TIDMAMC

RNS Number : 4395R

Amur Minerals Corporation

29 June 2015

29 June 2015

AMUR MINERALS CORPORATION

(AIM: AMC)

Operational Blueprint Defined For Kun-Manie

Amur Minerals Corporation ("Amur" or the "Company") is pleased to present the forward looking Operational Blueprint ("Blueprint") for the development of the Kun-Manie nickel copper sulphide project located in the Russian Far East. The optimised design has been derived from the combination of an extensive Company generated update to the 2007 SRK Consulting Ltd ("SRK") Pre Feasibility Study ("PFS") and the consideration of the terms and conditions as contained within the newly acquired "Detailed Exploration and Production Licence" (the "Licence").

Highlights of the Operational Blueprint include the following:

-- Existing resources can sustain a 15 year production period where 6.0 million tonnes per annum are produced. Infill drilling will be required.

   --     Mine production will be derived from four open pits and two underground operations. 

-- A simple flotation concentrate will be generated which can be smelted by the Company owned smelter as verified by Outotec.

   --     The project has an estimated operating cost per ore tonne of $US 34.86 per ore tonne. 

-- The total initial capital expenditure is projected to be $US 1.38 billion to be expended in a two year construction period. Sustaining capital is estimated to be $US 474 million over 15 years.

-- The Net Present Value ("NPV") using a 10% discount rate is projected to be $US 0.71 billion and $US1.44 billion using the long term nickel prices of $US 7.50 per pound and $US 9.50. per pound These economic projects cover an owner operated smelter and refinery.

The Blueprint establishes an operational plan for the comprehensive beneficiation of the sulphide ores from mining through the sale of final metal products generated by a Company owned smelter / refinery on the international market. Definition of the Blueprint included various trade off sensitivity studies that identified the most profitable configuration for Kun-Manie. From the plan, the operational configuration, technical operating parameters, operating and capital cost expenditures as well as pro forma cash flow projects have been established by the Company. The results will be independently audited by one of three shortlisted western mining consultancies possessing Russian experience.

Robin Young, CEO of Amur Minerals Corporation, commented:

"This Operation Blueprint contained within our PEA, represents ten years of successful exploration at Kun Manie, along with a total redesign of the project. As we worked on the study, we challenged all past and previous assumptions. As a result, mining will best be performed using a combination of underground and open pit productions, power will be generated on site, a substantial access road upgrade can be supported and the construction of own smelter and refinery.

"These choices make a tremendous difference to the bottom line, which we measure in global project NPV. Moving forward through infill drilling, metallurgy and more detailed engineering studies, we will continue to search for ways to optimise the project so that it delivers the highest possible value to the shareholders. We are comfortable with the final values we have generated as a Company, however, we are compiling a Request for Proposal from three independent companies."

Enquiries:

 
    Company        Nomad and Broker    Public Relations 
  Amur Minerals       S.P. Angel         Yellow Jersey 
      Corp.        Corporate Finance 
                          LLP 
  Robin Young                          Dominic Barretto 
       CEO            Ewan Leggat       Kelsey Traynor 
                      Katy Birkin 
  +44 (0) 7981        +44 (0) 20          +44 (0) 77 
     126 818           3470 0470          99 003 220 
 

Notes to Editors

The information contained in this announcement has been reviewed and approved by the CEO of Amur, Robin Young. Mr. Young is a Geological Engineer (cum laude) and is a Qualified Professional Geologist, as defined by the Toronto and Vancouver Stock Exchanges.

For further information, see the Company website at www.amurminerals.com.

Long Term Operational Blueprint

In 2014, the Company initiated an internal evaluation and update of the 2007 SRK Consulting Ltd ("SRK") Pre Feasibility Study ("PFS"). A substantial amount of technical data had been acquired since the 2007 PFS was issued, including the increase in the resource base through step out drilling and the discovery of two new deposits. The first conclusion derived from the update was that the additional resource could support a 20 year mine life producing at a nominal production rate of 4.0 million tonnes per year. This work confirmed that infill drilling should take priority over resource expansion, which also remains highly prospective.

In mid-2014, the PFS update was under executive review and prepared for release when two events impacted the quality of the study, placing its release on hold.

-- Economic sanctions placed against the Russian Federation required a reassessment of the equipment selection by identifying alternatives from within Russia and from sources outside the sanctions bloc.

-- A rapid devaluation of the Russian Rouble impacted the quality of all operating costs and selected capital equipment estimates. This especially disrupted the projections related to labour costs. The devaluation was so significant that it invalidated significant portions of the study.

During Q3 and Q4 2014, the Company continued to update the study information where possible whilst monitoring the Rouble exchange rate. By February 2015, the Rouble had stabilised and the Company resumed its update of the study, which included a key change in scope. In Q4 2014, the terms and conditions for the Production Licence were negotiated (though final approval was still pending) with a 20 year Production Licence life being established. As a result, the Company increased the annual nominal throughput from 4.0 million to 6.0 million tonnes. It was determined that the existing resource inventory could support the increase as well as sustain a total production of 90 million tonnes for a 15 year mine life.

Another key decision was undertaken by management wherein a longer term vision of the operation was implemented. This called for the development of an 'Operational Blueprint' of an optimised conceptual design, providing for a fully integrated operation that will produce a substantially improved financial assessment for Kun-Manie. By doing so, a series of trade off studies were identified wherein each step of the proposed operation could be optimised. In June 2015, the Operational Blueprint and the associated economic evaluation were completed.

It is important to note the reasons that the Company is restricted from specifically identifying its work as a PFS by JORC standards and therefore considers the results to be at a PEA level. There are three primary reasons for this use of the study as a PEA. Firstly, the project analysis included Inferred resource as reserves, portions of the work and results were derived internally by the Company, although much of the work is based on external results compiled by qualified specialist companies and our CEO, Mr. Robin Young is a licenced professional geologist provided substantial input to the document which could be considered to be a conflict of interest. Until the PEA has undergone independent audit, the Company cautions the shareholder that there are forward looking statements which could vary substantially from results obtained in the future. Presently, the Company has shortlisted three internationally recognised mining consultancies to complete the audit of the PEA which contains new information and identifiable changes from 2007 allowing the Company to update its strategy in a way that can significantly enhance the long-term economics of mining at Kun Manie. Pressing ahead without consideration of important new data could sacrifice profitability for short savings of time, a trade-off the Company could not have justified to its shareholders.

The Proposed Operational Blueprint

The PEA has established the Operational Blueprint for the Kun-Manie nickel - copper sulphide project. The indicated scale of the project supports the conclusions that it will be a substantial producer, placing the Company among some of the world's larger nickel miners. The integrated Operational Blueprint for Kun-Manie includes the following:

-- Power for the site will be generated using diesel fuelled generators, typical of remote Russian operations. The capital cost for site-generated power is substantially less than that required to construct a 360 kilometre long power line, estimated by the utility company to range from US$800,000 to US$1,000,000 per kilometre. Conversely, operating costs will be higher than with power delivered through a grid. This is a substantial change from 2007, when the local utility stated that the power line would be constructed at its expense. This is no longer the case. Power generation alternatives such as wind, hydroelectric, etc. could augment the power needs on site and shall be further investigated.

   --     To support the additional needs to provide power at the site, the access road design will be substantially upgraded by widening it to handle two-way traffic on a year round basis. This requires additional road maintenance equipment and is substantially higher than previous capital cost estimates related to construction of the 320 kilometre long access road. 
Amur Minerals (LSE:AMC)
Historical Stock Chart
From Mar 2024 to Apr 2024 Click Here for more Amur Minerals Charts.
Amur Minerals (LSE:AMC)
Historical Stock Chart
From Apr 2023 to Apr 2024 Click Here for more Amur Minerals Charts.