* Cash margin for the quarter at 66%

* Revised bonus system implemented to overcome production issues due to
  industrial action

P&SA2 at Marikana

* PGM production increased by 17% quarter-on-quarter to 28,416 PGM ounces
  (Aquarius attributable: 14,208 PGM ounces)

* Cash margin for the quarter decreased to 28%

* Change in the open pit mining methodology resulted in a more than doubling of
  production, albeit with high stripping costs

Everest

* PGM production increased 1% quarter-on-quarter to 31,327 PGM ounces (Aquarius
  attributable: 31,327 PGM ounces)

* Cash margin for the quarter at 65%

* High labour turnover, go-slows and general unrest affected labour availability
  during transition to owner-operator

Mimosa

* PGM production increased by 12% quarter-on-quarter to 38,517 PGM ounces
  (Aquarius attributable: 19,258 PGM ounces)

* Cash margin for the quarter increased to 77%

* Wedza Phase V Project commissioned

* Premature break down of Primary Ball Mill 2 in the older Phase 3 milling
  circuit negatively impacted production

CTRP

* PGM production decreased by 11% quarter-on-quarter to 2,044 PGM ounces
  (Aquarius attributable: 1,022 PGM ounces)

* Gross cash margin for the quarter at 80%

Platinum Mile

* PGM production for the quarter was 5,035 PGM ounces (Aquarius attributable:
  2,517 PGM ounces)

* Gross cash margin for the quarter was 47%

Production by Mine

                                       Quarter Ended                   
PGMs (4E)                                                              
                        Sep 2007     Dec 2007     Mar 2008     Jun 2008  
                                                                       
Kroondal                 106,493      101,542      100,020       83,062
                                                                       
Marikana                  35,200       37,744       24,223       28,416
                                                                       
Everest                   48,841       46,719       31,107       31,327
                                                                       
Mimosa                    38,660       39,372       34,283       38,517
                                                                       
CTRP                       2,681        2,816        2,309        2,044
                                                                       
Platinum Mile                  -            -       2,006*        5,035
                                                                       
Total                    231,875      228,193      193,948      188,401
                                                                       

Production by Mine Attributable to Aquarius

                                       Quarter Ended                   
PGMs (4E)                                                              
                        Sep 2007     Dec 2007     Mar 2008     Jun 2008  
                                                                       
Kroondal                  53,246       50,771       50,010       41,531
                                                                       
Marikana                  17,600       18,872       12,111       14,208
                                                                       
Everest                   48,841       46,719       31,107       31,327
                                                                       
Mimosa                    19,330       19,686       17,142       19,258
                                                                       
CTRP                       1,340        1,408        1,154        1,022
                                                                       
Platinum Mile                  -            -       1,003*        2,517
                                                                       
Total                    140,357      137,456      112,527      109,863
                                                                       

*From 1 March 2008

Metals Prices and Foreign Exchange

PGM prices continued to strengthen in the fourth quarter, but were showing
weakness in June as turmoil in financial markets affected most metals prices. 
Platinum closed 8% higher at $2,064 per ounce; rhodium increased 9% to $9,725
per ounce; palladium increased 10% to $497 per ounce, while gold added 4%,
closing at $934 per ounce.

Platinum, rhodium and to a lesser extent palladium continued to benefit from
heightened supply concerns from South Africa, notably due to industrial
relations and power constraints.  On the demand side, jewellery has certainly
seen some reduction in demand, yet demand from platinum autocatalysts and ETFs
in particular during the quarter witnessed significant growth.  All of our
commodities continue to benefit from the weak US dollar and the flight to
precious metals as an alternative asset class in the face of recessionary
concerns.

Average PGM basket prices for the Group maintained record levels over the
quarter in both Rand and US Dollar terms, achieving a peak of $2,454 per ounce
during the quarter.

At our South African operations, the four element basket price peaked at
R19,565 per ounce, and the average achieved price was 20% higher than the
previous quarter at R17,929 per ounce, equal to $2,310 per ounce.

In Zimbabwe, the average achieved basket price for the quarter was 30% higher
at $1,607 per ounce.

This resulted in a record group basket price equivalent of $2,187 per PGM ounce
or R11,173 per PGM ounce, 10% higher than the previous quarter.

Average PGM basket prices achieved at Aquarius operations: US$ per PGM ounce
(4E)

                                  Basket Prices (Quarter Ended)       
                                                                      
                            Sep 2007   Dec 2007   Mar 2008   Jun 2008 
                                                                      
Kroondal                     1,518      1,657      2,129      2,350   
                                                                      
Marikana                     1,480      1,632      2,041      2,311   
                                                                      
Everest                      1,475      1,635      2,112      2,266   
                                                                      
Mimosa                       1,065      1,083      1,237      1,607   
                                                                      
CTRP                         1,775      1,967      2,505      2,850   
                                                                      
Platinum Mile                  -          -          -        1,989   
                                                                      
Aquarius Group Average       1,438      1,567      1,981      2,187   
                                                                      

The Rand Dollar exchange rate for the quarter averaged 7.76, 5% weaker than the
7.40 average recorded in the previous quarter.

AQUARIUS PLATINUM (SOUTH AFRICA) (PTY) LTD (Aquarius Platinum 67.5%)

P&SA 1 at Kroondal

Safety

The 12-month rolling average DIIR for the quarter deteriorated from 0.40 in the
previous quarter to 0.49.  Thirteen lost time injuries were reported during the
quarter.

Mining

Production tons decreased by 10% to 1,389,997 tons

Head grade decreased by 1.6% to 2.52g/t.

Processing

Tons processed decreased by 16% to 1,334,325 tons.

Recoveries remained unchanged at 77%.

PGM production decreased by 17% to 83,062 PGM ounces.


P&SA1 at Kroondal PGM Production & Rand Cash Costs per PGM Ounce

Revenue

The basket price for the quarter averaged $2,350 per PGM ounce, 10% higher than
the previous quarter and the Rand Dollar exchange rate averaged 7.76.   Revenue
at Kroondal decreased by 22% to R1,368 million for the quarter (Aquarius
attributable: R684 million) due to the lower production and negative sales
pipeline adjustments, caused by a strengthening of the Rand at the close of the
period compared to the close of the prior quarter.

Operations

Total production decreased by 10% to 1,389,997 tons.  Production from
underground operations decreased by 8% to 1,389,997 tons.

The Central West opencast was completed during the previous quarter. 
Production from the Klipfontein opencast is planned to be completed during the
first quarter of the new financial year.

Production was adversely affected by underground mining contractor Murray &
Roberts Cementation employees embarking on several bonus related go-slow
industrial action and work stoppages, whilst Redpath SA's employees at K5 shaft
also embarked on industrial action relating to pay issues.  A revised
bonus-system was developed in consultation with the unions to resolve these
issues.

Production was also negatively affected by having fewer production days due to
four public holidays during the quarter.  Absenteeism was high following these
public holidays. The consequence of the industrial action and absenteeism
resulted in a loss of around 375,000 tons or 24,000 PGM ounces (12,000
attributable) for the quarter.

During the quarter, the commercial arrangement between AQPSA and MRC was
changed substantially to enable AQPSA to assume more managerial responsibility,
effectively allowing MRC to continue providing skilled labour and supervision,
procurement and engineering maintenance services.  It is expected that this
revised structure will positively affect operations going forward.

Tons processed decreased by 16% to 1,334,325 tons, comprising 1,327,740 tons
from underground and 6,586 tons of opencast material.  Stockpiles at the end of
the quarter were 4,907 tons.

The head-grade decreased by 1.6% to 2.52g/t as a result of lower in-situ grade
mined

Recoveries remained unchanged at 77%.

PGM production decreased by 17% to 83,062 PGM ounces (41,531 attributable).

Primary development for the quarter was 2,500 metres.

Kroondal: Metal in concentrate produced (PGM ounces)

Quarter ended     Pt      Pd      Rh     Au    PGMs    Attributable 
                                                       to Aquarius  
                                                                    
Jun 2008        49,621  24,054   9,014  372   83,062      41,531    
                                                                    
Mar 2008        59,834  28,966  10,759  461  100,020      50,010    
                                                                    
Dec 2007        60,726  29,525  10,819  472  101,542      50,771    
                                                                    
Sep 2007        63,860  30,855  11,259  518  106,493      53,246    
                                                                    

Operating Cash Costs

Cash costs per ton increased by 35% to R354 and costs per PGM ounce increased
by 37% to R5,680.  The cost base is experiencing significant appreciation due
to the escalation of power, diesel, chemical, explosive and steel grinding
media prices.  Specific to Kroondal, lower production output due to go-slow
industrial action and work stoppages, absenteeism and lower achieved grade also
affected costs.  Consequently the cash margin fell to 66%.

Kroondal: Operating Cash Costs per Ounce

                4E                6E          6E net of by-products 
                                                                    
          (Pt+Pd+Rh+Au)  (Pt+Pd+Rh+Ir+Ru+Au)         (Ni&Cu)        
                                                                    
Kroondal     R 5,680           R 4,669               R 4,500        
                                                                    

Capital Expenditure

Capital expenditure for the quarter was R93 million, all ongoing capital. 
Major items included establishment of the second phase of the K5 Rail Project
and underground infrastructure extensions.

P&SA2 at Marikana

Safety

The 12-month rolling DIIR deteriorated from 0.45 to 0.54.  Six lost-time
injuries were reported during the quarter.

Mining

Production tons increased by 40% to 515,492 tons, consisting of 276,498 tons
from underground and 238,994 tons from open pit operations.

Head grade decreased by 3.6% to 2.68 g/t.

Processing

Tons processed increased by 23% to 524,674 tons.

Recoveries fell by 2% to 62.6%.

PGM production increased by 17% to 28,416 ounces (Aquarius attributable: 14,208
ounces)

Revenue

The basket price for the quarter averaged $2,311 per PGM ounce 13% higher than
the previous quarter, with an average Rand Dollar exchange rate of 7.76.
Revenue at Marikana decreased by 8% to R428 million for the quarter (Aquarius
attributable: R214 million).  Despite higher production and basket prices,
revenue was lower due to a negative sales pipeline adjustment, caused by a
strengthening of the Rand at the close of the period compared to the close of
the prior quarter.

Operations

Total production increased by 40% to 515,492 tons for the quarter comprising
276,498 tons underground material and 238,994 tons open pit material.

Production was adversely affected by underground mining contractor Murray &
Roberts Cementation employees embarking on several bonus related go-slow
industrial action and work stoppages, whilst Redpath SA's employees at K5 shaft
also embarked on industrial action relating to pay issues.  A revised
bonus-system was developed in consultation with the unions to resolve these
issues.  Production was also negatively affected by having fewer production
days due to four public holidays during the quarter.  Absenteeism was high
following these public holidays. 

During the quarter, the commercial arrangement between AQPSA and MRC was
changed substantially to enable AQPSA to assume more managerial responsibility,
effectively allowing MRC to continue providing skilled labour and supervision,
procurement and engineering maintenance services.  It is expected that this
revised structure will positively affect operations going forward.

Production from underground operations increased by 8.8% to 276,498 tons,
dominating the underground to open pit production mix.

Production from the open pit material increased by 114% to 238,994 tons.  The
change in mining methodology reported in the previous quarterly report, is
bearing fruit and the outlook is positive.  The stripping ratio for the quarter
had to be increased to 46% to get the pit in the correct shape.  The stripping
ratio for the 2009 Financial Year is planned at a much reduced level 28:1
compared to 46:1 for the last quarter of the 2008 Financial Year.

Stockpiles at the end of the quarter were 70,263 tons, a reduction of 38%.  The
low-recovery-oxidised stockpile was processed during the quarter, taking
advantage of the high metal prices.  Stockpiles at the end of the quarter were
significant as all the fresh open pit material that was mined towards the end
of the quarter could not be processed in the quarter.

A total of 524,674 tons were processed during the quarter: 273,486 tons from
underground; 251,188 tons of open pit material which includes 70,220 tons of
low-recovery-oxidised material.

The head-grade decreased by 3.6% to 2.68 g/t due to the processing of the
low-recovery-oxidised material and pothole intersections in the decline sinking
operations.  Certain areas in the open pit intersected reef with increased
internal waste, having a further effect.

Recoveries deteriorated slightly to 62.6% due to the lower head grade and
treatment of oxidised material which was processed during the quarter.  The
oxidised material equates to 13% of tons processed.

PGM production increased by 17% to 28,416 ounces (Aquarius attributable: 14,208
ounces)

Marikana: Metal in concentrate produced (PGM ounces)

Quarter ended       Pt      Pd     Rh    Au    PGMs    Attributable  
                                                        to Aquarius  
                                                                     
Jun 2008          17,843  7,649  2,769  155   28,416      14,208     
                                                                     
Mar 2008          15,114  6,601  2,351  158   24,223      12,111     
                                                                     
Dec 2007          23,985  9,925  3,586  249   37,744      18,872     
                                                                     
Sep 2007          21,844  9,742  3,367  246   35,290      17,600     
                                                                     
Operating Cash Costs

Cash costs per ton increased by 11% to R586, whilst costs per PGM ounce
increased by 16% to R10,817.  As explained at Kroondal, appreciation in input
costs is placing significant pressure on costs.  Particular to Marikana a
stripping ratio of 46:1 in the open pit, production interruptions and
processing the low-recovery-oxidised material also affected costs. 
Consequently, the cash margin was lower at 28% for the quarter.

Marikana: Operating Cash Costs per Ounce

                4E                6E           6E net of by-products 
                                                                     
          (Pt+Pd+Rh+Au)  (Pt+Pd+Rh+Ir+Ru+Au)          (Ni&Cu)        
                                                                     
Marikana     R 10,817          R 8,944                R 8,680        
                                                                     

Capital Expenditure

Capital expenditure totalled R34 million, including R0.1 million of expansion
capital (AQPSA share R0.05million).

Contractor dispute with Moolman Mining

AQPSA's application to stay the Arbitration proceedings instituted by Moolman
Mining in the "rise and rall" formula dispute, pending the outcome of the
action proceedings instituted by AQPSA against Moolman Mining to set aside the
mining contract by reason of Moolman Mining's misrepresentation, has been set
down for hearing during the first week of March 2009.

Should AQPSA succeed in the application, the main action will be heard before a
judge in the High Court at some time in the future after that date,
alternatively should the outcome of the application be that the main action
should be referred to arbitration, that arbitration would also take place at
some indeterminate time in the future.  Accordingly, the March 2009 application
is simply to determine whether the main misrepresentation action can be heard
by the High Court or whether it must be submitted to Arbitration.

Everest Platinum Mine

Safety

The 12-month rolling average DIIR deteriorated from 0.75 to 0.89.  Ten
lost-time injuries occurred during the quarter, of which two were regrettably
fatal accidents. 

Mr Shaba Lepheana was injured on 21 March 2008, while he was busy replacing a
water manifold on a temporary water pipe installation.  Mr Lepheana died in
hospital two months later.

Mr Daniel Moeng was fatally injured on 23 April 2008 by a FOG whilst drilling a
face.

Investigationsand enquiries into both fatalities were concluded by the DME.  No
official reports have been received to date.

Mining

Production increased by 7% to 414,240 tons; consisting of 407,133 tons from
underground and 7,107 tons from opencast operations

Underground production increased by 23%

The head grade deteriorated by 2.6% to 2.91 g/t

Processing

Plant processed 418,934 tons, 2.3% less than the previous quarter

Recoveries improved from 75% to 80%, an improvement of 6.7%

PGM production increased marginally by 0.1% to 31,327 PGM ounces

Revenue

The basket price for the quarter averaged $2,266 per PGM ounce, 7% higher than
the previous quarter, with average Rand Dollar exchange rate of 7.76.  Despite
higher production and basket prices, revenue was lower at R530 million due to
the negative sales pipeline adjustments, caused by a strengthening of the Rand
at the close of the period compared to the close of the prior quarter.

Operations

Total production increased by 7.1% to 414,240 tons consisting of 407,133 tons
from underground and 7,107 tons from opencast operations.  Open pit operations
were completed at the end of the quarter in-line with the business plan.

Although production from underground operations increased by 23% to 407,133
tons, during the quarter, production was adversely affected by employees
embarking on go-slow industrial action and illegal work stoppages followed by a
number of interruptions which were bonus and pay-related.

On 28 May forty two LHD operators embarked on a stoppage relating to grievances
in respect of pay, joined in sympathy the next day by the remainder of the
underground workforce.  On 3 June the workforce returned to work, following an
agreement between AQPSA management and employee representatives, facilitated by
the NUM, whereby both parties resolved to work together to build a constructive
climate of engagement in the future.  In total, around 2,000 ounces of PGMs was
lost due to this industrial action.

Production was also negatively affected by the fewer number of production days
due to four public holidays during the quarter.  Absenteeism was high following
these public holidays.

As the transition to owner operator progresses, the time and attendance system,
as well as pay systems were improved and related problems were largely
resolved.

No stockpile remained at the end of the quarter.

A total of 418,934 tons were processed during the quarter: 411,827 tons from
underground; 7,107 tons of open pit material.

The head-grade deteriorated by 2.6% to 2.91 g/t. A risk assessment during the
quarter resulted in a decision by management to include the pyroxenite beam in
the face-cut on the northern-side of the mine for safety reasons.  This beam
thins out in the direction of mining and the effect of the additional waste
will reduce as mining approaches the norite hanging wall area.  Mining in the
higher stoping width area of the north bord section was below target resulting
in overall stoping widths not being achieved.  This was the main contributor
for not achieving the target grade.

Recoveries improved from 75% to 80% during the quarter.

PGM production increased marginally by 0.1% to 31,327 ounces.

Everest: Metal in concentrate produced (PGM ounces)

Quarter ended           Pt        Pd        Rh     Au     PGMs (4E)   
                                                                      
Jun 2008              18,777     9,060    3,236    254      31,327    
                                                                      
Mar 2008              18,863     8,912    3,072    259      31,107    
                                                                      
Dec 2007              27,897    13,576    4,877    369      46,719    
                                                                      
Sep 2007              28,890    14,486    5,069    396      48,841    
                                                                      
Operating Cash Costs

Cash costs per ton increased by 40% to R438, whilst costs per PGM ounce
increased by 36% to R5,859.  This was due to the significant increases to the
cost base of all consumable, and the impact of lost shifts due to industrial
action, absenteeism and the lower production units.  Consequently, margins were
lower at 65%.

Everest Operating Cash Costs per PGM Ounce

               4E                6E            6E net of by-products 
         (Pt+Pd+Rh+Au)   (Pt+Pd+Rh+Ir+Ru+Au)          (Ni&Cu)        
                                                                     
Everest     R 5,859            R 4,749                R 4,543        
                                                                     

Capital Expenditure

Capital expenditure for the quarter was R45 million, for ongoing capital.
 Major items included trackless mining equipment (associated with the move to
owner-operator), mining pumps and pump stations, conveyors (both strike and
dip), and portable standby generators.

MIMOSA INVESTMENTS (Aquarius Platinum 50%)

Mimosa Platinum Mine

Safety

The 12-month rolling DIIR improved from 0.41 to 0.18.  Three lost-time injuries
occurred during the quarter.

Mining

Underground production increased by 19% to 497,228 tons

Head grade increased 2% to 3.60g/t

The surface stockpile increased to a total 497,693 tons at the end of the
quarter, equivalent to over 99-days mill feed

Processing

Concentrator plant recoveries increased to 75.9% from 75.1%

Total mine production increased by 12% to 38,517 PGM ounces (Aquarius share:
19,258 PGM ounces)

Successful commissioning of the Wedza Phase V metallurgical plant

Premature breakdown of the Primary Ball Mill  in the older Phase Three milling
circuit negatively affected production

Revenue

The average achieved PGM basket price for the quarter increased by 30% to
$1,607 per PGM ounce.  The average achieved nickel price over the quarter
increased by 2% to $13.17 per pound from $12.92 per pound in the previous
quarter.  Revenue for the quarter increased to $76.3 million, with base metals
accounting for approximately 24% of revenue.  The cash margin increased to 77%
from 70% in the previous quarter.

Operations

During the quarter mining operations hoisted 497,228 tons compared to 419,196
tons in the previous quarter.  Tons milled during the quarter totalled 438,401
tons, with 58,827 being transferred to the stockpile, which totalled 497,693
tons at the quarter end.  In line with plan, the stockpile increased by 58,827
tons.

At Mimosa, the successful commissioning of the Phase 5 metallurgical plant
expansion and the very good performance of mining operations was negatively
impacted by premature equipment failures of the Primary Ball Mill 2 (PBM2) in
the older Phase 3 milling circuit.  The failure of a bearing and the mill end
of the PBM2 (the end was scheduled for replacement in July 2008) necessitated
repairs in South Africa and occurred in the run up to the election run-off. 
The reluctance by engineering service contractors to assist mine personnel
during this time, gave rise to total downtime on the Phase 3 milling circuit
(around 60% of mill capacity) of 38 days, of which 23 days were during the
quarter and 15 days in the first quarter of the 2009 financial year.  The
impact of the mill end failure on Mimosa's production is estimated at 5,550 4E
PGM ounces for the quarter.

The average plant grade marginally increased to 3.60g/t, compared to 3.56g/t in
the previous quarter.

Tons processed totalled 438,401, a 10% increase compared to the previous
quarter, due to Phase V commissioning at the end of the quarter.

Recoveries for the quarter slightly increased to 75.9% from 75.1%.

PGM production during the second quarter increased by 12% to 38,517 ounces
(Aquarius attributable: 19,258.5 ounces).

Mimosa: PGMs in concentrate produced (ounces)

Quarter ended    Pt     Pd    Rh    Au    PGMs  Attributable to Aquarius 
                                                                         
Jun 2008       19,532 14,821 1,535 2,628 38,517          19,258          
                                                                         
Mar 2008       17,392 13,234 1,351 2,306 34,283          17,142          
                                                                         
Dec 2007       19,996 15,216 1,563 2,597 39,372          19,686          
                                                                         
Sep 2007       19,644 14,883 1,517 2,616 38,660          19,330          
                                                                         

Mimosa: Base Metals in concentrate produced (tons)

                  Mine Production           Attributable to Aquarius     
                                                                         
Quarter ended   Ni      Cu       Co         Ni           Cu         Co   
                                                                         
Jun 2008       533      439      15       266.5         219.5       7.5  
                                                                         
Mar 2008       475      392      14       237.5          196         7   
                                                                         
Dec 2007       541      446      15       270.5          223        7.5  
                                                                         
Sep 2007       537      441      16       268.5         220.5        8   
                                                                         

Operating Cash Costs

Total cash costs for the quarter increased to $488 per PGM ounce, a 4% increase
compared to the previous quarter's figure of $471 per PGM ounce.  The increase
in cash costs for the quarter was attributable to the low production
throughput, increased power tariffs and internal inflation pressures which
resulted in increased Zimbabwean dollar denominated costs as the inflation rate
was not in parity with the achieved exchange rate.  The gross cash margin
increased to 77% from 70% in the previous quarter.

Net of by-products, cash costs were negative at $(23) per PGM ounce, compared
to $(1) per PGM ounce in the previous quarter, primarily due to the higher
nickel price.

Mimosa Operating Cash Costs per Ounce

              4E                  6E              4E net of by-products  
         (Pt+Pd+Rh+Au)    (Pt+Pd+Rh+Ir+Ru+Au)                            
                                                      (Ni, Cu & Co)      
                                                                         
Mimosa       $488                $462                     (23)           
                                                                         

Update on Foreign Currency Regime in Zimbabwe

On the 30th of April 2008, the Governor of the Reserve Bank of Zimbabwe issued
a Monetary Policy Statement. Part of the measures announced within this
statement was the liberalisation of the foreign exchange market, whereby
foreign currency trade takes place on a willing-buyer willing-seller basis at
the interbank market.  Mimosa also participates on the inter-bank foreign
currency market and transact at the inter-bank exchange rates to raise local
currency to meet local obligations.

Update on Indigenisation Legislation in Zimbabwe

The Indigenisation and Economic Empowerment Bill was enacted into law during
the last quarter of the financial year.  Specific details on the implementation
of the Act in various sectors of the economy are being awaited.  The details on
the mining sector are proposed to be incorporated into the amendments to the
Mines and Minerals Act which are yet to be brought before Parliament.

Wedza Phase 5 Expansion

Wedza Phase 5 Expansion Project was commissioned in April 2008.The Phase 5 part
of the operations has operated well since commissioning.  Operations are close
to steady-state, subsequent to the repair of the Primary Ball Mill 2.

AQUARIUS PLATINUM (SA) CORPORATE SERVICES (PTY) LTD

Chromite Tailings Retreatment Plant (CTRP) (Aquarius Platinum 50%)

Safety

The DIIR reduced from 5.65 to 5.62 from the previous quarter.  No lost time
accidents were recorded.

Processing

Material processed increased by 10% to 69,618 tons

Grade decreased 29% to 3.25 g/t

Recoveries increased by 15% to 29%.

Production decreased 11% to 2,044 PGM ounces (Aquarius attributable: 1,022 PGM
ounces).

Revenue

Revenue decreased by 17% to R45 million for the quarter (Aquarius attributable:
R22.5 million).  The basket price for the quarter averaged $2,850 per PGM ounce
15% higher than the previous quarter, the average Rand Dollar exchange rate
weakening to 7.76.  The higher basket prices helped to offset lower production,
resulting in the cash margin for the quarter decreasing to 80% from 88% in the
previous quarter.

Operations

Material processed increased to 69,618 tons due to increased feed-rate of
tailings dam material.

The head grade, however, decreased 29% to 3.25 g/t due to treatment of the
lower-grade material in the tailings dam.

Nevertheless, recoveries increased by 15% to 29% due to optimisation of the
mill circuit by increasing the media charge.

This resulted in production decreasing by 11% to 2,044 PGM ounces (Aquarius
attributable: 1,022 ounces).  Although the recovery and throughput increased
during the quarter the decrease in production was a result of treating lower
grade tailings dam material.

Operating Costs

Cash costs increased by 54% to R4,329 per PGM ounce. The increase is a result
of the grinding media being exported from China and R1 million being spent to
increase the stock levels to ensure feed and the purchase of a spare drum for
the Deswik mill at a cost of R350,000.

CTRP Operating Cash Costs per Ounce

             4E                  6E              4E net of by-products   
       (Pt+Pd+Rh+Au)     (Pt+Pd+Rh+Ir+Ru+Au)                                                  
                                (Ni, Cu& Co) 
     
                                                                         
CTRP      R 4,329              R 2,323                  R 2,205          
                                                                         

Platinum Mile (Aquarius Platinum 50%)

The effective date of the acquisition of the 50% interest in Platinum Mile was
1 March 2008. Comments below concern the three month period for the quarter
April to June 2008.  A quarter-on-quarter comparison is therefore not
available.

Safety

The DIIR was zero for the quarter.  No lost time accidents were recorded.

Processing

2,347 million tons were processed

Grade was 0.71 g/t

Production was 5,035 PGM ounces (Aquarius attributable: 2,517 PGM ounces)

Revenue

Revenue at Platinum Mile was R69 million for the quarter (Aquarius
attributable: R34.5 million).  The basket price for the quarter averaged $1,989
per PGM ounce, at an average Rand Dollar exchange rate of R7.76.  The cash
margin for the quarter ended 30 June 2008 was 47%.

Operations

The head grade was 0.71 g/t.  Recoveries were 9%.  This resulted in production
of 5,035 PGM ounces (Aquarius attributable: 2,517 ounces).

Production for the four months, 1 March to 30 June was 7,040 PGM ounces
(Aquarius attributable: 3,520 PGM ounces)

Operating Costs

Cash costs for the quarter were R7,376 per PGM ounce.

Platinum Mile Operating Cash Costs per Ounce

                     4E                6E          4E net of by-products 
               (Pt+Pd+Rh+Au)  (Pt+Pd+Rh+Ir+Ru+Au)                        
                                                        (Ni, Cu& Co)     
                                                                         
Platinum Mile     R 7,376              nm                    nm          
                                                                         

Capital expenditure for the quarter was R4.8 million: R0.2 million for ongoing
capital expenditure and R4.6 million for expansion capital expenditure.  Major
items included capital incurred in expansion of the fine grinding circuit at
the operation.

CORPORATE MATTERS

General Meeting

Subsequent to the period under review, on 16 July 2008, shareholders ratified
both Resolution 1, the ratification of issue of 23,144,000 (per Impala
repurchase) shares and Resolution 2, the ratification of issue of 2,680,854
(per Platinum Mile shares).

Purchase of Stakes of Impala Platinum in both Aquarius Platinum Limited and
Aquarius Platinum South Africa

On 28 April 2008, Aquarius announced the completion of the repurchase of the
21,425,898 common shares (approximately 8.4% of Aquarius' issued share capital)
previously held by Implats for £6.71 ($13.34) per share, representing a total
consideration of £143.8 million ($285 million). These shares have now been
cancelled. In addition, AQPSA repurchased Implats' 20% stake in AQPSA for a
total consideration of $504.9 million; comprising a  cash payment of $459.0
million to Implats and a Secondary Tax on Companies ("STC") charge of $45.9
million, as required under South African tax legislation.

The transactions were funded through a combination of an accelerated book
build, cash and debt.  The completed bookbuild resulted in the issuance of
23,144,000 new common shares of $0.05 each in Aquarius Platinum, at a price of
GBP 800 pence per placing share, raising gross proceeds of approximately $366
million (£185 million). The balance of the transaction was funded through cash
and debt.

AQPSA and ACS(SA) Appointments

Aquarius is pleased to announce three appointments at AQPSA and one at ASACS
during the quarter.

Mr Hulme Scholes, an attorney specialising in mineral rights legislation has
returned to work for AQPSA on a full time basis from the South Africa law firm
Werksmans.  Mr Scholes will continue to hold his seat at the AQPSA Board,
though as an Executive Director.

Ms Hélène Nolte, was appointed at AQPSA Finance Director on 1 July 2008.  Ms
Nolte commenced her career at KPMG where she spent over 9 years, mostly
servicing mining industry clients, her last position being that of Senior Audit
Manager.  She has been involved with AQPSA since 1999 in an audit capacity and
from 2004 in a consulting capacity.

Mr Mkhululi Duka has been appointed to the new position as General Manager of
Human Resources & Transformation.  Mr Duka joins from Petro SA where he was the
Group HR Manager.  His primary focus areas will include human resource
development, policies and procedures, Social and Labour Plans, local economic
development, recruitment and performance management.

In addition, Mr Paul Smith has been appointed to the new position of Director
New Business at Aquarius Platinum (SA) Corporate Services (Pty) Ltd (ACS(SA))
where he will be responsible for a wide remit including strategy and new
business development opportunities.  Paul has abundant experience in mining and
finance, notably at ABSA, African Merchant Bank and BoE-NatWest.

More information on all the corporate matters can be found at
www.aquariusplatinum.com

Aquarius Platinum Limited
Incorporated in Bermuda
Exempt company number 26290

Board of Directors

Nicholas Sibley               Non-executive Chairman 
                                                     
Stuart Murray                 Chief Executive Officer
                                                     
David Dix                     Non-executive          
                                                     
Timothy Freshwater            Non-executive          
                                                     
Edward Haslam                 Non-executive          
                                                     
Sir William Purves            Non-executive          
                                                     
Kofi Morna                    Non-executive          
                                                     
Zwelakhe Mankazana            Alternate to Kofi Morna
                                                     

Audit/Risk Committee                                 
                                                     
Sir William Purves (Chairman)                        
                                                     
David Dix                                            
                                                     
Edward Haslam                                        
                                                     
Nicholas Sibley                                      
 

Remuneration/Succession Planning Committee

Edward Haslam (Chairman)

Nicholas Sibley

 

Nomination Committee

The full Board comprises the Nomination Committee

 

Company Secretary

Willi Boehm

 

AQPSA Management                                                         
                                                                         
Stuart Murray     Executive Chairman                                     
                                                                         
Anton Wheeler     Managing Director                                      
                                                                         
Hélène Nolte      Director: Finance                                      
                                                                         
Willie Byleveld   General Manager: Technical Services                    
                                                                         
Graham Ferreira   General Manager: Group Admin & Company Secretary       
                                                                         
Hugo Höll         General Manager: Projects                              
                                                                         
Mkhululi Duka     General Manager: Group Human Resources & Transformation
                                                                         
Wessel Phumo      General Manager: Marikana                              
                                                                         
Jacques Pretorius General Manager: Everest                               
                                                                         
Gordon Ramsay     General Manager: Metallurgy                            
                                                                         
Rudi Rudolph      General Manager: Kroondal                              
                                                                         
Gabriel de Wet    General Manager: Engineering                           
                                                                         

ACS(SA) Management

Paul Smith Director: New Business
 

Mimosa Mine Management

Winston Chitando                   Managing Director                   
                                                                       
Herbert Mashanyare                 Technical Director                  
                                                                       
Peter Chimboza                     Operations Director                 
                                                                       

Issued Capital

At 30 June 2008, the Company had in issue:

262,052,778 fully paid common shares and 1,680,305 unlisted options

 

Substantial Shareholders 30 June 2008       Number of Shares   Percentage 
                                                                          
Nutraco Nominees Limited                       16,624,749        6.34%    
                                                                          
JP Morgan Nominees Australia Limited           12,543,507        4.79%    
                                                                          

Trading Information

ISIN number BMG0440M1284

ADR ISIN number US03840M2089

 

Broker (LSE) (Joint)           Broker (ASX)          Sponsor (JSE)        
                                                                          
Morgan Stanley & Co            Euroz Securities      Investec Bank Limited
International Limited                                                     
                               Level 14, The         100 Grayston Drive   
20 Cabot Square, Canary Wharf  Quadrant                                   
                                                     Sandown              
London, E14 4QW                1 William Street                           
                                                     Sandton 2196         
Telephone: +44 (0)20 7425 8000 Perth WA 6000                              
                                                     Telephone: +27 (0)11 
Facsimile: +44 (0)20 7425 8990 Telephone: +61 (0)8   286 7326             
                               9488 1400                                  
                                                     Facsimile: +27 (0)11 
                               Facsimile: +61 (0)8   291 1066             
                               9488 1478                                  
                                                                          
                                                                          
                                                                          
Investec Securities Limited                                               
                                                                          
Investec Bank (UK) Limited                                                
                                                                          
2 Gresham Street                                                          
                                                                          
London,  EC2V 7QP                                                         
                                                                          
Telephone: +44 (0)20 7597 5970                                            
                                                                          
Facsimile: +44 (0)20 75975120                                             
                                                                          

Aquarius Platinum (South Africa) (Proprietary) Ltd

67.5% Owned (At 30 June 2008)

(Incorporated in the Republic of South Africa)

Registration Number 2000/000341/07

 

Block A, 1st Floor, The Great Wall Group Building, 5 Skeen Boulevard,
Bedfordview, South Africa 2007

Postal Address    P O Box 1282, Bedfordview, 2008, South Africa.

Telephone:        +27 (0)11 455 2050

Facsimile:        +27 (0)11 455 2095

Aquarius Platinum Corporate Services Pty Ltd

100% Owned

(Incorporated in Australia)

ACN 094 425 555

Level 4, Suite 5, South Shore Centre, 85 The Esplanade, South Perth, WA 6151,
Australia

Postal Address    PO Box 485, South Perth, WA 6151, Australia

Telephone:        +61 (0)8 9367 5211

Facsimile:        +61 (0)8 9367 5233

Email:            info@aquariusplatinum.com

 

Glossary

A$       Australian Dollar                                             
                                                                       
Aquarius Aquarius Platinum Limited                                     
                                                                       
ABET     Adult Basic Education Training programme                      
                                                                       
APS      Aquarius Platinum Corporate Services Pty Ltd                  
                                                                       
AQPSA    Aquarius Platinum (South Africa) Pty Ltd                      
                                                                       
ACS(SA)  Aquarius Platinum (SA) (Corporate Services) (Pty) Limited     
                                                                       
CTRP     Chromite Ore Tailings Retreatment Operation. Consortium       
         comprising Aquarius Platinum (SA) (Corporate Services) (Pty)  
         Limited (ASACS), Ivanhoe Nickel and Platinum Limited and      
         Sylvania South Africa (Pty) Ltd (SLVSA).                      
                                                                       
DIFR     Disabling Injury Incidence Rate - being the number of         
         lost-time injuries expressed as a rate per 1,000,000 man-hours
         worked                                                        
                                                                       
DIIR     Disabling Injury Incidence Rate - being the number of         
         lost-time injuries expressed as a rate per 200,000 man-hours  
         worked                                                        
                                                                       
DME      South African Government Department of Minerals and Energy    
         Affairs                                                       
                                                                       
Dollar   United States Dollar                                          
or $                                                                   
                                                                       
EMPR     Environmental Management Programme Report                     
                                                                       
Everest  Everest Platinum Mine                                         
                                                                       
Great    A PGE bearing layer within the Great Dyke Complex in Zimbabwe 
Dyke                                                                   
Reef                                                                   
                                                                       
g/t      Grams per tonne, measurement unit of grade (1g/t = 1 part per 
         million)                                                      
                                                                       
JORC     Australasian code for reporting of Mineral Resources and Ore  
code     Reserves                                                      
                                                                       
JSE      JSE Securities Exchange South Africa                          
                                                                       
Kroondal Kroondal Platinum Mine or P&SA1 at Kroondal                   
                                                                       
LHD      Load Haul Dump machine                                        
                                                                       
Marikana Marikana Platinum Mine or P&SA2 at Marikana                   
                                                                       
Mimosa   Mimosa Mining Company (Private) Limited                       
                                                                       
MRC      Murray & Roberts Cementation                                  
                                                                       
nm       Not measured                                                  
                                                                       
NOSA     National Occupational Safety Association                      
                                                                       
NUM      South African National Union of Mineworkers                   
                                                                       
PGE(s)   Platinum Group Elements plus Gold.  Five metallic elements    
(6E)     commonly found together which constitute the platinoids       
         (excluding Os (osmium)).  These are Pt (platinum), Pd         
         (palladium), Rh (rhodium), Ru (ruthenium), Ir (iridium) plus  
         Au (gold)                                                     
                                                                       
PGM(s)   Platinum Group Metals plus Gold.  Aquarius reports the PGMs as
(4E)     comprising Pt+Pd+Rh plus Au (gold) with the Pt, Pd and Rh     
         being the most economic platinoids in the UG2 Reef            
                                                                       
P&SA1    Pooling & Sharing Agreement between AQPSA and RPM Ltd on      
         Kroondal                                                      
                                                                       
P&SA2    Pooling & Sharing Agreement between AQPSA and RPM Ltd on      
         Marikana                                                      
                                                                       
R        South African Rand                                            
                                                                       
ROM      Run of Mine.  The ore from mining which is fed to the         
         concentrator plant.  This is usually a mixture of UG2 ore and 
         waste.                                                        
                                                                       
RPM      Rustenburg Platinum Mines Limited                             
                                                                       
SavCon   The Savannah Consortium. The principal Black Empowerment      
         Investor in Aquarius Platinum                                 
                                                                       
TKO      TKO Investment Holdings Limited                               
                                                                       
Ton      1 Metric tonne (1,000kg)                                      
                                                                       
UG2 Reef A PGE bearing chromite layer within the Critical Zone of the  
         Bushveld Complex                                              
                                                                       
Z$       Zimbabwe Dollar                                               
                                                                       

 

For further information please contact:

In Australia:

Willi Boehm

+61 (0)8 9367 5211

 

In the United Kingdom and South Africa

Nick Bias

+ 44 (0)7887 920 530

nickbias@aquariusplatinum.com



END

<< Back


Aquarius Platinum Historical Chart Aquarius Platinum Intraday Chart  
Period
noad


LSE and PLUS quotes are live. NYSE and AMEX quotes are delayed by at least 20 minutes.
All other quotes are delayed by at least 15 minutes unless otherwise stated.
By accessing the services available at ADVFN you are agreeing to be bound by ADVFN's Terms & Conditions :: Contact Us :: Request an Exchange :: Affiliate Scheme
Copyright1999-2008 ADVFN PLC. Copyright and limited reproduction :: Privacy Policy :: Investment Warning :: Advertise with us :: Data accreditations :: Investor Relations :: Press office :: Jobs
ADDITIONAL SERVICES AVAILABLE FROM ADVFN
Upgrade - Click here for more information on ADVFN premium services Money Words - ADVFN Financial Glossary Investor Training ADVFN Financial Bookshop Online Training Academy
30 site:2us 081204 12:17 Stock Message Boards ( 2001 | 2002 | 2003 | 2004 | 2005 | 2005 | 2007 )