TIDMAMER

RNS Number : 6941D

Amerisur Resources PLC

02 February 2015

02 February 2015

Amerisur Resources Plc

Revised 2015 Plan, Outlook and Guidance Statement

Amerisur Resources Plc ("Amerisur" or the "Company"), the oil and gas producer and explorer focused on South America, is pleased to provide a 2015 update to shareholders in the context of the WTI oil price, currently at approximately $48.

Highlights:

2015 plan

-- Given the prevailing oil price and a conservative oil price assumption for 2015, and whilst the Company waits for the commissioning, construction and operation of the Ecuador interconnector, the Board has decided to optimise production from the Company's low lifting and transportation cost platforms in the Platanillo field

-- 4,500 bopd to be produced in the interim from Pads 5 and 9, which can be lifted at a cost of approximately $12 per barrel and transported and commercialised through Orito and the OTA system at approximately $12 per barrel

-- Production from more expensive pads to be temporarily suspended and transportation to Rio Loro at a cost of $23 per barrel to be reduced to a nominal daily volume, so preserving this delivery option

-- Production is expected to be increased to a 2015 exit rate of 8,200 bopd once the pipeline to Ecuador is operational and delivering transportation costs of under $5 per barrel. This is expected by the start of H2 2015

-- Production is expected to be increased through 2016, as pipeline capacity further increases and expected sales prices improve

-- Capital expenditure guidance for 2015 revised to approximately $45 million from $95 million, fully funded from operating cashflow and cash resources

   --      3 exploration wells to be drilled in 2015 

o Platanillo 21 and 22

o Putumayo 12 first exploration well to be spudded in December 2015

2014 highlights

-- 2014 average production of 6,242 barrels of oil per day ("bopd"), up 32% (2013 average production: 4,730 bopd)

   --      2014 year end cash position $96MM 

Revised 2015 WTI oil price assumptions

Base case assumptions

The Board has taken a conservative view on oil price assumptions for 2015, where broker forecasts for the 2015 oil price range from $46 to $67.5, and are thus using a WTI oil price assumption of $48 per barrel for 2015 and $65 for 2016.

In this context the Board has conducted a review of the 2015 plan, with the aim of minimising the use of high cost transportation until such time as the pipeline to Ecuador is operational, and / or a rapid return to a higher oil price, thus protecting the Company's balance sheet and highly valuable reserve base.

Due to reductions in production implemented by other operators in the area, available discharge volume at Orito has increased thus allowing the Company to take advantage of this increased available capacity. For example, over the last 7 days the Company has delivered an average of 4,200 bopd into the Orito facility, compared to an average of 2,358 BOPD in December 2014

As a result the Company has suspended production from higher cost pads where transportation, lifting and royalties would be close to the current oil price and will produce approximately 4,500 bopd from Pads 5 and 9, which can be lifted at a cost of approximately $12 per barrel and transported through Orito at a cost of approximately $12 per barrel. Rio Loro transportation at a cost of $23 per barrel has been reduced to a nominal daily volume in order to create strong netback benefits while ensuring the delivery facility is maintained. The suspension implemented at Pads 3 and A can be quickly reversed and that production brought on stream at any moment should sales prices increase or costs reduce.

Amerisur has also made significant progress in the reduction of field operating costs, with important discounts being obtained from contractors and other suppliers. The Company expects to continue with those efforts, bringing tariffs to levels significantly lower than those of 2014.

It is the Company's intention to increase production once the export pipeline to Ecuador is in operation, projecting an exit rate for 2015 of 8,200 bopd. The transportation costs through the pipeline are expected to be below $5 per barrel creating a strong positive effect on netback on the increased production.

Pipeline update

Permissions are moving forward, and the Operation Letter of Intent (LOI) with PetroAmazonas, the Operator of the Cuyabeño gathering system is expected to be signed this week and the Board is confident it will be in a position to commission, construct and operate the Ecuador interconnector in H1 2015. The delay in the delivery of the pipeline is mainly due to an expansion of the technical scope of the project, which now contemplates a 10.8" line over its entire length, reaching dedicated reception facilities at the central VHR production station. In this way the need to utilise an existing 6" flow line from platform VHR-21 is avoided, and full capacity can be utilised without further investment or engineering works. This technical scope has been approved by the Operator for simultaneous operations. All required materials and services have now been sourced and as such we are confident the system can be delivered by H2 2015.

2015 capex guidance

The Company has reviewed in detail its capital expenditure for 2015 in the context of the lower oil price environment and has revised its guidance from $95 million to $45 million, which is fully funded from operating cashflow and cash resources. This sum includes all one-off costs associated with the construction and commissioning of the Ecuador export line. The revised 2015 exploration and development drilling and seismic plan is designed to maximise the chance of success by controlling risk. The key components of the forward programme into 2015 are as follows:

Platanillo (AMER 100% and Operator)

   --      Construct, commission and operate Ecuador interconnector H1 
   --      Completion of 3D seismic on Platanillo North (northern 25% of the block) 

-- Suspend Libelula-1 following mechanical problems at 7,850ft. It is expected the Company will re-enter this well in 2016

-- Release the current rig (D-10) pending the results of this seismic and defer drilling of Platanillo-21 and 22 until the complete seismic data is available

-- The Company believes that drilling opportunities north of the Piñuna Blanca river can be made more diverse and lower risk following incorporation of the new, additional 3D seismic data and that rig and service rates will be significantly lower in the second half of 2015, when a rig will be contracted to continue the Platanillo drilling programme

-- In H2 2015 drill two wells in Platanillo North - locations of these wells will be defined by the new Platanillo North 3D data

   --      Install efficient Horizontal Electrical Hydraulic Lifting systems on Pads 5 and 9 

-- Construct a 10,000BO storage tank at Pad 5 to increase flexibility in the production system and further reduce lifting costs

   --      Purchase rented production equipment at Pad 5 

-- The mean prospective resources targeted by the 2015 Platanillo drilling programme will be defined once the 3D seismic programme is completed

   --      Estimated total Platanillo 2015 capex is $37m 

Putumayo 12 (AMER 60% and Operator)

-- Complete Put-12 2D seismic, prioritizing the western structures, which can be more rapidly licensed, drilled at lower costs and monetized more rapidly than the more distant eastern structures

-- Commencement of drilling programme; first target is Lead 1 similar in seismic terms to Platanillo and targeting mean prospective resources of 106.6 MMBO to be spudded in December 2015

   --      Estimated total Putumayo 12 2015 capex is $7m 

Putumayo 30 (AMER 50%)

   --      Commencement of 2D seismic programme covering 209km in early 2016 
   --      No capex is expected in Putumayo 30 during 2015 

Paraguay (AMER 100% and Operator)

   --      Defer Jaguarete-1 to 2016 or sooner should WTI recover to $85/bbl (under negotiation) 
   --      No capex is expected in Paraguay during 2015 

Fenix (AMER 100% and Operator)

   --      Defer Fenix drilling and conduct a strategic review of benefits of maintaining interest 

The purpose of this programme is to protect all of the Company's assets, whilst maintaining its exploration programme and guaranteeing positive operational cashflow at low oil prices. The programme is totally scalable in the event of a return to higher oil prices when relatively higher cost production can be brought back on stream very rapidly.

John Wardle, CEO of Amerisur commented:

"We have changed the 2015 plan in a responsible way ensuring a high probability of delivery and securing a platform with good upside potential. Importantly the main actions and savings can be implemented immediately. This plan maximises operational netback and gives flexibility in the case of a further sales price drop, while allowing production to be ramped up quickly once the pipeline becomes operational and / or sales prices rise. We have in effect deferred production of 500,000 barrels of oil; however the deferment period will be less than 12 months. This will have a positive impact on the Platanillo field NPV should prices recover more than the discount rate. The future period, though challenging, will I believe offer us an exciting opportunity to re-set our operating costs to extremely efficient levels, which will have strong positive impact on our results going forward as we continue to develop our exciting, highly prospective and diverse opportunity set."

Giles Clarke, Chairman of Amerisur said:

"Amerisur is a strong, profitable, well financed Company, with an exploration programme in 2015 which exposes our shareholders to significant upside. The 2015 plan is firmly directed at profitable activities to place the Company in a position to exploit all opportunities that may arise as market values become less volatile."

A presentation providing further detail can be found on the website http://www.amerisurresources.com/reportspresentations.html.

ENDS

Competent person: Technical information in this announcement has been reviewed by John Wardle Ph.D., the Company's Chief Executive. John Wardle has 28 years' experience in the industry, having worked for BP, Britoil, Emerald Energy and Pebercan, and is a trained drilling engineer.

ENQUIRIES:

 
Billy Clegg/Georgia Mann  Tel: +44(0)203 757 4980 
Camarco 
Jeremy Low/Daniel Conti   Tel: +44 (0)207 653 4000 
RBC Capital Markets 
Chris Sim                 Tel: +44 (0)207 597 4000 
Investec 
 

This information is provided by RNS

The company news service from the London Stock Exchange

END

MSCFMGGZVMZGKZM

Amerisur Resources (LSE:AMER)
Historical Stock Chart
From Mar 2024 to Apr 2024 Click Here for more Amerisur Resources Charts.
Amerisur Resources (LSE:AMER)
Historical Stock Chart
From Apr 2023 to Apr 2024 Click Here for more Amerisur Resources Charts.