Ariana Resources PLC Ariana Resources Plc : First Operational Update - Kiziltepe
January 11 2017 - 2:00AM
UK Regulatory
TIDMAAU
11 January 2017
AIM: AAU
FIRST OPERATIONAL UPDATE - KIZILTEPE
Ariana Resources plc ("Ariana" or "the Company"), the gold exploration
and development company operating in Turkey, provides its first
operational update on the Kiziltepe Mine within the Red Rabbit
Gold-Silver Project in Western Turkey ("Red Rabbit"). Kiziltepe is
being advanced towards production through a 50:50 Joint Venture ("JV")
with Proccea Construction Co. ("Proccea").
Highlights:
-- Process CIL/CIC and ADR* piping and electrical work fully completed, with
the process plant ready for operational start-up; automation works are
continuing.
-- Commissioning of ball mill is complete and wet commissioning of the
process plant is largely complete, with thickener tests due to be
completed this week.
-- Dry commissioning has been completed and the crushers and screens are now
fully operational.
-- Approximately 7,000 tonnes of ore ranging in grade from 2.7 to 0.5 g/t
gold and representing two weeks of production, is stockpiled ready for
the first full-scale tests and start-up.
-- Dam wall complete and installation of geomembrane for Stage 1 Tailings
Storage Facility ("TSF") is largely complete, though currently
experiencing delays due to unprecedented weather conditions.
-- Revisions to our resource and reserve estimates are ongoing following
recent drilling; an improved mining plan and associated scheduling is
underway.
-- Mine site laboratory is now operational with capability for routine Aqua
Regia digests and fire assay.
Dr. Kerim Sener, Managing Director, commented:
"Following a productive site visit conducted in the last few days, we
are very encouraged to report that the Kiziltepe Mine is now largely
operational, following the successful completion of major construction
in December. Dry and wet commissioning of the process plant, including
the CIL tanks and thickeners, is almost complete, although deteriorating
and unprecedented weather conditions during the latter part of December
and in to January have now delayed completion of the TSF. The
conditions being encountered at site have ranged from very wet weather
in late December to sub-zero temperatures and heavy snowfall in early
January, which have negated the laying of the final geomembrane for the
Stage One TSF, which comprises only another two weeks of work. Previous
guidance provided by the Company had indicated that Kiziltepe was likely
to become operational in late December but the timing of start-up has
now been necessarily postponed due to the conditions at site. As the
TSF completion is a critical path component of the project, we cannot
provide further guidance on formal start-up until the weather clears and
the conditions for laying geomembrane improve. In particular, the
temperatures for laying geomembrane must exceed five degrees Centigrade.
In the meantime, our teams are working on all other operational aspects
to ensure a smooth transition in to production once the TSF is able to
be completed. We will provide a further update on project progress
before the end of January.
The Company is also advancing work programmes on its other projects to
enhance its future production profile once Kiziltepe enters production
and we look forward to updating the market on this activity in due
course."
* CIL - Carbon-in-Leach; CIC - Carbon-in-Column; ADR -
Adsorption-Desorption-Recovery
Figure 1: View of the Kiziltepe process plant showing the completed
CIL/CIC and ADR plant, taken from the site of the ball mill. The
pipeline from the ball mill to the thickeners (in the foreground) is
completed.
Link: http://hugin.info/138153/R/2070388/777898.pdf
Figure 2: View of the CIL tanks within the completed CIL/CIC and ADR
plant. All components within the process plant, including the ADR
system have been individually tested. Full system commissioning is due
to commence shortly.
Link: http://hugin.info/138153/R/2070388/777899.pdf
Figure 3: View of the fully operational ball mill. Testing of the ball
mill is complete and piping of slurry to the thickeners will occur
during the week.
Link: http://hugin.info/138153/R/2070388/777900.pdf
Figure 4: View of the TSF location looking towards the dam wall. Two
feet of snow has obscured the facility and inhibits the laying of
remaining geomembrane.
Link: http://hugin.info/138153/R/2070388/777901.pdf
This announcement contains inside information for the purposes of
Article 7 of EU Regulation 596/2014.
Contacts:
Ariana Resources plc Tel: +44 (0) 20 7407 3616
Michael de Villiers, Chairman
Kerim Sener, Managing Director
Beaumont Cornish Limited Tel: +44 (0) 20 7628 3396
Roland Cornish / Felicity Geidt
Beaufort Securities Limited Tel: +44 (0) 20 7382 8300
Jon Belliss
Panmure Gordon (UK) Limited Tel: +44 (0) 20 7886 2500
Adam James / Tom Salvesen
Editors' Note:
About Ariana Resources
Ariana is an exploration and development company focused on epithermal
gold-silver and porphyry copper-gold deposits in Turkey. The Company is
developing a portfolio of prospective licences originally selected on
the basis of its in-house geological and remote-sensing database.
The Company's flagship assets are its Kiziltepe and Tavsan gold projects
which form the Red Rabbit Gold Project. Both contain a series of
prospects, within two prolific mineralised districts in the Western
Anatolian Volcanic and Extensional (WAVE) Province in western Turkey.
This Province hosts the largest operating gold mines in Turkey and
remains highly prospective for new porphyry and epithermal deposits.
These core projects, which are separated by a distance of 75km, form
part of a 50:50 Joint Venture with Proccea Construction Co. The
Kiziltepe Sector of the Red Rabbit Project is fully-permitted and is
nearing start-up. The total resource inventory at the Red Rabbit
Project and wider project area stands at c. 525,000 ounces of gold
equivalent.
In north-eastern Turkey, Ariana owns 100% of the Salinbas Gold Project,
comprising the Salinbas gold-silver deposit and the Ardala
copper-gold-molybdenum porphyry among other prospects. The total
resource inventory of the Salinbas project area is c. 1 million ounces
of gold equivalent.
Beaufort Securities Limited and Panmure Gordon (UK) Limited are joint
brokers to the Company and Beaumont Cornish Limited is the Company's
Nominated Adviser.
For further information on Ariana you are invited to visit the Company's
website at www.arianaresources.com.
Ends
Figure 4: http://hugin.info/138153/R/2070388/777901.pdf
Figure 2: http://hugin.info/138153/R/2070388/777899.pdf
Figure 3: http://hugin.info/138153/R/2070388/777900.pdf
Figure 1: http://hugin.info/138153/R/2070388/777898.pdf
This announcement is distributed by Nasdaq Corporate Solutions on behalf
of Nasdaq Corporate Solutions clients.
The issuer of this announcement warrants that they are solely
responsible for the content, accuracy and originality of the information
contained therein.
Source: Ariana Resources plc via Globenewswire
http://www.arianaresources.com/s/Home.asp
(END) Dow Jones Newswires
January 11, 2017 02:00 ET (07:00 GMT)
Copyright (c) 2017 Dow Jones & Company, Inc.
Ariana Resources (LSE:AAU)
Historical Stock Chart
From Mar 2024 to Apr 2024
Ariana Resources (LSE:AAU)
Historical Stock Chart
From Apr 2023 to Apr 2024